Download presentation
Presentation is loading. Please wait.
1
ESS Pre- Operations Dave McGinnis Accelerator Division/RF Group
2
Pre-Operations (my definition) Starts when we try to accelerate one proton down the beam tube Until we achieve 5 million Watts (5 MegaWatts) – 900 trillion protons per pulse – 14 times a second – Beam voltage of 2.5 billion volts
3
What is 5 MegaWatts? At 5 MegaWatts, – one beam pulse has the same energy as a 16 lb (7.2kg) shot traveling at – 1100 km/hour – Mach 0.93 Has the same energy as a 1000kg car traveling at 96 km/hour Happens 14 x per second – You boil 1000 kg of ice in 83 seconds A ton of tea!!!
4
Pre-Pre-Operations Will start during construction. As soon as a small section of the accelerator is ready (Ion Source->RFQ- >Drift Tube) – We will run beam to check out major systems (controls, RF, instrumentation, operations staff…) Beam is the Ultimate System Integrator! Commissioning will happen from 8pm – 8am – Construction and repair will happened during the day
5
Accelerator Readiness Because of the immense damage the beam can cause we will have to prepare procedures to makes sure all systems are ready – A BIG DEAL For example, formal sign-offs of all the systems: – Safety (shielding, interlocks, electrical,…) – Electrical – Vacuum – Instrumentation – RF – Cryogenics
6
Pre-Operations Once the machine is cold, and the accelerator is ready, we will begin round- the-clock operations – It is too expensive to not run round-the- clock – We have to maintain configuration control We will need to make a detailed commissioning plan – Detailed shift plan for 3 shifts per day for 3 months. People, tasks, tools – Plan will be invalid after the first shift “Plans are worthless, but planning is everything. ” Dwight Eisenhower
7
Staff We will need two types of crews – Operations crew (permanent) 3 operators/crew 5 crews – Scientist/ Engineer crew (temporary) 2 staff members/crew 6-7 crews We will need coordination – Machine coordinator (scientist) – Machine scheduler (operations) Meetings – Shift change meetings – Daily operations meetings
8
Super Rough Schedule ~1 month to thread the beam 1-6 months for 100kW beam 6-24 months for > 2 MW beam What are we doing between 2020-2025???
9
“If it works the first time, then its over-designed” Archimedes to his junior engineer, Wally, ~220 B.C
10
Upgrades A “gold-plated” accelerator is un- affordable. We have to plan to upgrade (fix) systems that did not perform as expected – Every large accelerator system built has taught us this LHC Tevatron SNS … Funding will be needed during the pre-operations phase for upgrades.
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.