1 MICE Top-Level Project Schedule Step IV Step V Step VI Revision date: 17 th June, 2011 1

2 STEP IV ComponentDate Spectrometer solenoid #1 + #2June’12 Fibre tracker #1 + #2Ready Focus coil #1Sept’11* LH 2 deliveryDec ‘11 Solid absorber?? Liquid absorberReady DiffuserJune’11 Virostek plate?? Substation upgradeReady EMR installationDec’11 Radiation shutter?? AFC Moving platform #1Nov’11 Step IV ready...Q3, 2012

3 STEP V ComponentDate Absorber focus coil #2Q4 2011 LH2 system BQ1 2013 RF AmplifiersQ3 2013 RF InfrastructureQ3 2013 RFCC #1Q1 2013 AFC Moving platform #2Q4 2012 RFCC Moving platform #1Q4 2012 Step V ready... Q4, 2014

4 STEP VI ComponentDate Focus coil #3 RFCC #2Q3 2013 LH2 system #3Q2 2014 AFC Moving platform #3 RFCC Moving platform #2 Step VI ready...Q4, 2016