Download presentation
Presentation is loading. Please wait.
Published byChristian Hoover Modified over 9 years ago
1
Workshop on Technology Development for reaching 250 MT (19-20) Mahanadi Coalfields Limited
3
Estimated demand & Gap Demand of coal IN MT (at 100% satisfaction level) as per FSA/LOA Year 15-1616-1717-1818-1919-20 Demand 199.00242.00 Prod150.00167.00187.00222.00250.00 Gap49.0075.0055.0020.00-8.00
5
Year 14-1515-1616-1717-1818-1919-20 UG1.50 OC125.50148.50165.50185.50220.50248.50 TOTAL127.00150.00167.00187.00222.00250.00 Coal production projection Year wise upto 2019-20
7
Additional Shovel required to achieve 250 Mty by 2019-20 Capacity15-1616-1717-1818-1919-20Total 34 Cum2103 20-22 Cum142411 9-10 Cum727355478 5-6.5 Cum368--17 2.5-4.3 Cum-42--6 Grand Total115
8
Replacement of Shovel Existi ng 14- 15 15- 16 16- 17 17- 1818-19 19- 20 Total 10 Cum 12- 4.5 -6.5 Cum40 22 4 2.5 to 4.3 Cum37 24521 14
9
Capacity15-1616-1717-1818-1919-20Total 35 T7831--46 50/60 T48108139--295 85-100 T632293285553728 190 T-6362052114 240 T-20 --40 Total1223 Additional Dumper required to achieve 250 Mty by 2019-20
10
Replacement of Dumper Exist ing 14- 15 15- 1616-1717-18 18- 1919-20 Total 50/60 T284 3431661710- 158
11
Additional Dozer required to achieve 250 Mty by 19-20 Capacity 15-1616-1717-1818-1919-20Total 770-850 HP (with Ripper attachment)41795338 410 HP1525419999
12
Replacement of Dozer Existi ng 14-1515-1616-1717-1818-1919-20 Total 410 HP75 9201162- 48 320 HP31 --151- 7
13
Additional Drill required to achieve 250 Mty by 2019-20 15-1616-1717-1818-1919-20 Total 250 mm8314698102 150-160 mm1226304577
14
Replacement of Drill Existing 14-1515-1616-1717-1818-1919-20 Total 250 mm34 141 6 160 mm55 76132 19
15
Additional Surface Miner required to achieve 250 Mty by 2019-20 15-1616-1717-1818-1919-20 Total 3000- 3800 mm 38143432
16
Additional Loading machine (Pay loader) required to achieve 250 Mty by 2019-20 15-1616-1717-1818-1919-20 Total >5 cum51113--29 >10 cum-143412
17
Replacement Loading M/C (Pay loader) Existi ng 14-15 15-1616-1717-1818-1919-20 Total >5cum 10 41 5
18
Additional equipment required for UG upto 2019-20 Capacity Nos ExistingReplacement Continuous Miner 1.4 to 4.6 M2 SDL1 cum918 Low Height SDL 0.8 cum6 Low Height SDL 1 cum 3 LHD1.2 cum22920 LHD2.7 cum4 Roof BolterQuad bolter2 Shuttle Car15 Te6 ConveyorBelt Conveyor11800 m Roof Bolter15
19
Tube/pipe conveyorRequirement/Capacity Hingula5 Km Bhubaneswari3.5 km Other P&M ( other than HEMM) requirement to achieve 250 MT
20
Washery Jagannath washery10 Mty Hingula washery10 Mty Kulda washery10 Mty Basundhara washery10 Mty Siarmal washery10 Mty X 4 Lakhanpur integrated20 Mty & 10 Mty Other P&M ( other than HEMM) requirement to achieve 250 MT
21
Kaniha/Gopalji SILO30 Mty Lingaraj SILO16 Mty Bhubaneswari SILO20 Mty Ananta SILO15 Mty Bharatpur SILO15 Mty Hingula SILO15 Mty Gopalprasad SILO15 Mty Talabira-II &III SILO20 Mty Lakhanpur SILO 30 Mty Kulda SILO 10 Mty Siarmal SILO 40Mty Rapid Loading System including SILO requirement to achieve 250 MT
22
Technological Development & Mechanization of Mines Proposed Present technology Production level in 19-20 SDL/LHD with Bord & Pillar in UG Man-riding system in UG 1.5 MT Dragline & Shovel-Dumper combination for OB removal, Loader-Tipper for coal production in OC Surface miner for blast free coal production in OC248.5 MT OITDS, GPS for better monitoring Future technology Continuous miner in UG Higher capacity Shovels & Dumpers Pipe conveyor for coal transportation Ripper dozer for blast free OB removal in OC RLS with SILO for faster loading of wagons
23
Award of Contracts SlProjectsKey Contracts for EPC, OB removal, coal removal etc. Timeline 1 Kaniha OCP Award of contract for MDOSep-17 2 Siarmal OCP Award of contract for MDO Dec-16
24
Issues with BEML (A) Delay in supply of spare parts. Spare parts of a module is not supplied in full rather it is supplied in piecemeal due to which repair of particular assembly and equipment is delayed. (B) BE-1600 Hydraulic Excavator 9.5 cum. 06 nos. supplied to MCL are going under frequent breakdown, due to Failure of engines, Hydraulic pumps & Hydraulic tubes, Cooling system and other components since its commissioning.
25
The performance of BEML : Year 2008- 09 2009- 10 2010- 11 2011- 12 2012- 13 2013- 14 2014- 15 % Availability Model Present populat ion BE 1600 D6-796655394550 BE 1000 D12-847168545253 BE 1000 E569647269576669
26
The performance of BEML : Year 2008- 09 2009- 10 2010- 11 2011- 12 2012- 13 2013- 14 2014- 15 % Breakdown Model Present populat ion BE 1600 D6-142941585146 BE 1000 D12-102327424443 BE 1000 E527322427403027
27
(C)The performance of BH-100 Ton Dumpers after warranty period is very poor due to failure of Engines, Transmission and other components. Performance is as below : Year2008- 09 2009- 10 2010- 11 2011- 12 2012- 13 2013- 14 2014- 15 % Availability Present population 29 Model BH-100 (100T) -637661553438
28
(C)The performance of BH-100 Ton Dumpers after warranty period is very poor due to failure of Engines, Transmission and other components. Performance is as below : Year2008- 09 2009- 10 2010- 11 2011- 12 2012- 13 2013- 14 2014- 15 % Breakdown Model Present population BH-100 (100T) 29-301935426359
29
(D) Recently, supplied BH-60 Ton Dumpers are giving problems like Cabin Vibration, Regular failure of suspension, Air Conditioning compressor mounting bolt loosening problem, Sensors are not working, Camera monitoring foundation bracket failure & Transmission pump failure etc. (E) Recently supplied BD-355 Dozers are also not performing to the mark and giving troubles like : Automatic release of blades sometimes Misalignment of cabin Non functioning of Air Conditioner Fuel Injection Pumping problem Starting problem etc.
30
ISSUES WITH M/S.H.E.C., RANCHI There is general delay in supply of equipment as well as spare parts. As HEC is facing financial constraints, they are demanding advance payment for supply of equipment for recently ordered 10 cum. Electric Rope Shovel
31
ISSUES WITH M/S. PROMTRACTOR (JSC), RUSSIA Performance of 15 nos. 410 HP Dozers are very very poor due to abnormal failure of engine & transmission even in warranty period. The performance is as below : M/s. Promtractor (JSC), Russia has no Indian service provider for supply of spare parts and maintenance and also not supporting well for supply of spare parts and services. Year2008-092009-102010-112011-122012-132013-142014-15 CompanyM/s. Promtractor (JSC), Russia % Availability Model Present Populati on Promtractor T- 25.01CB-1 15--7153312411 % Breakdown Model Promtractor T- 25.01CB-1 --2343677488
32
Thank you
33
All HEMM should be supplied with Guaranteed Spare Parts Supply (GPS) or Maintenance and Repair Contract (MARC) for life time. SUGGESTIONS FOR SUPPLY AND MAINTENANCE OF EQUIPMENT
34
Guarantee for initial 2-3 years is meaningless as machine will perform initially better than when it gets older after 03 years. Hence, guarantee for later period is more important. Cost of equipment quoted is very less but spare parts are very costly which ultimately result into higher cost of production. If life cycle cost is adopted this can be eliminated. Buy back system is to be incorporated in case of spare parts which are not consumed during warranty period. Some manufacturers are reluctant for life time guarantee due to uncertainty in foreign currency fluctuation. This problem can be sorted out by incorporating currency escalation/de- escalation clause. SUGGESTIONS FOR SUPPLY AND MAINTENANCE OF EQUIPMENT
35
4-5 years satisfactory performance may be introduced instead of one year as per existing standard NIT. At least 30-40% of the tendered quantity may be considered for meeting the prove ness criteria instead of at least one number as per existing standard NIT. Tender finalization should be 60/40 basis as per earlier system to have a check on L-1 bidder both in price as well as performance. The equipment which are not having base in India should not be given chance for participation in open tender as there is also problem of spare and service support because of non availability of India Agent. There should be a provision of consignment store having major population nearer to the project. Modification in Proveness criteria
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.