Statistical Process Control Dr. Ron Lembke
2
Statistics
3
Measures of Variability Range: difference between largest and smallest values in a sample Very simple measure of dispersion R = max - min Variance: Average squared distance from the mean Population (the entire universe of values) variance: divide by N Sample (a sample of the universe) var.: divide by N-1 Standard deviation: square root of variance
4
Skewness Lack of symmetry Pearson’s coefficient of skewness: Skewness = 0 Negative Skew < 0 Positive Skew > 0
5
Kurtosis Amount of peakedness or flatness Kurtosis < 0 Kurtosis > 0 Kurtosis = 0
6
Table 14.2 Is everything OK? How can we decide? Does it look normal?
7
Histogram of 150 data points Histogram looks pretty normal, but definitely not perfect. Looks like 2 peaks, actually, but pretty normal.
8
Is it Normal? Sorted all 150 data points, plotted Mean = 0.7616, stdv = 0.0738
9
Compute 1,2,3 sigma limits
10
Is it Normal? F(m-3s) = 0F(m+1s) = 129/150 = 0.86 F(m-2s) = 7/150 = 0.0467F(m+2s) = 149/150 = 0.993 F(m-1s) = 24/150 = 0.16F(m+3s) = 150/150 = 1.00 F(m) = 71/150 = 0.473
11
Is it Normal? DataTheoretical F(m-3s) = 00.001 F(m-2s) = 0.04670.023 F(m-1s) = 0.1600.159 F(m) = 0.4730.500 F(m+1s) = 0.8600.841 F(m+2s) = 0.9930.977 F(m+3s) = 1.0000.999 Values we get are pretty close to a normal distribution.
12
Real Test of Normality Kolmologorov-Smirnov Anderson-Darling Sadly, we don’t have time for either today You need SAS or something like it. Excel can’t do everything.
13
Process Capability UTL = 1.0 LTL = 0.5 Cpk > 1.0 Process capable, but barely Is everything OK?
14
Plot Data over time No significant trend to data?
15
Plot Data over time Data is in sets of 5, all taken at same time. Plotting individual points makes us see trends that aren’t really there. Solution – plot averages of each sample
16
Sample Means
17
Control Chart Control Limits are mean +/- 3 std. dev.
18
We have Out-of-Control Points Looks like the mean has shifted. Something is definitely wrong.
19
Control Limits catch early In fact, we should compute control limits using first 17 data points
20
Revise Control Limits New control limits using first 16 data points.
21
Control Chart Usage Only data from one process on each chart Putting multiple processes on one chart only causes confusion 10 identical machines: all on same chart or not?
22
In Control A process is “in control” if it is not affected by any unusual forces Compute Control Limits, Plot points
23
X-bar Chart for Averages
24
Definitions of Out of Control 1. No points outside control limits 2. Same number above & below center line 3. Points seem to fall randomly above and below center line 4. Most are near the center line, only a few are close to control limits 1. 8 Consecutive pts on one side of centerline 2. 2 of 3 points in outer third 3. 4 of 5 in outer two-thirds region
25
You’re manager of a 500-room hotel. You want to analyze the time it takes to deliver luggage to the room. For 7 days, you collect data on 5 deliveries per day. Is the process in control? Hotel Example
26
Hotel Data DayDelivery Time 17.304.206.103.455.55 24.608.707.604.437.62 35.982.926.204.205.10 47.205.105.196.804.21 54.004.505.501.894.46 610.108.106.505.066.94 76.775.085.906.909.30
27
R & X Chart Hotel Data Sample DayDelivery TimeMeanRange 17.304.206.103.455.555.32 7.30 + 4.20 + 6.10 + 3.45 + 5.55 5 Sample Mean =
28
R & X Chart Hotel Data Sample DayDelivery TimeMeanRange 17.304.206.103.455.555.323.85 7.30 - 3.45Sample Range = LargestSmallest
29
R & X Chart Hotel Data Sample DayDelivery TimeMeanRange 17.304.206.103.455.555.323.85 24.608.707.604.437.626.594.27 35.982.926.204.205.104.883.28 47.205.105.196.804.215.702.99 54.004.505.501.894.464.073.61 610.108.106.505.066.947.345.04 76.775.085.906.909.306.794.22
30
R R Chart Control Limits R k i i k 1 385427422 7 3894....
31
R Chart Control Limits Solution From B-1 (n = 5) R R k UCLDR LCLDR i i k R R 1 4 3 385427422 7 3894 (2.114)(3.894)8232 (0)(3.894)0.....
32
R Chart Control Chart Solution UCL
33
X Chart Control Limits Sample Range at Time i # Samples Sample Mean at Time i
34
X Chart Control Limits From Table B-1
35
R & X Chart Hotel Data Sample DayDelivery TimeMeanRange 17.304.206.103.455.555.323.85 24.608.707.604.437.626.594.27 35.982.926.204.205.104.883.28 47.205.105.196.804.215.702.99 54.004.505.501.894.464.073.61 610.108.106.505.066.947.345.04 76.775.085.906.909.306.794.22
36
X Chart Control Limits X X k R R k i i k i i k 1 1 532659679 7 5813 385427422 7 3894........
37
X Chart Control Limits From B-1 (n = 5) X X k R R k UCLXAR i i k i i k X 1 1 2 532659679 7 5813 385427422 7 3894 5813058 *38948060............
38
X Chart Control Limits Solution From Table B-1 (n = 5) X X k R R k UCLXAR LCLXAR i i k i i k X X 1 1 2 2 532659679 7 5813 385427422 7 3894 5813(058) 5813(058) (3.894) = 3.566............ (3.894) = 8.060
39
X Chart Control Chart Solution* 0 2 4 6 8 1234567 X, Minutes Day UCL LCL
40
Subgroup Size All data plotted on a control chart represents the information about a small number of data points, called a subgroup. Variability occurs within each group Only plot average, range, etc. of subgroup Usually do not plot individual data points Larger group: more variability Smaller group: less variability Control limits adjusted to compensate Larger groups mean more data collection costs
41
General Considerations, X-bar, R Operational definitions of measuring techniques & equipment important, as is calibration of equipment X-bar and R used with subgroups of 4-9 most frequently 2-3 if sampling is very expensive 6-14 ideal Sample sizes >= 10 use s chart instead of R chart.
42
Single Data Points? What if you only have one data point on a process? Inspect every single item There is no range. R=0? Charts for Individuals (x-Chart) CL: x-bar +/- 3R-bar/d2 R = difference between consecutive units Draw control limits on the chart We can also put User specification limits on, for reference purposes Doesn’t catch trends as quickly Normality assumption must hold
43
Attribute Control Charts Tell us whether points in tolerance or not p chart: percentage with given characteristic (usually whether defective or not) np chart: number of units with characteristic c chart: count # of occurrences in a fixed area of opportunity (defects per car) u chart: # of events in a changeable area of opportunity (sq. yards of paper drawn from a machine)
44
p Chart Control Limits # Defective Items in Sample i Sample i Size
45
p Chart Control Limits # Defective Items in Sample i Sample i Size z = 2 for 95.5% limits; z = 3 for 99.7% limits # Samples
46
p Chart Control Limits # Defective Items in Sample i # Samples Sample i Size z = 2 for 95.5% limits; z = 3 for 99.7% limits
47
p Chart Example You’re manager of a 500- room hotel. You want to achieve the highest level of service. For 7 days, you collect data on the readiness of 200 rooms. Is the process in control (use z = 3)? © 1995 Corel Corp.
48
p Chart Hotel Data No.No. Not DayRoomsReady Proportion 12001616/200 =.080 2200 7.035 320021.105 420017.085 520025.125 620019.095 720016.080
49
p Chart Control Limits
50
16 + 7 +...+ 16
51
p Chart Control Limits Solution 16 + 7 +...+ 16
52
p Chart Control Limits Solution 16 + 7 +...+ 16
53
p Chart Control Chart Solution UCL LCL
54
P-Chart Example Enter the data, compute the average, calculate standard deviation, plot lines
55
Dealing with out of control Two points were out of control. Were there any “assignable causes?” Can we blame these two on anything special? Different guy drove the truck just those 2 days. Remove 1 and 14 from calculations. p-bar down to 5.5% from 6.1%, st dev, UCL, LCL, new graph
56
Revised p-Chart
57
Different Sample sizes Standard error varies inversely with sample size Only difference is re-compute for each data point, using its sample size, n. Why do this? The bigger the sample is, the more variability we expect to see in the sample. So, larger samples should have wider control limits. If we use the same limits for all points, there could be small-sample-size points that are really out of control, but don’t look that way, or huge sample-size point that are not out of control, but look like they are. Judging high school players by Olympic/NBA/NFL standards.
58
Different Sample Sizes
59
How not to do it If we calculate n-bar, average sample size, and use that to calculate a standard deviation value which we use for every period, we get: One point that really is out of control, does not appear to be OOC 4 points appear to be OOC, and really are not. Only potentially do this if all values fall within 25% of the average But with computers, why not do it right?
60
5 false readings
61
np Charts – Number Nonconforming Counts number of defectives per sample Sample size must be constant
62
C-Chart Control Limits # defects per item needs a new chart How many possible paint defects could you have on a car? C = average number defects / unit Each unit has to have same number of “chances” or “opportunities” for failure UCL c z C c LCLz C c c
63
Paint Blemishes
64
Number of data points Ideally have at least 2 defective points per sample for p, c charts Need to have enough from each shift, etc., to get a clear picture of that environment At least 25 separate subgroups for p or np charts
65
Small Average Counts For small averages, data likely not symmetrical. Use Table 7.8 to avoid calculating UCL, LCL for averages < 20 defects per sample Aside: Everyone has to have same definitions of “defect” and “defective” Operational Definitions: we all have to agree on what terms mean, exactly.
66
U charts: areas of opportunity vary Like C chart, counts number of defects per sample No. opportunities per sample may differ Calculate defects / opportunity, plot this. Number of opportunities is different for every data point n i = # square feet in sample i