Presentation is loading. Please wait.

Presentation is loading. Please wait.

MICE Target Schedule Chris Booth Sheffield 12 th June 2006.

Similar presentations


Presentation on theme: "MICE Target Schedule Chris Booth Sheffield 12 th June 2006."— Presentation transcript:

1 MICE Target Schedule Chris Booth Sheffield 12 th June 2006

2 Chris BoothUniversity of Sheffield 2 Key Dates Assembly test R76 (RAL): 24 th -28 th April (past!) Mechanical test R76: 17 th -21 st July Mechanical & Electrical test R76: September Installation & Run in ISIS: Oct. – Nov. Installation for MICE: Summer ‘07

3 Chris BoothUniversity of Sheffield 3 To date: Low power tests (in air) in Sheffield –Demonstrated principles of control & drive –Demonstrated optical readout –Cooling, noise, reliability issues April assembly test & review –Redesign shuttle shaft –Redesign optical window enclosure, fibre alignment system, … –Checks on flanges, indium seals, etc

4 Chris BoothUniversity of Sheffield 4 Now to July Indium seal tests (RAL) Build new shaft (Oxford) Design/build top chamber/readout (Sheffield/RAL) Build new stator (Sheffield) Vacuum tests (Sheffield) Optical isolation of control boards (Sheffield) Optical drive of hex bridge (Sheffield) Improved control & monitoring (Sheffield) Acceleration & temperature tests (in vacuum) (Sheffield) Reliability tests (Sheffield) Mechanical test at RAL 17 th -21 st July –Demonstrate vacuum quality –Demonstrate mechanical compatibility

5 Chris BoothUniversity of Sheffield 5

6 Chris BoothUniversity of Sheffield 6 Now to September Build & test IGBT hex bridge driver (Daresbury) Build second shaft (Oxford) Build second (improved?) stator (Sheffield) Build second top chamber/readout (Sheffield/RAL) New quadrature board for optics (Sheffield) Improved controller hardware & software (Sheffield) ISIS interface boards (Sheffield) Temperature monitoring hardware & s/w (Sheffield) Acceleration tests (at 80 A) (Sheffield) Temperature, reliability tests (at 80 A) (Sheffield) Mechanical & electrical test at RAL 18 th -22 nd September –Demonstrate reliability –Measure vibration etc –Pass ISIS acceptance criteria – not yet defined!

7 Chris BoothUniversity of Sheffield 7

8 Chris BoothUniversity of Sheffield 8 September to October Fix any problems revealed in September! Continue to test & improve controls, interfaces, monitoring November test aims Operation with ISIS – interlocks, synchronisation Run at ISIS startup at 50 Hz/64 or 50 Hz/128 (lower activation, reduced cooling problems, …) Probably only run ~1 shift Measure beam halo profile – determine required insertion depth End of test: Raise above gate valve & close –Maybe run in that position at intervals during ISIS run?

9 Chris BoothUniversity of Sheffield 9 Beyond November Optimisation of stator cooling –Alternative to potting? –Closer cooling elements (eddy currents?) –Multiple coil banks Optimisation of acceleration –Magnet dimensions? –Shaft design (reduce mass) –Optimisation of control (current timing etc) Development of interlocks –Temperature, ISIS beam loss, … Development of monitoring –Temperature –Target profile –Links with MICE monitoring (EPICS) Development of control –Dynamic feedback from monitoring?


Download ppt "MICE Target Schedule Chris Booth Sheffield 12 th June 2006."

Similar presentations


Ads by Google