Download presentation
Presentation is loading. Please wait.
1
Telecommunications Project Management Quality Management PERT
2
Quality ISO 9000 “Totality of feature and characteristics of a product or service that bears on its ability to satisfy stated or implied needs” Figure 20-1
3
Quality Control Equipment design Project quality ≠ Management of operations Telecom: Service = Product Project quality and Operations quality boundary unclear Quality control Verify project deliverables comply with standards set Take action if needed
4
Telecom Quality Control Overlapping requirements 1.Network operations and maintenance 2.End-user experience Include internal workers If well executed and follow best practices may still lead to failure
5
Quality and Innovation Identify demographics Identify needs →Project specs Sustaining innovations Oral transmission of knowledge Social interactions Service platform innovations More involved due to technology leap More uncertainty Disruptive innovations Customer profile fuzzy & expectations tentative Reinvent the “wheel” Quality decisions pass from engineers to lawyers and accountants
6
Quality and Cost Prevention cost – Cost of all activities to prevent known defects from affecting agreed service levels Appraisal cost – Cost during evaluation of equipment due to inspections, tests, etc. Failure cost – Cost of experiencing a failure during operation
7
Quality Examples PSTN Lasts 30 or more minutes & disrupts 1000 subscribers Causes loss of service to a government response agency Must report to the Network Reliability Council any outage that affects 30,000 subscribers >30 minutes
8
Quality Examples Enhanced services (data, VoIP) Defined by service level agreements (SLA) More than 5% of active ports unusable for >30 minutes More than 10% of active ports unusable QoS agreements Table 8.1
9
Service Release Management Total Quality cost = Prevention cost + appraisal cost + failure cost <Upper bound cost of quality Appraisal cost < Prevention cost + failure cost Table 8.2
10
Quality Plan 1.Quality targets – performance limits within that service will meet sponsor’s objectives 2.Resources allocated for implementation – features & methods to be tested & expected behavior 3.Data collection – what to be complied accuracy & relationship (I.e. hardware failures not included in software reliability) 4.Data analysis – track project progress
11
Quality Plan 5.Improvement plan – resolve difference between observed and desired behaviors 6.Communication – inform customer concerning project status 7.Retain methodology and information
12
Categorization of Defects: Urgency and Criticality Figure 8.1 Table 8.4
13
Appraisal 1.Unit/Module Tests 2.Functional Tests 3.Integration Tests 4.Systems/Software Quality Assurance test (SQA) 5.Customer Acceptance Testing
14
Telecom Non-Incremental Innovation Figure 8.3
15
Evaluation of Testing Progress 1.Number of test cases executed, passed, failed and blocked 2.Progress 3.Percentage and number of tests passed 4.Number of unresolved critical or major defects 5.Number of defects without root cause analysis: could not be solved with available resources 6.Turnaround time for defect resolution
16
When to Stop Testing Vendor fixed all critical defects discovered and all major defects that do not have acceptable workarounds Finding of defects is typically zero after all tests After all tests completed, expected number of critical or major problems less than predefined number
17
Vendor Management During Testing Figure 8.10
18
Total Quality Management (TQM) System for integrating organizational elements into: Design Development Manufacturing efforts Cost-effective products/services to customer Externally – Customer oriented & provides customer satisfaction Internally – Reduces production line bottlenecks and operating costs – improves product quality and organizational morale
19
Program Evaluation and Review Technique (PERT) Similar to Critical Path Method (CPM) Requirements: Individual tasks must be clear enough to put in a network (WBS) Events and activities must be sequenced that allow critical and sub-critical paths (10 - >100) Time estimates made on a three way basis Optimistic, most likely, pessimistic Critical path and slack times computed
20
PERT advantages Extensive planning Network development and critical path show interdependencies and problems otherwise hidden Determine the probability of meeting deadlines by developing alternative plans Ability to evaluate effect of changes Large amount of sophisticated data presented in a well-organized diagram
21
PERT Disadvantages Complexity adds to implementation problems More data requirements Expensive to maintain Utilized most often on large, complex programs
22
Network Events and Activities Event – milestone Activity – Element of work that must be accomplished Duration – Total time required to complete activity Effort – Amount of work actually performed during duration Critical Path – Longest path through the network and determines the duration of the project
23
Standard PERT terms Figure 12-1
24
Gantt vs. PERT Chart Figure 12-3
25
Series vs. Parallel PERT Chart Figure 12-13
26
Expected Time Between Events t e = a + 4m + b --------------- 6 t e = expected time a = most optimistic time b = most pessimistic time m = most likely time
27
Estimate Total Project Time σ t e = b – a ------ 6 σ t e = standard deviation of the expected time Figure 12-15
28
PERT Disadvantages End-item oriented – removes ability to make decisions Unless repetitive project – little historical information to base cost estimates of most optimistic, most pessimistic, and most likely Each division of organization may use its own method for estimating costs
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.