Download presentation
Presentation is loading. Please wait.
1
10.7.2007TRD ROC Status Clemens Adler TRD Status Meeting 10.7.07 TRD ROC Status
2
10.7.2007TRD ROC Status Clemens Adler Panels ROB Positioning holes at wrong position –Delivered Panels: redrill with provided template –Other panels: rework at FACC Signal cable cutouts too small on some panels –Rework at FACC (if possible)
3
10.7.2007TRD ROC Status Clemens Adler Padplane problem in Dubna 3 L1C0 Padplanes (type 1) were cut badly by Optiprint. Not noticed at delivery David in Contact with Optiprint
4
10.7.2007TRD ROC Status Clemens Adler Material delivery status Panels: –FACC delayed: Delivery of last panels shifted by 4-5 weeks (August) -> no issue. Glue+Wires: –Christian+Jörg assembling needs for the rest of production.
5
10.7.2007TRD ROC Status Clemens Adler Profile production Front profiles: –One workshop out of the game (machine broken, until ~November) –Production will barely satisfy chamber construction needs. –~250 pc to be done (until ~Feb. 2008) L-profiles: – still ~160 pc. to do (~4 month)
6
10.7.2007TRD ROC Status Clemens Adler Production Status Status 09.07.07 BucharestDubnaFrankfurtGSIHeidelbergSum wired frames 22713 2 26 Taped 241613 tested taped314 glued (tests not completed)1135 tested glued7491218138305 to be repaired 4 4 Sum 357 Rates (wiring) over last ~2 month: Frankfurt: ~0,7 ch/week Heidelberg ~0,7 ch/week (1/week over last 4 weeks, due to additional manpower ) GSI: ~2 ch./week Bucharest/Dubna: Material transport limited
7
10.7.2007TRD ROC Status Clemens Adler Production planning Distribution of 44 ‘homeless’ chambers: –Dubna will most likely take over 22 chambers (L2C1). (Technical details to be discussed). –Bucharest will most likely take over 22 chambers (L3C1). (Technical details to be discussed).
8
10.7.2007TRD ROC Status Clemens Adler ROC Production planning (March, 30th 2007) Status (3/2007) Finished chambers to be done Total: Bucharest:67 41108 Dubna: 91 14103 Frankfurt:27 4471 GSI:68 78 146 Heidelberg:39 46 85 Production rates (historical average): Bucharest: 1 ch/week Dubna:1 ch/week Frankfurt:0.7 ch/week GSI:1.2 ch./week Heidelberg0.5 ch/week Further Production ): Type: # to be done Lab # prod at Lab LxC0: 14 Dubnaall L0C1: 44 Frankfurtall L1C1:46Heidelbergall L2C1:42Bucharest20 L3C142Bucharest20 L4C139GSIall L5C139GSIall Timescale estimate: (assuming 4 weeks Summer vacation, 2 weeks Christmas vacation) LabDuration (weeks)End of prod Bucharest:413/ 2008 Frankfurt:637-8/ 2008 GSI:657-8/ 2008 Heidelberg922/ 2009 +44 chambers which are not included, leading to additional ~44 production weeks.
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.