Download presentation
Presentation is loading. Please wait.
1
Making Investment Decisions with the Net Present Value Rule Principles of Corporate Finance Brealey and Myers Sixth Edition Slides by Matthew Will Chapter 6 © The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw Hill
2
© The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw Hill 6- 2 Topics Covered What To Discount IM&C Project Project Interaction Timing Equivalent Annual Cost Replacement Cost of Excess Capacity Fluctuating Load Factors
3
© The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw Hill 6- 3 What To Discount Only Cash Flow is Relevant
4
© The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw Hill 6- 4 What To Discount Only Cash Flow is Relevant
5
© The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw Hill 6- 5 What To Discount Do not confuse average with incremental payoff. Include all incidental effects. Do not forget working capital requirements. Forget sunk costs. Include opportunity costs. Beware of allocated overhead costs. Points to “Watch Out For”
6
© The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw Hill 6- 6 Be consistent in how you handle inflation!! Use nominal interest rates to discount nominal cash flows. Use real interest rates to discount real cash flows. You will get the same results, whether you use nominal or real figures. Inflation INFLATION RULE
7
© The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw Hill 6- 7 Inflation Example You own a lease that will cost you $8,000 next year, increasing at 3% a year (the forecasted inflation rate) for 3 additional years (4 years total). If discount rates are 10% what is the present value cost of the lease?
8
© The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw Hill 6- 8 Inflation Example You own a lease that will cost you $8,000 next year, increasing at 3% a year (the forecasted inflation rate) for 3 additional years (4 years total). If discount rates are 10% what is the present value cost of the lease?
9
© The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw Hill 6- 9 Inflation Example - nominal figures
10
© The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw Hill 6- 10 Inflation Example - real figures
11
© The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw Hill 6- 11 IM&C’s Guano Project Revised projections ($1000s) reflecting inflation
12
© The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw Hill 6- 12 IM&C’s Guano Project NPV using nominal cash flows
13
© The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw Hill 6- 13 IM&C’s Guano Project Cash flow analysis ($1000s)
14
© The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw Hill 6- 14 IM&C’s Guano Project Details of cash flow forecast in year 3 ($1000s)
15
© The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw Hill 6- 15 IM&C’s Guano Project Tax depreciation allowed under the modified accelerated cost recovery system (MACRS) - (Figures in percent of depreciable investment).
16
© The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw Hill 6- 16 IM&C’s Guano Project Tax Payments ($1000s)
17
© The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw Hill 6- 17 IM&C’s Guano Project Revised cash flow analysis ($1000s)
18
© The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw Hill 6- 18 Timing Even projects with positive NPV may be more valuable if deferred. The actual NPV is then the current value of some future value of the deferred project.
19
© The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw Hill 6- 19 Timing Example You may harvest a set of trees at anytime over the next 5 years. Given the FV of delaying the harvest, which harvest date maximizes current NPV?
20
© The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw Hill 6- 20 Timing Example - continued You may harvest a set of trees at anytime over the next 5 years. Given the FV of delaying the harvest, which harvest date maximizes current NPV?
21
© The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw Hill 6- 21 Timing Example - continued You may harvest a set of trees at anytime over the next 5 years. Given the FV of delaying the harvest, which harvest date maximizes current NPV?
22
© The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw Hill 6- 22 Equivalent Annual Cost Equivalent Annual Cost - The cost per period with the same present value as the cost of buying and operating a machine.
23
© The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw Hill 6- 23 Equivalent Annual Cost Equivalent Annual Cost - The cost per period with the same present value as the cost of buying and operating a machine.
24
© The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw Hill 6- 24 Equivalent Annual Cost Example Given the following costs of operating two machines and a 6% cost of capital, select the lower cost machine using equivalent annual cost method.
25
© The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw Hill 6- 25 Equivalent Annual Cost Example Given the following costs of operating two machines and a 6% cost of capital, select the lower cost machine using equivalent annual cost method. Year Machine1234PV@6%EAC A1555528.37 B106621.00
26
© The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw Hill 6- 26 Example Given the following costs of operating two machines and a 6% cost of capital, select the lower cost machine using equivalent annual cost method. Year Machine1234PV@6%EAC A1555528.3710.61 B106621.0011.45 Equivalent Annual Cost
27
© The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw Hill 6- 27 Machinery Replacement Annual operating cost of old machine = 8 Cost of new machine Year: 0 1 2 3 NPV @ 10% 15 5 5 5 27.4 Equivalent annual cost of new machine = 27.4/(3-year annuity factor) = 27.4/2.5 = 11 MORAL: Do not replace until operating cost of old machine exceeds 11.
28
© The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw Hill 6- 28 Cost of Excess Capacity A project uses existing warehouse and requires a new one to be built in Year 5 rather than Year 10. A warehouse costs 100 & lasts 20 years. Equivalent annual cost @ 10% = 100/8.5 = 11.7 0... 5 6... 10 11... With project 0 0 11.7 11.7 11.7 Without project 0 0 0 0 11.7 Difference 0 0 11.7 11.7 0 PV extra cost = + +... + = 27.6 11.7 11.7 11.7 (1.1) 6 (1.1) 7 (1.1) 10
29
© The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw Hill 6- 29 Fluctuating Load Factors
30
© The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw Hill 6- 30 Fluctuating Load Factors
31
© The McGraw-Hill Companies, Inc., 2000 Irwin/McGraw Hill 6- 31 Fluctuating Load Factors
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.