1 Information Technology Improvement Plan J. Brice Bible Chief Information Officer Ohio University June 28, 2007

2 Office of Information Technology June 28, 2007 2 Where Do We Go From Here? 75 Day Plan (April 15 to July 1) Organizational Review and Realignment Budget Review and Plan (FY08) Governance Model (ITAC and Advisory Groups) Gartner Infrastructure and Staffing Plan Prepare for FY08 (OHIO IT Strategic Plan) FY08 Key Activities Create Vision Ohio IT Plan Implement Gartner Recommendations (Year 1) Align Central-Distributed IT Responsibilities for Improved Efficiencies and Services Allocate New Funds Toward Top Priorities Create and Implement IT Security Framework

3 Office of Information Technology Gartner Findings OIT is significantly under-funded OIT is significantly under-staffed Performance not sustainable without investment Outsourcing currently not cost effective June 28, 2007 3

4 June 2, 2015 Office of Information Technology OHIO IT Spending vs. Peers 4 $7.4M Annually Below Bottom 25% of University Peers 17.2 FTEs Below Bottom 25% of University Peers 56.7 FTEs Below Average of University Peers $15.4M Annually Below Average of University Peers

5 Office of Information Technology June 28, 2007 5 Establish a New Identity Office of Information Technology (OIT) Name The Office of Information Technology (OIT) Mission Statement To ensure modern, reliable, secure, and customer-oriented information technology services and solutions are available to advance the academic mission and objectives of Ohio University Goals Provide a robust and secure information infrastructure Provide customer-oriented and integrated applications and services Provide transparent and measurable management practices

6 Office of Information Technology June 28, 2007 6 OIT Organization President Chief Information Officer Academic Technologies Infrastructure Systems and Operations Application and Information Services Customer Support Services Information Technology Security Business Services and Special Projects ITAC IT Recruiting, Retention, and Development Project Management

7 Office of Information Technology June 28, 2007 7 Office of Information Technology Establish Governance Model and Customer Involvement IT Advisory Council (ITAC) - The ITAC is a Presidentially-approved committee whose primary charge is to support the CIO in upholding the principles of Vision Ohio Functional Support Committees – Customer-oriented support committees focused on specific IT issues. Student Advisory Group Technology Architecture Council Faculty Senate IT Committee Administrative Technology Advisory Group

8 Office of Information Technology June 28, 2007 8 Anecdotal Customer Observations by CIO (First 2 Months) Blackboard account for continuing education courses Email assignment for admitted students Web hosting service Server hosting service Server security standardization policy URL acquisition and management (org, etc) Grad student printing quota Increase email quota Ensure the unlikelyhood of an outage similar to last Fall Simple mapped storage drive for all Identity management AD enhancement plan between central and distributed IT Telephone cost model improvements – don’t charge too much for handsets Eliminate desktop service call charge Provide easy support for DNS entry changes Eliminate charge for static IPs Improve wireless connections in the dorms Simplify software distribution Assist Baker Center with scheduling system Enable Blackberries to work seamlessly with email Integrate email and calendar Provide better grant expense reporting Integrate email system compatible with data phones and office products Centrally-support online course evaluation Faculty CV management system Etc, etc, etc… Provides Additional Customer Input Into IT Improvement Plan

9 Office of Information Technology June 28, 2007 9 Office of Information Technology IT Priority Areas Key Priority Areas: Infrastructure Modernization and Stability Service Enhancements and Improvements Priorities and policies are subject to review and governance by the Information Technology Advisory Council (ITAC).

10 Office of Information Technology June 28, 2007 10 Office of Information Technology IT Priority #1: Infrastructure Modernization and Stability (1 of 3) Network Infrastructure LAN Robustness, Redundancy, Flexibility, Capacity, and Security 10Gb Core, 10Gb to Buildings, 100Mb to users, Redundant Routing Continuation of Rewiring Plan Network Access Control and Security New Resources: Staffing (firewall and network engineers), Routers, Switches and Training Computer Systems Storage and Server Standardization and Modernization Create Enterprise Storage Architecture Replace Aging Servers with Unix and Linux Architecture Solutions Seamless and Secure Identity Management Architecture New Resources: Staffing (system engineers and administrators) and Systems

11 Office of Information Technology June 28, 2007 11 Office of Information Technology IT Priority #1: Infrastructure Modernization and Stability (2 of 3) Disaster Recovery and Business Continuity Develop IT Business Continuity Plan (Risk Acceptance) Define and Execute Backup and Disaster Recovery Plan (OSU, Second Data Center) Update Data Center Environmental Reliability (UPS, Cooling, etc) Complete Business Impact Analysis (BIA) for OIT provided services New Resources: Facilities and Systems Information Technology Security Regulatory and Legal Compliance (HIPAA, GLB, CALEA, Audit, etc) IT Staff Training and Certifications Campus Awareness and Training Programs Forensics, Monitoring, Copyright, and Analysis Tools IT Security Framework and Policies New Resources: Staffing, Training, Marketing, and Systems

12 Office of Information Technology June 28, 2007 12 Office of Information Technology IT Priority #1: Infrastructure Modernization and Stability (3 of 3) Customer Support Services Single Point of Contact (ITIL Service Model) Problem Resolution and Tracking System Campus Zone Support Managed Desktop Support Environment (academic-friendly model) Campus-Wide “Go Mobile” (laptop program) Support Infrastructure New Resources: Staffing, Systems, and Training Program Management Program Management Office (PMO) to Track Projects, Progress, and Priorities Process Management Coordination to Ensure Service Reliability and Performance New Resources: Staffing and Training

13 Office of Information Technology June 28, 2007 13 Office of Information Technology IT Priority #2: Service and Application Improvements (1 of 2) Financial and HR Administrative Systems Implement Solutions from BPR Study Create Position Management Solution Enhance Oracle e-Business Suite of Products (Based on Customer Survey Priorities) New Resources: Staffing (Oracle DBA, etc) Data Warehousing and Reporting Provide Decision Support Tools in Coordination with RCB and Institutional Effectiveness New Resources: Staffing and Analytical Tools Student Information System (SIS) Acquire and Implement Fully-Integrated and Web-Based SIS Conduct Campus Readiness Assessment Develop State Institution Partnerships New Resources: Staffing (contract), Software, Systems, Integration Partner, Facilities, and Training

14 Office of Information Technology June 28, 2007 14 IT Priority #2: Service and Application Improvements (2 of 2) Departmental Solutions Support College and Departmental Applications Needs (ex: Faculty CV System, Student Course Evaluation, etc) New Resources: Staffing, Software, and Systems Academic and Instructional Technologies Upgrade and Enhance Blackboard Releases Facilitate Faculty Evaluation and Selection of Additional Instructional Services (e-Portfolio, Assessment, etc) Support Asynchronous and Synchronous Classroom Tools Reallocate Current Resources to Instructional Design and Technology Support Provide Web Services for Campus Provide Lab Consolidation Services New Resources: Hardware, Software, and Staffing Collaboration Tools Survey Faculty, Staff, and Students on Collaboration and Communication Capability Needs Email, calendaring, shared storage (mapped drives), IM, etc Procure and Implement Selected Solutions New Resources: Hardware, Software, Staffing, and Training

15 June 28, 2007 15 Office of Information Technology Student Information System Update Board Approved $4M Start-up Phase Last FY Software Selection Committee Evaluation Complete (June 2007) PeopleSoft Software Recommendation IT Infrastructure NOT Ready to Begin Implement ation Recommended Next Phase – Readiness Assessment Determine Project Team Staffing Requirements (Technical and Functional) Appoint Project Management Team Develop Detailed Project Costing Ensure IT Improvement Plan Requirements Underway Determine Sources and Availability of Funding for Entire Project Pursue and Develop Possible State Alliances Four State Universities Using Same SIS Solution All at Approximately Same Step in Implementation Process Provide Detailed Proposal for Board of Trustees in Fall 2007

16 Office of Information Technology June 28, 2007 16 Proposed IT Improvement Funding Strategy Purpose Based on the Gartner Report and OU assessment, Central IT needs $7-$10M in additional funding to provide stable, reliable, and secure IT services Board of Trustees require rapid improvements President and Campus demand better IT service and enhanced information security Approach Set target goal of $8M in additional base IT funding over five years Ramp-up with $5M over first three years (Phase 1) Establish progress measurement criteria and conduct quarterly reviews Conduct program evaluation after Year 1 and create/revise into “rolling” two year plan

17 Office of Information Technology June 28, 2007 17 Office of Information Technology Initiative (In Priority Order) 1.Critical Staffing and Training 2.Computer Systems Modernization 3.Network Infrastructure Upgrade 4.Disaster Recovery and Security 5.Faculty Computer Refresh Program 6.Academic Technology Solutions 7.Data Warehousing and Reporting Tools 8.Collaboration Tools (email, etc) TOTAL ANNUAL FUNDING Allocation of New Funding 3 Year Ramp-up Plan to $5M Annually Year 2 $1,900,000 $500,000 $900,000 $200,000 $100,000 $200,000 $4,000,000 Year 1 $1,100,000 $300,000 $200,000 $100,000 $2,000,000 Annual Baseline Increase Year 3 $2,600,000 $500,000 $1,000,000 $300,000 $200,000 $100,000 $200,000 $5,000,000 $2,000,000 $1,000,000 11 Positions8 Positions5 Positions Finance and HR System Enhancements Student Information System (SIS) $2,000,000 $20,000,000

18 Office of Information Technology Twenty-Four (24) Critical IT Staff Additions (Over Three Years) Director, Systems & Operations Director, Customer Support Services Director, Infrastructure Director, Information Tech Security Program Mgmt Officer Infrastructure & Storage Administrator Unix Administrator (2) Windows Administrator (Departmental applications, etc) Applications Analyst Blackboard System Administrator Blackboard Applications Administrator Lead DBA DBAs (2) Network Administrator (2) Service Administrator (2) Network Engineer Security Analyst OS Programmer (2) Data Warehouse Architect Increases Infrastructure Staffing to 92 FTE Within 2.5 FTE of Bottom 25% of Peers (Gartner Report) Still 42 FTE Below Peer Average June 28, 2007 18 24 Positions (Base + Benefits)$2,200,000 Training & Development$124,000 Market Adjustments$316,000 Total Recurring Funding$2,640,000

19 June 28, 2007 19 Office of Information Technology Improvement Plan Hardware/Systems (3 Years) Network Upgrade Fiber Plant Upgrade and Dual Core Installation - Years 1 and 2 Central Buildings Cutover – Year 3 Remaining Building Connections to New Network - Years 4-7 Computer Systems Improvements Enterprise Storage – Years 1 and 2 (Distributed Storage Centralization) Server Replacement – Year 2 (Distributed Computer Systems Centralization and Security) Identity Management – Years 2 and 3 Backup/Recovery (DR) and Security Enhancements – Years 1 and 2 Critical Staffing (as defined earlier) – Years 1, 2, and 3 Faculty Computer Refresh Program – Year 2 Academic Technologies Blackboard Software Upgrade – Year 1 Software and Service Enhancements (Asynchronous, Open Source) – Years 2 and 3 Data Warehousing Decision Support Tools – Year 2 Collaboration Tool Improvements Exchange Email/Calendar Pilot Project – Year 1 Email/Calendar Production System – Year 2

20 June 28, 2007 20 Office of Information Technology Proposed Accomplishments for First Year (Metrics and Measurements) Network Infrastructure Upgrade Complete New Network Design and Detailed Budget Plan Begin Core Hardware Procurement Effort Computer Systems Improvements Design, Procure, and Implement Enterprise Storage Architecture Design Enterprise Server Architecture IT Security Improvements Develop Security Framework Plan and Create Data Classification Policy Conduct Identity Management Assessment Implement Disaster Recovery Service for SIS Critical Staffing Recruit and Hire First Round of Critical Staff Positions Ensure Performance Reviews are Conducted for all OIT Employees Academic Technologies Complete Upgrade to Current Version of Blackboard Provide Faculty Assessment Opportunity of New Blackboard Modules Collaboration Tool Improvements Conduct Exchange Email/Calendar Pilot Project with OU-COM

21 June 2, 2015 Office of Information Technology June 28, 2007 21 Office of Information Technology IT Infrastructure Life-Cycle Refresh Plan Establish TCO (Life-Cycle) Models for Core Infrastructure Services: Networks and Telephone Systems Computer Systems Enterprise Applications Desktop and Lab Computers Computer Systems: Components: Storage, Servers, IdM, Backup, DR, Email, Middleware, etc Value: $5M Replacement Cycle: 5 Years (Typ) Replacement Annual Fund Base - $1M ($500k in existing budget) Network Infrastructure: Components: Routers, Switches, Network Security, etc Value: $10M Replacement Cycle: 6 Years Ramp up to $1.6M Annually ($600k available)

22 June 28, 2007 22 Office of Information Technology Technology 1.Implementing a perimeter firewall 2.Monitoring network activity to identify attempted intrusions. 3.Conducting an IT risk assessment 4.Classifying data by the level of security required 5.Completing the installation of Active Directory (Authentication System) 6.Developing an enterprise-wide security architecture Strategy and Process 7.Developing policies and procedures for enterprise-wide IT 8.Implementing practices designed to prevent security problems, including network segmentation, virus and spyware detection. 9.Reducing the use of Social Security numbers and encrypting those that are required 10.Implementing processes to monitor security and assure compliance 11.Developing a strategic plan for Information Technology 12.Assuring "business continuity" for network and systems operations 13.Creating a security administration framework 14.Inventorying IT applications and information assets across the University Organization and Governance 15.Restructuring the central IT organization in order to establish clear roles 16.Hiring additional security staff 17.Conduct an IT skills assessment to identify IT training and development needs 18.Establishing a project management team within the central IT office 19.Improving communications with stakeholders 20.Restructure the IT Leadership Council Progress on Original 20 Point Plan FY07FY08FY09

23 Office of Information Technology June 28, 2007 23 Office of Information Technology Central-Distributed IT Alliance Focus on Four Areas of Joint Support: Server Administration Application Management Desktop Support Computer Lab Management Verify Approach Through Pilot Projects Finance and Administration College of Arts and Sciences College of Engineering Use Central IT Stabilization Approach

24 June 28, 2007 24 Office of Information Technology Conclusions Continued Focus on Stability and Security Established Scalable Organization (OIT) $8M Annually Needed to Stabilize IT Operations $5M Annually Over Three Years Provides Rapid Improvement Ramp-Up Detailed First Year Plan Includes Metrics to Monitor Performance New Governance Model In Place (ITAC) Central-Distributed IT Alliance Underway SIS Selection Completed Infrastructure Stabilization First Readiness Assessment Underway