Mid-Quarter Design Review April 7, 2009 Aaron Heyman Adam Cook.

Similar presentations


Presentation on theme: "Mid-Quarter Design Review April 7, 2009 Aaron Heyman Adam Cook."— Presentation transcript:

1 Mid-Quarter Design Review April 7, 2009 Aaron Heyman Adam Cook

2 Agenda Capacity Model (3.0) Changes since 2.8 Validation Process Overall Capacity What’s Next

3 Capacity Tool Global Changes Removal of Global units per line Added “Delay Allowance”  Calculated Effective Shift Length Added color coding to Max Workers

4 Capacity Tool Changes Pick Areas Removed unnecessary ADM input fields Identified and fixed error in ADM labor hour calculations New Pick Times (excludes breaks and lunch)

5 Validation Compared our calculated numbers against a one month sample of actuals Used Total Labor Hours as metric Calculated based on daily demand Results: Calculated labor hours were 5.5% less than actuals (avg. of all areas)

6

7

8 Overall Capacity Provided four options of presentation  MTBF/MTTR  Upper & Lower Bounds  Independent Areas  Bottleneck Identification Selection was a combination of Independent areas and Bottleneck ID

9 Overall Capacity ADM @ 95% uptime: 534 orders/hr PTL: 260 lines/hour/person Voice: 101 lines/hour/person Carousel: 206 lines/hour/person Bottleneck is a factor of pick times, people and demand in area

10 Next Steps Finalize Documentation for Capacity Tool Focus on Overall Capacity Analysis Addition of Pack to Capacity Tool  (If time allows)

11 Questions ?