1 Systems Engineering in Systems Deployment and Retirement Presented to INCOSE by the Minneapolis – St. Paul Chapter of SOLE – The International Society.

Similar presentations


Presentation on theme: "1 Systems Engineering in Systems Deployment and Retirement Presented to INCOSE by the Minneapolis – St. Paul Chapter of SOLE – The International Society."— Presentation transcript:

1 1 Systems Engineering in Systems Deployment and Retirement Presented to INCOSE by the Minneapolis – St. Paul Chapter of SOLE – The International Society of Logistics November 13, 2003

2 2 System Life Cycle Phases Conceptual Design Preliminary System Design Detail Design and Development Production and/or Construction Utilization and Support Retirement and Disposal - Logistics Engineering & Management, 5 th Ed,, B. Blanchard

3 3 Systems Concept Not to be covered – previously covered!! Conceptual Design and Development Systems Design Production and Construction What to cover in this meeting? Utilization and Support You are building this product and are going to deploy it. How do you support it (keep it running)? Retirement and Disposal When is this phase in its operational (service) life? How are your firm, or the buyer, going to get rid of it?

4 4 Utilization Phases Commercial Concept Install Phase Operation & Support Phase Conversion or Decommission Phase Support Analysis “Reliability, Maintainability, & Supportability - RMS” DoD/Military & Space Concept Utilization and Support Phase Retirement & Disposal Support Analysis “Integrated Logistics Support – ILS”

5 5 SUPPORT ANALYSIS Fielded System How to support the system? Leave It on the Loading Dock and Forget It? Have the Customer Mail it Back When It Fails? Have a Field Crew do Repairs? Whose Field Crew? How much will support cost for the life of the system? This Will Determine How You Support the System This Will Also Determine Who Will Pay for Support

6 6 Build & Install System “Key Dimensions” Complexity Varies Consumer products Copy Machines, Sump Pumps Industrial/Commercial products Lighting, Office Products Military systems Ships, Airplanes, Boats Space systems Shuttle, Space Station Mobility Non-mobile (fixed, semi-fixed) Moderately Mobile (vehicle) Highly Mobile (space)

7 7 ILS Elements (DoD/Military) Commercial World has different mix and titles but tasks remain the same Maintenance and Support Planning Maintenance and Support Personnel Supply Support (Spare/Repair Parts and Inventories) Test, Measurement, Handling and Support Equipment Technical Data, Information Systems and Database Structures Training & Training Support Computer Resources (Hardware and Software) Maintenance Facilities Packaging, Handling, Storage/Warehousing & Transportation Disposal Planning

8 8 Post-Sale Time Stages of Systems Distribution/Installation and Initial Use Shipment, setup, construction/installation, test, acceptance System & Equipment Customer Support (post- installation, continuing thru Service Life) This is where you find out if your repair analysis and cost estimates were correct System & Equipment phase-out and Disposition This is governed by the initial support analyses made during design. This cost may make or break a program

9 9 Initial Distribution & Customer Support Distribution and Customer Support – Physical supply and distribution Role of distribution Material management, packaging, transportation, warehousing and handling

10 10 Customer Support (post-sale) Customer support (post-installation) Maintenance and repair Field engineering and data; feedback & use System Configuration Management Configuration Identification & Control Plans Hardware, Software, Firmware Configuration Status Accounting, Authentication Configuration Mgmt Performance Metrics Ongoing engineering change insertion Minor Upgrades (components) Major Upgrades (system)

11 11 LCC Operations Cost Categories operator labor, repair labor, support equipment maintenance, recurring training, repair parts and materials, repair consumables, condemnation spares, technical data revisions, transportation, recurring facilities, recurring item management, software maintenance contractor services, engineering changes, and recurring warranties.

12 12 Operational/Field Data Operational Use Factors Are Significant We must know if a product is being used within the parameters for which it was designed Service Can & Must Be Managed To be cost effective System Service Life Is Generally Long And in these times getting longer Maintenance Can Be Analyzed & Modeled This is an on going process for the life of the product

13 13 Operational/Field Data (cont’d) Life Cycle Costs >> LCC Can Be Calculated with empirical info This info can be used on future products as well as for upgrades on the presently fielded product LCC of Design Options Can Be Compared See if the option we used was the best Minimum LCC Option is Preferred Always

14 14 SE Tasks, Skills and Methods Tasks & Skills Close-loop field failure analysis (hardware) User feedback of applications (software) Processes in use. Human use scenario. Environmental impact. Interface situations. Methods Weibull Analysis Post-installation Configuration management Process analysis. Use analysis. Adaptation impact. Modification impact.

15 15 Maintenance & Phase Out Costs Maintenance & Support Maintenance Management Maintenance Personnel Spare/repair parts and Inventory Control Test and Support Equipment Maintenance Facilities Operator and maintenance training/training equipment Maintenance data Transportation and handling Systems modifications Retirement & Disposal Systems Management System/Product Retirement Disposal of non-repairable condemned items Documentation

16 16 Phase-Out and Disposition Equipment phase-out and Disposition Phase-out and replacement costs Phase Management Costs Demilitarization Costs Handling and processing costs Environmental clean-up costs Unit Disposition, and Scrap (disposal) Reclamation Salvage and reuse of usable components Recycling of basic materials.

17 17 Analytical Models/Tools Categories of Software Tools Reliability & Maintainability Predictions FMECA Process Failure Modes and Effects Analysis Level of Repair Analysis (LOR) Life Cycle Cost (LCC) Analysis LCC Models

18 18 Reference Books DoD, Space & Large Systems “Systems Engineering and Management” 3 rd Ed., by B. Blanchard & W. Fabrycky “Logistics Engineering & Management”, 5 th Ed, by Ben Blanchard “Product Assurance Technologies: Principles and Practices, by Dev G. Raheja, 1995 Military & Commercial Systems “Reliability, Maintainability, Supportability”, 3 rd Ed. By SAE International RMS Committee, 1995. “Reliability and Maintainability Guideline for Manufacturing Machinery and Equipment, 2 nd Ed. SAE International & NCMS, 1999.

19 19 Extension Education Stevens Institute of Technology Office of the SDOE Program, SEEM Department, School of Engineering Systems Design & Operational Effectiveness “Design for System Reliability, Maintainability, and Supportability” SYS 645 “System Supportability & Logistics” SYS 640 One week courses http://www.stevens-tech.edu/sdoe

20 20 SOLE & References Visit web site at http://www.sole.orghttp://www.sole.org SAE International at http://www.sae.orghttp://www.sae.org CASA 8.0 Life Cycle Cost tool (free downloadable, see http://www.logsa.army.mil/alc/casa/ ) (9.47 MB) http://www.logsa.army.mil/alc/casa/ Commercial Service Concepts AFSMI at http://www.afsmi.orghttp://www.afsmi.org This brief presented by: Larry DeVries, CPL at larrydev@earthlink.net Joe O’Brien, CPL at j.f.obrien@worldnet.att.net

21 21 LCC Tool What is CASA? The Cost Analysis Strategy Assessment (CASA) model is a Life Cycle Cost (LCC)/Total Ownership Cost (TOC) decision support tool. CASA can present the total cost of ownership depending on user selections: including cost of RDT&E, acquisition/production, operating/support, and disposal. CASA covers the entire life of the system, from its initial research costs to those associated with yearly maintenance, as well as spares, training costs, and other expenses. CASA uses standard LCC/TOC and logistics equations for the computation of costs and resource requirements. CASA also enables optimization of spares allocation to be performed. The link to free downloadable executable: CASA 8.0 (free downloadable, see http://www.logsa.army.mil/alc/casa/ )http://www.logsa.army.mil/alc/casa/

22 22 THANK YOU!! SOLE – The International Society of Logistics