Presentation is loading. Please wait.

Presentation is loading. Please wait.

BA 333 Operations Management

Similar presentations


Presentation on theme: "BA 333 Operations Management"— Presentation transcript:

1 BA 333 Operations Management
Project Management PERT/CPM Spring, 1998

2 Lecture Outline Project Management Introduction
Definition & Background Components event activity critical path PERT/CPM

3 Introduction to Project Management
Definition to plan, implement, and control the management of large, one time projects Used in Construction, Shipbuilding, Weapons Systems Development, etc. Applies to uncertain technology projects Applies to variable cost resource allocation History of PERT/CPM - Navy/Booze Allen Hamilton Consultants

4 Introduction to Project Scheduling

5 Components of Project Control Systems
Predecessor was Gantt Charts Horizontal Bar Charts - Time Lines Tasks Milestones Flow Charts - Relationships Among All Tasks Activities (tasks that take time and resources) sequential vs. concurrent Events (an accomplishment occurring at a specific point in time)

6 Project Characteristics
Single unit Many related activities Difficult production planning & inventory control General purpose equipment High labor skills

7 Examples of Projects

8 Examples of Projects Building construction  © 1995 Corel Corp.

9 Examples of Projects Sheer to waist pantyhose Building construction
New product introduction New! Improved! 19 · Nude Sandalfoot Medium to Tall (B) No nonsense Sheer to waist pantyhose © 1995 Corel Corp.

10 Examples of Projects Building construction New product introduction
Training seminar © Corel Corp.

11 Examples of Projects Building construction New product introduction
Training seminar Research project © Corel Corp.

12 Project Management Activities

13 Project Management Activities

14 Project Management Activities
Planning Objectives Resources Work break-down sched. Organization

15 Project Management Activities
Planning Objectives Resources Work break-down sched. Organization Scheduling Project activities Start & end times Network

16 Project Management Activities
Planning Objectives Resources Work break-down sched. Organization Scheduling Project activities Start & end times Network Controlling Monitor, compare, revise, action

17 Project Planning

18 Project Planning Establishing objectives Defining project
Creating work breakdown structure Determining resources Forming organization © 1995 Corel Corp.

19 Project Organization Often temporary structure
Uses specialists from entire company Headed by project manager Coordinates activities Monitors schedule & costs Permanent structure called ‘matrix organization’ Eng. Eng. Mkt. Acct. Mgr. © 1995 Corel Corp.

20 Project Scheduling

21 Project Scheduling Sequencing activities
Identifying precedence relationships Determining activity times & costs Estimating material & worker requirements Determining critical activities PERT Test J Build M A M J Design J F Month Activity © 1995 Corel Corp.

22 Project Scheduling Techniques
Gantt chart Critical Path Method (CPM) Program Evaluation & Review Technique (PERT) © T/Maker Co.

23 Gantt Chart

24 Gantt Chart

25 PERT & CPM Network techniques Developed in 1950’s
CPM by DuPont for chemical plants PERT by U.S. Navy for Polaris missile Consider precedence relationships & interdependencies Each uses a different estimate of activity times

26 Questions Answered by PERT & CPM
Completion date? On schedule? Within budget? Probability of completing by ...? Critical activities? Enough resources available? How can the project be finished early at the least cost?

27 PERT & CPM Steps Identify activities Determine sequence Create network
Determine activity times Find critical path Earliest & latest start times Earliest & latest finish times Slack

28 Constructing Networks

29 Graphical Representation of Events and Activities
Flow Charting - Uses Nodes and Arrows Arrows An arrow leads from tail to head directionally Nodes A node is represented by a circle Node Arrow

30 Activity On Node Task is Represented by Node as the Completion of an Activity Arrows Represent the Sequential Linkages Between Activities For Example, Node 1 is Begin, Node 2 is Complete Task 1, Node 3 is Complete Task 2 1 2 3

31 Activity On Arrow Task is Represented by an Arrow Bounded on Either End by a Node (Event) Each Event is Identified by a Number The Activity is Designated by the Leading Event Number and the Following Event Number - i.e. Activity 1 - 2 1 2

32 Designating Task Relationships
Sequential vs. Concurrent Activities 1 2 3 Sequential Task Relationship 1 2 3 4 Concurrent Task Relationships

33 Designating “DUMMY” Activities
Represented by Dashed Arrows Show Sequential Relationships Among Tasks, but Take No time or Resources 2 1 4 Dummy Activity 2-3 indicates that both Activities 1-2 and 2-3 must be Completed before beginning Activity 3-4 3

34 Network Terms

35 Network Terms Project: Obtain a college degree (B.S.)

36 Network Terms Project: Obtain a college degree (B.S.) Register 1

37 1 Network Terms Project: Obtain a college degree (B.S.) Register
Event (Node)

38 1 Network Terms Project: Obtain a college degree (B.S.) Register
Attend class, study etc. 1 4 Years Event (Node)

39 1 Network Terms Project: Obtain a college degree (B.S.) Register
Attend class, study etc. 1 4 Years Activity (Arrow) Event (Node)

40 1 2 Network Terms Project: Obtain a college degree (B.S.)
Receive diploma Register Attend class, study etc. 1 2 4 Years Activity (Arrow) Event (Node) Event (Node)

41 Activity Relationships

42 Activity Relationships
1

43 Activity Relationships
2 A 1 B 3 A & B can occur concurrently

44 Activity Relationships
A must be done before C & D can begin 2 D A C 1 4 B 3

45 Activity Relationships
2 D A C 1 4 B 3 E B & C must be done before E can begin

46 Activity Relationships
A must be done before C & D can begin 2 D A C 1 4 B 3 E A & B can occur concurrently B & C must be done before E can begin

47 Dummy Activities Activities are defined often by beginning & ending events Example: Activity 2-3 Every activity must have unique pair of beginning & ending events Computer programs get confused Dummy activities maintain precedence Consume no time or resources

48 Dummy Activities Example

49 Dummy Activities Example
2-3 Incorrect 1-2 3-4 1 2 3 4 2-3

50 Dummy Activities Example
2-3 Incorrect 1-2 3-4 1 2 3 4 2-3 Different activities; same designation

51 Dummy Activities Example
Incorrect 2-3 1-2 3-4 1 2 3 4 2-3 Correct 1-2 2-4 4-5 1 2 4 5 2-3 3 3-4: Dummy activity

52 Network Diagramming First Step in Project Management
Begins with a Work Breakdown Lists the “WHAT’ of a Project Begins with Finished Project Consists of Tree Chart, with Each Branch Listing the “WHAT’s” at that Level Then List Each Task that Must Be Completed to Accomplish the “WHAT”

53 Example Work Breakdown
House Site Prep Masonry Carpentry Finishing Exterior Walls Footings Piers Chimney Mixed Concrete Concrete Poured Forms Removed Forms Laid

54 Listing Of Activities Follows the “WHAT” with List of “HOW”
Each “WHAT” Results in Detailed List of the “Specific” Tasks Necessary to Accomplish the “WHAT” Followed by Specification of Sequential and Concurrent Relationships Among Tasks Results in Network Flow Diagram Representing the Tasks and Their Relationships

55 Activity Time Estimates
CPM - One Time Estimate per Activity PERT - Three Time Estimates per Activity a = Optimistic Time Estimate m = Most Likely Time Estimate b = Pessimistic Time Estimate Can Calculate Activity Mean Time Estimate and Variance

56 PERT Time Estimates Activity Mean Time Estimate = te
Activity Variance Estimate = Sigmae te = (a + 4m + b)/6 Sigmae = (b - a)/6 Can Use Central Limit Theorem to Estimate Project Time

57 Example Network Flow Diagram
7 6 5 4 3 2 1 A G C I H E B J F

58 Example Activity Characteristics
b te Sigmae A /3 B /3 C /3 D /3 E /3 F /3 G /3 H /3 I /3 J /3

59 Example Network Flow Diagram
te =7 7 6 5 4 3 2 1 te =12 te =13 te =11 te =4 te =8 te =7 te =10 te =11 te =10

60 Early Start & Early Finish
The Early Start Time for an Activity Emanating from an Event is the Earliest Point in Time that an Activity can Begin Determined by the Latest Early Finish of All Activities Terminating in an Event The Early Finish for an Activity is the Sum of its Early Start Time and its te

61 Example Network Flow Diagram
ES=12 ES=31 te =7 7 6 5 4 3 2 1 te =12 ES=18 ES=0 te =4 te =11 ES=52 te =13 te =8 ES=42 ES=11 te =7 te =10 te =11 te =10

62 Late Start & Late Finish
The Late Finish Time for an Activity Terminating in an Event is the Point in Time that it can be Completed Without Delaying the Completion of the Project Determined by Assigning to the LF the Value of the Earliest LS of all Activities Emanating from the Event The Late Start for an Activity is it Late Finish minus its te

63 Example Activity Characteristics
b te Sigmae ES LS EF LF / / / / / / / / / /

64 Example Network Flow Diagram With Critical Path
ES|LS|EF|LF t2-5=7 12|24|19|31 2 5 t1-2=12 0|2|12|14 t5-6=11 31|31|42|42 t4-5=13 18|18|31|31 t2-4=4 12|14|16|18 t4-6=8 18|34 |26|42 4 1 7 t3-4=7 11|11|18|18 t1-3=11 0|0|11|11 t6-7=10 42|42|52|52 6 3 t3-6=10 11|32|21|42

65 SLACK Total Slack Free Slack Critical Path
The Length of Delay in an Activity that Won’t Delay the Completion of the Project - LF- EF or LS-ES Free Slack The Length of Delay in an Activity that Won’t Delay the Beginning of Another Activity Critical Path Activities with the Minimum Total Slack - Often Total Slack on Critical Path Activities = 0

66 Probabilistic Estimates
Use of te and Sigmae Allows One to Make Probabilistic Estimates of Completion Dates By Summing the te‘s of the Activities on the Critical Path You Can Estimate the Duration of the Entire Project By Summing the Variance (Sigmae2) of the Activities on the Critical Path, You Can estimate the Total Variance of the Critical Path and Make One-Sided Interval Estimates of Project Completion Times

67 Probabilistic Estimates Example
Sigmae (Sigmae)2 /3 4/9 /3 36/9 /3 25/9 /3 49/9 /3 16/9 Variance = 130/9 = 14.4 Std Dev = 3.8 Probability that the Project Duration is Less than 60 days = Pr(T<60) Same as the Probability that Z < (60-52)/3.8 = 2.1 Therefore: Pr(T<60) = Pr(Z<2.1) = (see App. A, H&R, p. 842)

68 PERT Probability Example
You’re a project planner for General Dynamics. A submarine project has an expected completion time of 40 weeks, with a standard deviation of 5 weeks. What is the probability of finishing the sub in 50 weeks or less? © Corel Corp.

69 Converting to Standardized Variable

70 Converting to Standardized Variable
Assume project completion time follows a normal distribution.

71 Converting to Standardized Variable
Assume project completion time follows a normal distribution. Normal Distribution

72 Converting to Standardized Variable
Normal Distribution Standardized Normal Distribution

73 Converting to Standardized Variable
Normal Distribution Standardized Normal Distribution

74 Obtaining the Probability

75 Obtaining the Probability
Standardized Normal Probability Table (Portion) Probabilities in body

76 Obtaining the Probability
Standardized Normal Probability Table (Portion) .97725 Probabilities in body

77 Critical Path Method Uses Deterministic Time Estimates for Activities
Also Estimates Cost of Resources Levels for Each Activity Generally You Can increase the Resource Commitment and Reduce the Time Estimate for and Activity Use CPM to Analyze How To Reduce the Critical Path Most Efficiently

78 Benefits & Limitations of PERT/CPM

79 Benefits of PERT/CPM Useful at many stages of project management
Mathematically simple Use graphical displays Give critical path & slack time Provide project documentation Useful in monitoring costs

80 Limitations of PERT/CPM
Clearly defined, independent, & stable activities Specified precedence relationships Activity times (PERT) follow beta distribution Subjective time estimates Over emphasis on critical path

81 Conclusion Explained what a project is
Summarized the 3 main project management activities Drew project networks Compared PERT & CPM Determined slack & critical path Computed project probabilities

82 BA 333 Operations Management
Project Management PERT/CPM Spring, 1998 THE END

83


Download ppt "BA 333 Operations Management"

Similar presentations


Ads by Google