Download presentation
Presentation is loading. Please wait.
1
IWAA2010 - R. BEUNARD – September 13-17, 2010 – DESY, Hamburg, Germany 1 20m Rémy Beunard A. Lefevre, F. Legruel GANIL, CAEN, FRANCE The 11th INTERNATIONAL WORKSHOP ON ACCELERATOR ALIGNMENT DESY, Germany, September 13-17, 2010
2
IWAA2010 - R. BEUNARD – September 13-17, 2010 – DESY, Hamburg, Germany 2 Outline
3
3 PARIS CAEN FRANCE Geographical location The SPIRAL 2 project is located at the GANIL * facility in Caen in Basse-Normandie. *GANIL: (Large National Heavy-Ion Accelerator) GANIL Hamburg
4
IWAA2010 - R. BEUNARD – September 13-17, 2010 – DESY, Hamburg, Germany 4 HRS+RFQ Cooler GANIL/SPIRAL1/SPIRAL2 facility A/q=6 Injector option DESIR Facility low energy RIB RIB Production Cave Up to 1014 fiss./sec. RIB Production Cave Up to 1014 fiss./sec. A/q=3 HI source Up to 1mA A/q=3 HI source Up to 1mA A/q=2 source p, d, 3,4He 5mA A/q=2 source p, d, 3,4He 5mA LINAC: 33MeV p, 40 MeV d, 14.5 A MeV HI S3 separator spectrometer Neutrons For Science GANIL/SPIRAL 1 today CIME cyclotron RIB at 1-20 AMeV (up to 9 AMeV for fiss. fragments) 50 m ~
5
IWAA2010 - R. BEUNARD – September 13-17, 2010 – DESY, Hamburg, Germany 5 Organization – Two construction phases
6
IWAA2010 - R. BEUNARD – September 13-17, 2010 – DESY, Hamburg, Germany 6 GANIL Phase 1 Accelerator & S3, NFS Building 3D visualization DESIR Phase 2 RIB PRODUCTION Process will be installed underground at level -9.50 m
7
IWAA2010 - R. BEUNARD – September 13-17, 2010 – DESY, Hamburg, Germany 7 Process Phase 1 Cross section 25 m ~ Accelerator Process : level -9.50 m Towards Production Building
8
IWAA2010 - R. BEUNARD – September 13-17, 2010 – DESY, Hamburg, Germany 8 HRS + RFQ Cooler RIB Production RIB to GANIL Level : -1.75 m RIB to DESIR Production Module Beam from the accelerator Level : -8.0 m Process Phase 2
9
IWAA2010 - R. BEUNARD – September 13-17, 2010 – DESY, Hamburg, Germany 9 SPIRAL2 …the milestones 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Construction of new detectors Exp. with S3 Exp. with NFS Construction Phase 1 Stable ion beams from LINAC Commis- sioning Phase 1 Construction Phase 2 Commis- sioning Phase 2 First LINAC Beam Feb. 2012 Today First RIB Oct. 2013 RIB
10
IWAA2010 - R. BEUNARD – September 13-17, 2010 – DESY, Hamburg, Germany 10 The geodetic systems: local and national Why two systems at GANIL ?
11
IWAA2010 - R. BEUNARD – September 13-17, 2010 – DESY, Hamburg, Germany 11 the facility. CSS1 X = 500. 00 m Y = 200.000 m Z = 20.000 m Y X Z 25 m CIME The local geodetic system CSS1 X = 100. 000 m X = 500. 00 m Y = 200.000 m Z = 10. 000 m Z= 20.000 m CSS2 X = 100. 000 m X = 500. 000 m Y = 229.0154 m Z = 10. 000 m Z = 20.000 m « Point Croix » X = 111. 000 m X = 511.000 m Y = 241.5154 m Z = 10. 000 m Z = 20.000 m connection of the radioactive beam transport line Reference network marks
12
IWAA2010 - R. BEUNARD – September 13-17, 2010 – DESY, Hamburg, Germany 12 Y X The national geodetic system Topographic plan CSS2 CSS1 CIME radioactive beam transport line Existing GANIL facility geographical location of the SPIRAL2 process 50 m
13
IWAA2010 - R. BEUNARD – September 13-17, 2010 – DESY, Hamburg, Germany 13 S118 S1191 S123S122 7031 7032 7033 7034 25 m Topographic ground point (station) New ground point outside existing installations … Connection of the local geodetic system to the national system Now, the project coordinates can be expressed in both geodetic systems X Z Y Local system X Z Y Lambert 1 system Phase 2 radioactive beam transport line
14
IWAA2010 - R. BEUNARD – September 13-17, 2010 – DESY, Hamburg, Germany 14 Diagram showing the Cartesian coordinates in the two systems of the process fundamental points Linac/LHE intersection systemX (m) Y (m) Lambert 1 403 428.339171 900.345 Local 445.113 31348.231 53 Linac axis LHE axis 50 m X Z Y Local system X Z Y Lambert 1 system Intersection Linac/LHE system Coord. X (m) Coord. Y (m) Lambert 1403 428.339171 900.345 Local445.113 31348.231 53 D52 magnet system Coord. X (m) Coord. Y (m) Lambert 1403 498.343171 834.095 Local498.323 31267.866 69 CIME cyclotron centre system Coord. X (m) Coord. Y (m) Lambert 1403 497.653171 828.567 Local496.400 01262.638 39 LHE intersection / 1+ Line-Section 0 system Coord. X (m) Coord. Y (m) Lambert 1403 437.022171 862.940 Local445.113 31309.831 53 S3 Existing GANIL
15
IWAA2010 - R. BEUNARD – September 13-17, 2010 – DESY, Hamburg, Germany 15 Surface geodetic network project Type of geodetic pillar equipped with a forced centring 1 Pillar of the Linac and LHE line axes (included in the geodetic network) Geodetic network pillar 6 7 8 2 9 5 4 3 10 Phase 2 radioactive beam transport line How to install the process geographically ?
16
IWAA2010 - R. BEUNARD – September 13-17, 2010 – DESY, Hamburg, Germany 16 1 3 4 2 Surface geodetic network project Reference pillar for process installation at – 9.50 m Phase 2 radioactive beam transport line
17
IWAA2010 - R. BEUNARD – September 13-17, 2010 – DESY, Hamburg, Germany 17 The first solution which occurred to us is to transfer the beam Linac axis by optical plummet through this survey shaft. Installation the 2 nd order geodetic network Linac axis Pillar N°1 Pillar N°2 shaft longitudinal section of the Linac Lev. 0.0 m Lev. -9.50 m Filling up layer (calcareous stone extracted during the excavation) This solution was rejected because of the risk of neutron scattering at level 0 due to the difficulty to press down the calcareous stone around the shaft Transfer of aboveground coordinates into the tunnel via plumbing The beam line axis will be transferred onto the concrete slab from pillars 1 to 2
18
IWAA2010 - R. BEUNARD – September 13-17, 2010 – DESY, Hamburg, Germany 18 talus Sketch Block limit ACC 1/2-2/2 Intersection Linac / LHE Pillar N° 1 Lev. + 1.43 m Lev. 0.0 m Slope Slab Lev -9.50 m Slope Lines of sight Markers sealed in the slab Installation principle of the process (Linac) axes at level – 9.50 m Installation the 2 nd order geodetic network Pillar N° 2 Lev. + 1.43 m Linac axis Constraint of this solution : This operation must be performed before the concrete slabs of the higher levels are poured (ceiling of Linac and beam transport rooms)
19
IWAA2010 - R. BEUNARD – September 13-17, 2010 – DESY, Hamburg, Germany 19 Installation the 2 nd order geodetic network Partial view of the topometric network of the process at -9.50m Installation of a floor grid reference spaced between 3 and 5 m. Reference marks sealed in the slab Reference marks sealed againts the walls (study is ongoing) Viewing window installed during the making of concrete walls
20
IWAA2010 - R. BEUNARD – September 13-17, 2010 – DESY, Hamburg, Germany 20 Altimetric systems (m) GANIL "local" NGF (topographic plan) Contactor (building plans) GANIL Accelerator floor +18.50+ 58.470.00 Experimental area floor + 18.25+ 58.22-0.25 ACC Beam Median Plane lev 0 + 20.00+ 59.97+1.50 ACC Beam Median Plane lev -1 + 16.75+ 56.72-1.75 SPIRAL2 Floor lev +0.00 (ground level) +18.50+ 58.470.00 SPIRAL2 Beam Median Plane + 10.50+ 50.47-8.00 Floor lev -9.50 (Linac) + 9.00+ 48.97-9.50 Mapping between the various alltimetric systems used alltimetric systems used Systems which will be used on the site depending on requirements
21
IWAA2010 - R. BEUNARD – September 13-17, 2010 – DESY, Hamburg, Germany 21 Monitoring of building movements at ground level Lines of sight to monitor the building Block ACC 1/2 Block ACC2/2 Block S3 Block NFS/LHE
22
IWAA2010 - R. BEUNARD – September 13-17, 2010 – DESY, Hamburg, Germany 22 Summary
23
IWAA2010 - R. BEUNARD – September 13-17, 2010 – DESY, Hamburg, Germany 23 Thanks for your attention!
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.