1
Status at DORIS Hall Argus was removed by end of march Argus Parts (except 4 heavy pieces) shipped to Hall 1 Rails of electronics hut have to be extended (ordered) Hut to be moved away from beam for 3 m to allow free access to pit for assembly of OLYMPUS Cables for power, telefon and firedetection to be adapted for movement of electronics hut Will have a fixed cable channel on the floor Jan Hauschildt, MEA1, 26th April 2010
2
Status at DORIS Hall Free space available now for storage and mounting Pipes for gassupply recovered from ZEUS experiment Work on piping started Cables for power of coils : routing fixed and ordered Power supplies and polarity switches : partly moved to DORIS hall Pipes and hoses for water supply : recovered from ZEUS experiment Discussion this morning with MKK → go with 12 bars, have orifice plates in each circuit, go without active regulating valve, replace fitting and hoses with DESY standards Jan Hauschildt, MEA1, 26th April 2010
3
Status at DORIS Hall, Hall 1 Work on shielding design started Work on lead curtain design in DORIS Tunnel started Jan Hauschildt, MEA1, 26th April 2010
4
Status at DORIS Hall, Hall 1 Work on shielding design started Work on lead curtain design in DORIS Tunnel started Hall 1 Wait for parts from Bates to come Free space available now for storage Jan Hauschildt, MEA1, 26th April 2010
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.