Linda R. Coney – 24th September 2009 MOM Update End of Sept Run Linda R. Coney 05 October, 2009
2
Linda R. Coney – 5 Oct 2009 Outline Taking Data Studies Done Target Operations Progress Made 2
3
Linda R. Coney – 5 Oct 2009 Recent Data Taking Program Since working on the DAQ last week (see VC slides V.Verguilov): Positive beam particles: u 300 MeV/c pions - 4000 target pulses (translates to about 330,000 particles used for calibrating the TOF system) u 250 MeV/c pions - 350 target pulses (also for TOF) u 200 MeV/c pions - 450 pulses (also for TOF) u 300 MeV/c positrons - 1500 target pulses (calibration of CKOV and KL calorimeter) u 150 MeV/c positrons - 1200 target pulses (calibration of CKOV and KL calorimeter) u 330 MeV/c pions for study of Decay Solenoid effects on beam optics - 2000 pulses u 444 MeV/c piplus -to- muon beam s to understand beam optics for producing muons - 500 pulses u Pion beam at 330 MeV/c – Decay Solenoid beam dynamics study s Nominal setting at 550 A (3.1 T) s 9 settings higher and lower in steps of 0.15 T s Only required ~60 target pulses/point to get sufficient counts in TOF0 3
4
Linda R. Coney – 5 Oct 2009 DS Study Pion Beam at 330 MeV/c – Decay Solenoid beam dynamics study u Nominal setting at 550 A (3.1T) u 9 settings higher and lower in steps of 0.15 T u 100 target pulses/point to get sufficient counts in TOF0 Run 1121 DS current down 0.30T 4
5
Linda R. Coney – 5 Oct 2009 DS Study II – Positive Particles Run 1122 DS current lower 0.15T Run 1123 Nominal DS current Run 1124 DS current up 0.15T Run 1125 DS current up 0.30T 5
6
Linda R. Coney – 5 Oct 2009 Recent Data Taking Program II Since working on the DAQ last week (see VC slides V.Verguilov): Friday – switched beamline polarity Now running Negative beam particles: u 300 MeV/c pi- : 2800 target pulses (calibrating the TOF system) u 300 MeV/c electrons - 1500 target pulses (calibration of CKOV and KL calorimeter) u 150 MeV/c electrons - 1200 target pulses (calibration of CKOV and KL calorimeter) u 330 MeV/c pi- for particle rate vs beam loss study s 50mV, 100mV, 200mV, 300mV, 400 mV, 500 mV losses – 400 pulses/point (2400) u 444 MeV/c piplus -to- muon beam - 1500 u 337 MeV/c piplus -to- muon beam – 1550 u Optimization of Upstream Beamline 6
7
Linda R. Coney – 5 Oct 2009 Recent Data – 300 MeV/c pi- Run 1172: 300 MeV/c pi- 7
8
Linda R. Coney – 5 Oct 2009 Recent Data – 444 MeV/c pi- to mu- Run 1176: 444 MeV/c pi- to mu- (Saturday Oct3) 8
9
Linda R. Coney – 5 Oct 2009 Recent Data – 444 Mev/c pi+ to mu+ Run 1163: 444 MeV/c pi+ to mu+ (Thursday Oct1) 9
10
Linda R. Coney – 5 Oct 2009 Muon Particle Rate Study An initial study of muons in TOF1 as a function of beamloss was also done using a 337 MeV/c at target pi- to mu- beamline u 100mV - 15 particle triggers/spill TOF0 - 4.2 muons/spill in TOF1 (assuming all hits are muons) u 200mV - 34 particle triggers/spill TOF0 - 8.6 muons/spill TOF1 u 300mV - 44 particle triggers/spill TOF0 - 10.7 muons/spill TOF1 u 400mV - 60 particle triggers/spill TOF0 - 16.1 muons/spill TOF1 u 500mV - 71 particle triggers/spill TOF0 - 19.1 muons/spill TOF1 10
11
Linda R. Coney – 5 Oct 2009 Optimization of Upstream Beamline Simulation – triangles Data from Sunday - circles 11
12
Linda R. Coney – 5 Oct 2009 Target Performance Continues to do well – no problems Stopped at 50,000 pulses at end of running Thursday Sat/Sun – went on to final count of 62,650 Target depth Beam loss over time 200 MeV/c pi+ Inspected Sunday 12
13
Linda R. Coney – 5 Oct 2009 Target DAQ Target DAQ Moving closer 13
14
Linda R. Coney – 5 Oct 2009 Target Run Information Beam Loss/target position pi- to mu- beam 611 mV BCD = 28.4 14
15
Linda R. Coney – 5 Oct 2009 Target Run Information II Beam Loss/target position/dip timing pi- to mu- beam (Sat) 611 mV BCD = 28.7 15
16
Linda R. Coney – 5 Oct 2009 Detectors KL installed/bolted to TOF1 u Incorporated into DAQ again u Problem with one FADC module – 6 channels on top of detector TOF0 ch. 17 PMT still not reading out All FADCs (except PMT 17) look good u Plots: 300 MeV/c electrons FNAL BPMs not running now u Hardware problem probably – need check into veto/load signals PMT 17 PMT 18 FADCs 16
17
Linda R. Coney – 5 Oct 2009 Recent Data: TOF Calibration Beginning to calibrate TOFs Last year’s data……..This year… Making progress..need more data.. 2009: 300 MeV/c more statistics 2009 330 MeV/c 2008 17
18
Linda R. Coney – 5 Oct 2009 Operations I eLOG u Moved to IIT u Works great! Fantastic! u Temporary solution while work w/RAL networking to sort out heplnw17 Magnets: u D2 s magnet H2O trips, Willie increased water flow slightly on access to DSA Wed s No problems since u Q4 s MPS water flow trips – Thursday every 45 minutes during running s Swapped out flow sensor Friday s Now ok – no trips over weekend s Danfysik will replace all flow sensors u Polarity switched u Capacity of distribution board checked s Ok – need few new fuses – may still want upgrade u Slow ramp of magnets – s Software written s Tested and did not work – ongoing Beamstop not always cooperative – possible faulty controller connection 18
19
Linda R. Coney – 5 Oct 2009 Operations II PPS u Need rack to RAL u John Alexander to RAL to integrate DSA into ISIS system – TBC Shifters u Many thanks to my shifters s especially Pierrick Hanlet, Henry Nebrensky, and Ray Gamet s here for 1 week each! s Working very hard for MICE Alarm Handler u Still need to sort out sound card u Need Decay Solenoid PVs into alarm handler to assist monitoring u Need DAQ variables into Alarm Handler Need to understand ISIS beam loss vs MICE in MLCR u What exactly defines our limits? 19
20
Linda R. Coney – 5 Oct 2009 Next ISIS shutdown Oct 5 – Nov 1 Machine Physics period starts Nov 2 – need shifters User Run ~Nov 9 through Dec 20 – need shifters Next User Run – Feb/March 2010 Calibrate detectors Study effect of proton absorber? Build during shutdown Install luminosity monitor 20
21
Linda R. Coney – 5 Oct 2009 Conclusions Within the last month: We are running again New target Higher loss limits Decay Solenoid Operational! Routinely used. Detectors working Good NEWS – u Learning a LOT u Last year < 50 particles/spill, Now: averaging 160 – 200 u Running with negative or positive particles u We have seen MUONS! 21