Copyright © 2003 Americas’ SAP Users’ Group Use of Impress SAP-P3 Interface for Projects – Session 3804 Stuart Graham, Halliburton Process Lead - Project Systems Monday, May 19, 2003
2
Topics Halliburton Company Why SAP-P3 Interface and Why Impress Pilot Project Interface Requirements Design Issues and Solutions Impress Interface Process OpenPS Comparison Future Development Open Discussion
3
Halliburton Company Merger of Halliburton and Dresser Companies Two Global Business Units Halliburton Energy Services Group - Oil Field Services Kellogg / Brown & Root - Engineering and Construction $15 Billion Annual Revenue 80,000 Employees / 120 Countries SAP Global Instance – 4.6c 17,000 SAP Users World-wide / 4,000 Concurrent users
4
Need for SAP P3 Interface SAP Strengths: Integrated Operational Environment Cost Accounting Limitation: Scheduling Scheduling Process Cumbersome Capacity Planning Very Cumbersome Inadequate Schedule Reporting Managing Contractor Projects SAP Strengths: Integrated Operational Environment Cost Accounting Limitation: Scheduling Scheduling Process Cumbersome Capacity Planning Very Cumbersome Inadequate Schedule Reporting Managing Contractor Projects Primavera P3 Powerful Scheduling Tool Good Schedule Reporting Primavera P3 Powerful Scheduling Tool Good Schedule Reporting
5
Why iMPRESS Pilot Project? Impress Partnership with SAP / Primavera SAP Application Server SAP Connector Impress Server IMPRESS Middleware Configuration Database P3 Connector Primavera P3 Local Application Configurability Versatility Expandability (P3e, MS Project….) Configurability Versatility Expandability (P3e, MS Project….) Objective – Deliver Robust, Out-of-Box Product Impress Collaboration Engine
6
Interface Requirements Complex Environment Multiple Collaboration Scenarios Complex Project Controls Environment System Mapping P3 Activity 10-character Limitation Multiple SAP Object Mapping Exclusion / Aggregation Mapping Many to 1 Mapping (P3 to SAP / SAP to P3) Resource Mapping (Planned and Actual)
7
Project Scenarios ‘Simple’ Projects: SAP – P3 Congruent Large, Multi-Site Projects: Multiple P3 Projects – One SAP Project SAP P3 SAP Eng P3 Const P3
8
Project Scenarios Managing Contractor Projects: Large P3 – One SAP Project (subset) SAP P3
9
Projects Scenarios Construction / Fabrication Projects: Multiple SAP Projects – One P3 Project P3 E P C SAP Fabrication SAP * Multiple Project Resource Planning
10
Projects Scenarios Plant Shutdown Projects: Project Systems and Plant Maintenance Plant Maintenance Contract on Owner’s SAP: PM Orders Only PM SAP PM P3 SAP PM Net P3
11
SAPP3 Project Controls Environment Schedule – Cost Breakdown P3 Proposal to SAP Operational Project Differing Company Naming Conventions / Processes Schedule / Cost Integration Different Objectives / Perspectives Different Levels of Detail Schedule Cost Work Package Matchpoint Exclusion 2 Dynamic Environments How do you Avoid data Corruption? 2 Dynamic Environments How do you Avoid data Corruption? XXXXXXXX XXXXXXXX Grouping / Summing
12
Topics Halliburton Company Why SAP-P3 Interface and Why Impress Pilot Project Interface Requirements Design Issues and Solutions Impress Interface Process Design Issues and Solutions Impress Interface Process OpenPS Comparison Future Development Open Discussion OpenPS Comparison Future Development Open Discussion
13
Design Tools Design Objectives Efficiency Flexibility Design Toolbox Collaboration Project Global Parameters Exception Overrides: P3 Custom Code Fields / SAP User Fields Data Transfer: Synchronization Action Types (SAT)
14
Design Solutions P3 Activity Mapping P3 10-character Activity SAP Network / Activity / element (12, 4, 4- characters) Solution Global Parameter – Default Network Prefix SAP (TE5001C100PI 0010) Prefix (TE5001) P3 (C100PI0010) Overrides P3 Custom Data Fields (to SAP) SAP User Field (to P3) Solution Global Parameter – Default Network Prefix SAP (TE5001C100PI 0010) Prefix (TE5001) P3 (C100PI0010) Overrides P3 Custom Data Fields (to SAP) SAP User Field (to P3)
15
Design Solutions Multiple SAP Object Mapping Network / PM Order Activity / Activity element Subnetwork Multi-Plant (Company) Solution Global Network Type (Project Profile/Network Profile) P3 Custom Data Fields Order Type Override (Plant, MRP Controller, Order Type) Activity Type, Superior Activity, Subnetwork I, E, S, P, X (Internal, Preq, Service, Primary, Exclude) Solution Global Network Type (Project Profile/Network Profile) P3 Custom Data Fields Order Type Override (Plant, MRP Controller, Order Type) Activity Type, Superior Activity, Subnetwork I, E, S, P, X (Internal, Preq, Service, Primary, Exclude) XP3 Activity (Exclude) E0010External Activity element to Activity 0010 G0030SG090E200Primary Activity of Subnet to Network SG090E200 0030 IInternal Activity Examples:
16
Design Solutions Exclusion / Aggregation Mapping SAP Objects P3 Objects Solution SAP Objects Priority Code = “X” Activity element Grouping / Summarization P3 Activities Custom Data Field: Type = “X” Grouping / Summarization Solution SAP Objects Priority Code = “X” Activity element Grouping / Summarization P3 Activities Custom Data Field: Type = “X” Grouping / Summarization
17
Design Solutions Many to 1 Mapping Many P3 Projects to One SAP Project Many SAP Projects to One P3 Project Solution Many P3 Projects Separate Impress Collaboration Projects Mapping Options: WBS Subtree Priority Code Many SAP Projects Multiple Parameter (Value) Sets Solution Many P3 Projects Separate Impress Collaboration Projects Mapping Options: WBS Subtree Priority Code Many SAP Projects Multiple Parameter (Value) Sets
18
Design Solutions Resources - Planned / Actual P3 Resource to SAP Work Center Mapping Planned / Actual / Forecast Work Mapping Solution Resources Mapping Global Parameters by Plant Overrides (P3 / SAP) Work Quantity Mapping Multiple Synchronization Action Types (SATs) SAT Parameters (Switches) Solution Resources Mapping Global Parameters by Plant Overrides (P3 / SAP) Work Quantity Mapping Multiple Synchronization Action Types (SATs) SAT Parameters (Switches)
19
Design Solutions Dynamic Environments – How do you avoid obliterating the Other System? SAP Scope / Plans Primavera Schedule Impress Synchronization Action Types (SAT) - Multiple SATs (10 to date) WBS Update: Both ways (optional) Activity Update – Multiple (parameterized) Relationships: Both ways (optional) Sequencing SATs Impress Synchronization Action Types (SAT) - Multiple SATs (10 to date) WBS Update: Both ways (optional) Activity Update – Multiple (parameterized) Relationships: Both ways (optional) Sequencing SATs Collaboration Project
20
Impress SAP-P3 Process Create Collaboration Project(s) Project Name Source System Source System Parameters Target System Project is Set up! Target System Parameters +
21
Impress SAP – P3 Process Project Synchronization Select Project Synchronization Types Synchronization Parameters Action Simulate Synchronize Now Schedule Reprocess Action Simulate Synchronize Now Schedule Reprocess Synchronization History
22
Topics Halliburton Company Why SAP-P3 Interface and Why Impress Pilot Project Interface Requirements Design Issues and Solutions Impress Interface Processes OpenPS Comparison Future Development Open Discussion OpenPS Comparison Future Development Open Discussion
23
OpenPS Interface OpenPS Advantages Many Users at Relatively Low Cost No Servers Required Simple to Maintain WBS / Network Coding Same For Smaller, Less Dynamic Projects (Most Projects) HR Integration (Resources by Employee) Fixed Mapping Fixed Mapping Rules / No Flexible Configuration No Exclusions (SAP or P3) No Hybrid PS / PM Projects Fixed Synchronizations SAP to MS Project – Creates New MS Project MS Project to SAP – Creates / Updates Structure and Schedule: Can be modified as to what is updated. Close Synchronization Coordination Required
24
Future Development Project Scenarios (on-going): Many SAP to 1 P3 (designed) PM Orders (NPPD deployed) Plant Shutdown (PS – PM Projects) Engineer-to-Order Projects (PP Orders)? Synchronization Action Types SAP Calendar SAP Resources Planned Costs / Actual Costs Earned Value Confirmations (limited)? Simulation Versions?
25
Key to Success Rationalize Code Conventions between SAP and Primavera Define Cost / Schedule Integration Matchpoint - Activity OR Suffer Detailed Cross-Coding Risk Suffer Detailed Cross-Coding Risk ! Business Processes NOT Systems
26
Any Questions? SAP – P3 Interface
27
Copyright © 2003 Americas’ SAP Users’ Group Thank you for attending! Please remember to complete and return your evaluation form following this session. Session Code: 3804