City of Houston Core Infrastructure Roadmap Architecture and Discovery
2
Purpose Outline overall time-phasing and roadmap for the following projects –Enterprise Infrastructure Architecture –Discovery and Due Diligence for Seats Management –Transition for Seats Management –Windows/Exchange 2000
3
Enterprise Architecture Multi-year strategic infrastructure plan Overall duration 8-10 weeks –Design Review at 3 weeks –Final review & presentation at completion Key Deliverables –Current state architecture –Future state architecture –Gap identification and key priority recommendations
4
Discovery and Due Diligence Basis for final SOW for Seats Management Duration: 16 weeks Key deliverables –Set of detailed assessment reports –Roadmap to enter Seats Management Transition activities & plan SLAs and other contractual agreements Service management plans
5
Discovery and Due Diligence Focus areas: –Deskside/break fix infrastructure and equipment –Network topology and equipment –Server infrastructure and equipment –Applications environment –Messaging –Support infrastructure and environment
6
Windows/Exchange 2000 Enterprise wide design, pilot, and implementation planning Duration: 22 weeks –Multiple milestones Key Deliverables –Detailed Win2k/Exchange 2k Design –Lab environment with detailed test plans/results –Pilot –Deployment plans for the enterprise
7
Overall Roadmap Week 1Kickoff and architecture interviews Week 3Architecture Design Review Discovery activities begin Kickoff Windows/Exchange project Week 4Build Windows/Exchange Lab Windows/Exchange test planning Win/Exchange high-level design Week 7Win/Exchange Detailed Design
8
Overall Roadmap cont Week 10Final Architecture presented Week 14Win/Exch design review Week 15Win/Exch pilot Week 18Due Diligence Complete Week 19Transition to Seats Management Week 20Win/Exch Deployment planning Week 27Win/Exch planning complete