MICE VC 15/3/07Chris Nelson MICE Hall
2
Issues Realistically, I would expect D2 drawings to go for tender by end next week 23/3 but I hope we can use same manufacturer as D1 hence eliminate tender time – back on schedule. Realistically, Quad stand drawings to go for tender by end week following 30/3 The solenoid prep for vacuum work I have proposed for 21/22 March. This allows just enough time to prepare. Hence nose repair hopefully complete by 22nd Trolley weld now complete The plinth is out for tender, I expect to get quotes by end this week, so will achieve date in schedule of placing order by 30/3 latest.