Using MS Project To draw a Network diagram
3
Add tasks Add the 8 tasks listed for making a cup of tea. Add the duration of each –Note: MS Project doesn’t expect seconds – change to hours
4
Tasks entered…
5
Click ‘task’ icon
6
Select ‘schedule tasks’
7
Note icons to schedule tasks
8
To arrange the schedule For bursts: –Select 2 or more tasks You need to hold down the CTRL button to do this. –Click the ‘start to start’ icon. For one task2 following task 1: –Select task 1 –Hold down CTRL button and select task 2 –Click the ‘finish to start’ icon –Note the change in start time / date of the dependent task.
9
To look at the results Using the view menu Choose gantt chart for calendar view. Use Network Diagram to look at the network diagram –Note, it will have fitted in non-critical tasks to run concurrently with the critical path. –The critical path is red.
10
Gantt chart
11
Part of the network diagram