Download presentation
Presentation is loading. Please wait.
1
Contents Introduction Requirements Engineering Project Management
Software Design Detailed Design and Coding Quality Assurance Maintenance PVK-HT05
2
Project Management Project Management Activities Project Scheduling
Cost Estimation PVK-HT05
3
Project Management Activities
Project acquisition Project planning Resource assessment Risk and option analysis Cost estimation Project scheduling Work breakdown structure Effort distribution Resource assignment Project tracking and control Reporting PVK-HT05
4
Project Resources People Hardware and software tools Required skills
Availability Duration of tasks Start date Hardware and software tools Description Duration of use Delivery date PVK-HT05
5
Risk Analysis What is a risk?
Risk impact: the loss associated with the event Risk probability: the likelihood that the event will occur Risk control: the degree to which we can change the outcome Risk exposure = (risk probability) x (risk impact) PVK-HT05
6
Top Ten Project Risks Staff deficiencies
Unrealistic schedules and budgets Developing the wrong functions Developing the wrong interface Over-engineering Changing requirements Externally developed items Externally performed tasks Performance problems Assumptions on technology PVK-HT05
7
Define Work Breakdown Structure
Activity Major work unit Start date End date Consumes resources Results in work products (and milestones) Project function Continue throughout the project Not bound to specific phases Step 1 Step 2 Activity 1 Activity 2 Activity 3 Phase 1 Step 1 Step 2 Activity 1 Activity 2 Task 1 Task 2 Task 3 Project Phase 2 Step 1 Step 2 Phase N PVK-HT05
8
Schedule Activities Almost all activities depend on the completion of some other activities Many activities can be performed in parallel Organisation necessary to balance work-load, costs, and duration PERT chart (activity network/task graph) Critical path Project Time-line (Gantt chart) Resource table PVK-HT05
9
PERT Charts Program Evaluation and Review Technique Graph Compute
Nodes = activities/tasks and estimated duration Edges = dependencies Compute Slack time = available time - estimated duration Critical path A path is critical when it contains an activity that, if delayed, will cause a delay of the whole project. PVK-HT05
10
Example PERT Chart PVK-HT05
11
Gantt charts A Gantt chart is used to graphically present the start and end dates of each software engineering task One axis shows time. The other axis shows the activities that will be performed. The black bars are the top-level tasks. The white bars are subtasks The diamonds are milestones: Important deadline dates, at which specific events may occur PVK-HT05
12
A Gantt Chart (Project Time Line)
PVK-HT05
13
Another Gantt Chart PVK-HT05
14
Cost Estimation Approach Problems: Use empirical and historical data
Decompose problem Check for experiences/ data on sub problems Make qualified estimations (Make at least two independent estimates) Problems: What are good measures? Do the estimates affect the result? Does the type of software affect the result? Does the project environment affect the result? ... Use empirical and historical data Algorithmic cost modelling COCOMO (based on LOC) FP (based on function points) PVK-HT05
15
COCOMO Constructive Cost Modelling [Boehm 81]
Based on publicly available historical data of 63 TRW projects Basic assumptions: Requirements change only slightly during the project There is good project management The historical data is representative Assigning more resources to the project does NOT result in linear decreasing development time PVK-HT05
16
Basic Model Effort = a (KDSI)b Schedule = c (Effort)d a b c d 2.4
KDSI = Kilo Delivered Source Instructions ( LOC - comments) The a, b, c, and d factors vary depending on the type of project Effort is measured in PM (Person Months = 152h of work) Schedule is the Development Time measured in Months a b c d 2.4 3.0 3.6 1.05 1.12 1.20 2.5 0.38 0.35 0.32 Organic In-house IS, Development in a familiar environment OM: Organic Mode projects Small teams which are familiar with the type of application with low communication overhead Development in a familiar environment EM: Embedded Mode projects Large and inexperienced teams Many constraints are those that develop complex hardware software systems. Experience level is low since most projects are one of a kind. SDM: Semi Detached Mode projects Between OM- and EM projects are those projects made up of experienced and inexperienced staff. Organic Familiar environment, small team of experienced programmers are main characteristics of organic mode projects. For example, a personnel system project for an organization which is located on a single building with Local Area Network facilities only. Semi Detached Semi-detached mode projects are intermediate projects between organic mode and embedded mode. Such projects partially shows both characteristics. For example, a software project for a large bank, including daily customer operations and the ATM machine activities on a Wide Area Network can be considered as of type semi-detached.. Embedded In the embedded mode, projects has tight constrains, more than one processor and various types of peripherals exist. Uncertainties in the problem definition is another characteristics of such projects. Hardware driving projects are good examples of embedded types. For example, a software project related to control the production of various automobile parts is of embedded type. Effort PM: Person Months 2.4 (KDSI)1.05 for OM projects 3 (KDSI)1.12 for SDM projects 3.6 (KDSI)1.20 for EM projects TDEV: Time for DEVelopment 2.5 (PM)0.38 for OM projects 2.5 (PM)0.35 for SDM projects 2.5 (PM)0.32 for EM projects N: Number of personnel PM / TDEV Semi-detached Between OM- and EM projects Embedded Large and inexperienced teams, many constraints PVK-HT05 Boehm, Software Engineering Economics, Prentice-Hall, 1981.
17
COCOMO Summary Works quite well in practice Needs KLOC as input
Problems: Estimating KLOC in early project stages Comparison of projects using different LOC counts Outdated metrics base (70s) Solutions: Cross-check using an other estimation technique Standardised LOC counts Continuous model calibration COCOMO II is a recent new version PVK-HT05
18
COCOMO II Goal: To develop a software cost and schedule estimation model tuned to the life cycle practices of the 1990’s and 2000’s 3 Models Application Composition: prototyping to resolve high-risk user interface issues, 2 environment drivers, 0 process drivers, Sizing in Object Points Early Design Model: to explore alternative architectures and concepts,7 environment drivers, 5 process drivers, Sizing in Function Points or SLOC Post Architecture Model: development has begun, 17 environment drivers, 5 process drivers, Sizing in Function Points or SLOC Why ? allow for spiral model instead of waterfall model only Use FP and LOC for Sizing Assumptions COCOMO II includes same activities as COCOMO 81 development activities are included: documentation, planning& control, software configuration management (CM) excluded: database management, general CM, Management COCOMO II has add-on effort for back-end Transition Phase (conversion, installation, training) Labour categories: direct project-charged + overhead (e.g. project mgr), but not secretaries, higher management, computer centre operators, ... PVK-HT05
19
Effort and schedule in COCOMO 2
Application Composition Model Effort = NOP/productivity NOP = OP * [(100 -%reuse)/100] Productivity = NOP/man-months, 5 productivity levels depending on the 2 environment drivers (table 3.12 course book) Early Design and Post-architecture Model æ ö Environment [ ] ( ) Factors Scale Process Effort = ç ÷ Size ç ÷ Multipliers è ø Environment: product, platform, people, project factors Process: constraint, risk/architecture, team, maturity factors ( ) [ ] Effort ( ) Factors Scale Process Schedule = Multiplier PVK-HT05
20
COCOMO II Model Stages Overestimated Underestimated
4x Overestimated 2x Early Design (13 parameters) 1.5x 1.25x Relative Size Range x 0.8x Post-Architecture 0.67x (23 parameters) 0.5x Underestimated Applications Composition (3 parameters) 0.25x Product Detail Concept of Rqts. Design Design Accepted Operation Spec. Spec. Spec. Software Feasibility Plans Product Detail Devel. and Design Design and Test Rqts. PVK-HT05 Phases and Milestones
21
COCOMO II summary COCOMO II
allow for spiral model instead of waterfall model only Size of project can be listed as object points, function points or source lines of code (SLOC) The environmental multipliers are calculated from seventeen cost drivers better suited for today's methods Calibration is difficult, but can improve accuracy by a factor of five Problems with CoCoMo II Not developed for Web apps Estimates driven by SLOC count PVK-HT05
22
Function Points Function Point Analysis (FPA) measures the size of a software product in terms of the functionality it delivers to the users. A.J. Albrecht 1979 What the software must do from the user’s perspective Irrespective of software construction Based on five function types: Inputs Outputs Inquiries Logic Files Interfaces PVK-HT05
23
Project plan contents Documentation plan Project scope
Data management plan Resource management plan Test plan Training plan Security plan Risk management plan Maintenance plan Project scope Project schedule Project team organization Technical description of system Project standards and procedures Quality assurance plan Configuration management plan PVK-HT05
24
Difficulties and Risks in Project Management
Accurately estimating costs is a constant challenge It is very difficult to measure progress and meet deadlines It is difficult to deal with lack of human resources or technology needed to successfully run a project Communicating effectively in a large project is hard It is hard to obtain agreement and commitment from others PVK-HT05
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.