128 April 2008 Spectrometer Solenoid Fabrication Update MICO Meeting 19 May 2008 S. Virostek, M. Zisman LBNL
2
228 April 2008 Magnet #1 Completion Schedule End plate errors corrected and end-plate welding completed Magnet “tower” components installed and insulated with MLI Tower will be vacuum sealed today and made ready for pumpdown Pumping will take a few days, followed by detailed leak check Barring vacuum problems, magnet cool down will commence Starting May 24 using LN 2 and LHe Week of June 2: magnet filling w/LHe, energizing and magnetic testing Lost about 1 week due to end-plate glitch Instrumentation and power cables being prepared by next week; Wang will provide connectors for instrumentation used at Fermilab and RAL
3
328 April 2008 Cryocooler Testing, FNAL Testing Prep Still under way Currently working on shipping arrangements to FNAL Still have to decide if the magnet will be shipped cold -If shipped warm, need to decide if under vacuum or not -Shipping cold is the current preference
4
428 April 2008 Fabrication Photos (5/16/08) Magnet end view; patch panel end Magnet end view, shield side Cryocooler and HTS lead tower
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.