4/8: Cost Propagation & Partialization Today’s lesson: Beware of solicitous suggestions from juvenile cosmetologists Exhibit A: Abe Lincoln Exhibit B:

Similar presentations


Presentation on theme: "4/8: Cost Propagation & Partialization Today’s lesson: Beware of solicitous suggestions from juvenile cosmetologists Exhibit A: Abe Lincoln Exhibit B:"— Presentation transcript:

1 4/8: Cost Propagation & Partialization Today’s lesson: Beware of solicitous suggestions from juvenile cosmetologists Exhibit A: Abe Lincoln Exhibit B: Rao Next Class: LPG—ICAPS 2003 paper. *READ* it before coming. Homework on SAPA coming from Vietnam

2 Multi-objective search  Multi-dimensional nature of plan quality in metric temporal planning:  Temporal quality (e.g. makespan, slack)  Plan cost (e.g. cumulative action cost, resource consumption)  Necessitates multi-objective optimization:  Modeling objective functions  Tracking different quality metrics and heuristic estimation  Challenge: There may be inter-dependent relations between different quality metric

3 Example  Option 1: Tempe  Phoenix (Bus)  Los Angeles (Airplane)  Less time: 3 hours; More expensive: $200  Option 2: Tempe  Los Angeles (Car)  More time: 12 hours; Less expensive: $50  Given a deadline constraint (6 hours)  Only option 1 is viable  Given a money constraint ($100)  Only option 2 is viable Tempe Phoenix Los Angeles

4 Solution Quality in the presence of multiple objectives  When we have multiple objectives, it is not clear how to define global optimum  E.g. How does plan compare to ?  Problem: We don’t know what the user’s utility metric is as a function of cost and makespan.

5 Solution 1: Pareto Sets  Present pareto sets/curves to the user  A pareto set is a set of non-dominated solutions  A solution S1 is dominated by another S2, if S1 is worse than S2 in at least one objective and equal in all or worse in all other objectives. E.g. dominated by  A travel agent shouldn’t bother asking whether I would like a flight that starts at 6pm and reaches at 9pm, and cost 100$ or another ones which also leaves at 6 and reaches at 9, but costs 200$.  A pareto set is exhaustive if it contains all non-dominated solutions  Presenting the pareto set allows the users to state their preferences implicitly by choosing what they like rather than by stating them explicitly.  Problem: Exhaustive Pareto sets can be large (non-finite in many cases).  In practice, travel agents give you non-exhaustive pareto sets, just so you have the illusion of choice  Optimizing with pareto sets changes the nature of the problem—you are looking for multiple rather than a single solution.

6 Solution 2: Aggregate Utility Metrics  Combine the various objectives into a single utility measure  Eg: w1*cost+w2*make-span  Could model grad students’ preferences; with w1=infinity, w2=0  Log(cost)+ 5*(Make-span) 25  Could model Bill Gates’ preferences.  How do we assess the form of the utility measure (linear? Nonlinear?)  and how will we get the weights?  Utility elicitation process  Learning problem: Ask tons of questions to the users and learn their utility function to fit their preferences  Can be cast as a sort of learning task (e.g. learn a neual net that is consistent with the examples)  Of course, if you want to learn a true nonlinear preference function, you will need many many more examples, and the training takes much longer.  With aggregate utility metrics, the multi-obj optimization is, in theory, reduces to a single objective optimization problem  *However* if you are trying to good heuristics to direct the search, then since estimators are likely to be available for naturally occurring factors of the solution quality, rather than random combinations there-of, we still have to follow a two step process 1.Find estimators for each of the factors 2.Combine the estimates using the utility measure THIS IS WHAT WE WILL DO IN THE NEXT FEW SLIDES

7 Our approach  Using the Temporal Planning Graph (Smith & Weld) structure to track the time-sensitive cost function:  Estimation of the earliest time (makespan) to achieve all goals.  Estimation of the lowest cost to achieve goals  Estimation of the cost to achieve goals given the specific makespan value.  Using this information to calculate the heuristic value for the objective function involving both time and cost  New issue: How to propagate cost over planning graphs?

8 The (Relaxed) Temporal PG Tempe Phoenix Los Angeles Drive-car(Tempe,LA) Heli(T,P) Shuttle(T,P) Airplane(P,LA) t = 0t = 0.5t = 1t = 1.5 t = 10

9 Time-sensitive Cost Function  Standard (Temporal) planning graph (TPG) shows the time-related estimates e.g. earliest time to achieve fact, or to execute action  TPG does not show the cost estimates to achieve facts or execute actions Tempe Phoenix L.A Shuttle(Tempe,Phx): Cost: $20; Time: 1.0 hour Helicopter(Tempe,Phx): Cost: $100; Time: 0.5 hour Car(Tempe,LA): Cost: $100; Time: 10 hour Airplane(Phx,LA): Cost: $200; Time: 1.0 hour cost time 0 1.5210 $300 $220 $100  Drive-car(Tempe,LA) Heli(T,P) Shuttle(T,P) Airplane(P,LA) t = 0t = 0.5t = 1t = 1.5 t = 10

10 Estimating the Cost Function Tempe Phoenix L.A time 01.5210 $300 $220 $100  t = 1.5 t = 10 Shuttle(Tempe,Phx): Cost: $20; Time: 1.0 hour Helicopter(Tempe,Phx): Cost: $100; Time: 0.5 hour Car(Tempe,LA): Cost: $100; Time: 10 hour Airplane(Phx,LA): Cost: $200; Time: 1.0 hour 1 Drive-car(Tempe,LA) Hel(T,P) Shuttle(T,P) t = 0 Airplane(P,LA) t = 0.5 0.5 t = 1 Cost(At(LA))Cost(At(Phx)) = Cost(Flight(Phx,LA)) Airplane(P,LA) t = 2.0 $20

11 Cost Propagation  Issues:  At a given time point, each fact is supported by multiple actions  Each action has more than one precondition  Propagation rules:  Cost(f,t) = min {Cost(A,t) : f  Effect(A)}  Cost(A,t) = Aggregate(Cost(f,t): f  Pre(A))  Sum-propagation:  Cost(f,t)  The plans for individual preconds may be interacting  Max-propagation: Max {Cost(f,t)}  Combination: 0.5  Cost(f,t) + 0.5 Max {Cost(f,t)} Probably other better ideas could be tried Can’t use something like set-level idea here because That will entail tracking the costs of subsets of literals

12 Termination Criteria  Deadline Termination: Terminate at time point t if:   goal G: Dealine(G)  t   goal G: (Dealine(G) < t)  (Cost(G,t) =   Fix-point Termination: Terminate at time point t where we can not improve the cost of any proposition.  K-lookahead approximation: At t where Cost(g,t) < , repeat the process of applying (set) of actions that can improve the cost functions k times. cost time 0 1.5210 $300 $220 $100  Drive-car(Tempe,LA) H(T,P) Shuttle(T,P) Plane(P,LA) t = 0 0.5 1 1.5 t = 10 Earliest time point Cheapest cost

13 Heuristic estimation using the cost functions  If the objective function is to minimize time: h = t 0  If the objective function is to minimize cost: h = CostAggregate(G, t  )  If the objective function is the function of both time and cost O = f(time,cost) then: h = min f(t,Cost(G,t)) s.t. t 0  t  t  Eg: f(time,cost) = 100.makespan + Cost then h = 100x2 + 220 at t 0  t = 2  t  time cost 0 t 0 =1.52t  = 10 $300 $220 $100  Cost(At(LA)) Earliest achieve time: t 0 = 1.5 Lowest cost time: t  = 10 The cost functions have information to track both temporal and cost metric of the plan, and their inter-dependent relations !!!

14 Heuristic estimation by extracting the relaxed plan  Relaxed plan satisfies all the goals ignoring the negative interaction:  Take into account positive interaction  Base set of actions for possible adjustment according to neglected (relaxed) information (e.g. negative interaction, resource usage etc.)  Need to find a good relaxed plan (among multiple ones) according to the objective function

15 Heuristic estimation by extracting the relaxed plan  Initially supported facts: SF = Init state  Initial goals: G = Init goals \ SF  Traverse backward searching for actions supporting all the goals. When A is added to the relaxed plan RP, then: SF = SF  Effects(A) G = (G  Precond(A)) \ Effects  If the objective function is f(time,cost), then A is selected such that: f(t(RP+A),C(RP+A)) + f(t(G new ),C(G new )) is minimal (G new = (G  Precond(A)) \ Effects)  When A is added, using mutex to set orders between A and actions in RP so that less number of causal constraints are violated time cost 0 t 0 =1.52t  = 10 $300 $220 $100  Tempe Phoenix L.A f(t,c) = 100.makespan + Cost

16 Heuristic estimation by extracting the relaxed plan  General Alg.: Traverse backward searching for actions supporting all the goals. When A is added to the relaxed plan RP, then: Supported Fact = SF  Effects(A) Goals = SF \ (G  Precond(A))  Temporal Planning with Cost: If the objective function is f(time,cost), then A is selected such that: f(t(RP+A),C(RP+A)) + f(t(G new ),C(G new )) is minimal (G new = (G  Precond(A)) \ Effects)  Finally, using mutex to set orders between A and actions in RP so that less number of causal constraints are violated time cost 0 t 0 =1.52t  = 10 $300 $220 $100  Tempe Phoenix L.A f(t,c) = 100.makespan + Cost

17 Adjusting the Heuristic Values Ignored resource related information can be used to improve the heuristic values (such like +ve and –ve interactions in classical planning) Adjusted Cost: C = C +  R  (Con(R) – (Init(R)+Pro(R)))/  R  * C(A R )  Cannot be applied to admissible heuristics

18 4/10

19 Partialization Example A1A2A3 A1(10) gives g1 but deletes p A3(8) gives g2 but requires p at start A2(4) gives p at end We want g1,g2 A position-constrained plan with makespan 22 A1 A2 A3 G p g1 g2 [et(A1) = st(A3)] [et(A2) <= st(A3) …. Order Constrained plan The best makespan dispatch of the order-constrained plan A1 A2A3 14+  There could be multiple O.C. plans because of multiple possible causal sources. Optimization will involve Going through them all.

20 Problem Definitions  Position constrained (p.c) plan: The execution time of each action is fixed to a specific time point  Can be generated more efficiently by state-space planners  Order constrained (o.c) plan: Only the relative orderings between actions are specified  More flexible solutions, causal relations between actions  Partialization: Constructing a o.c plan from a p.c plan Q R R G Q RR {Q} {G} t1t1 t2t2 t3t3 p.c plano.c plan Q R R G Q RR {Q} {G}

21 Validity Requirements for a partialization  An o.c plan P oc is a valid partialization of a valid p.c plan P pc, if:  P oc contains the same actions as P pc  P oc is executable  P oc satisfies all the top level goals  (Optional) P pc is a legal dispatch (execution) of P oc  (Optional) Contains no redundant ordering relations P Q P Q X redundant

22 Greedy Approximations  Solving the optimization problem for makespan and number of orderings is NP-hard (Backstrom,1998)  Greedy approaches have been considered in classical planning (e.g. [Kambhampati & Kedar, 1993], [Veloso et. al.,1990]):  Find a causal explanation of correctness for the p.c plan  Introduce just the orderings needed for the explanation to hold

23 Partialization: A simple example Pickup(A)Stack(A,B)Pickup(C)Stack(C,D) Pickup(A) Stack(A,B) Pickup(C) Stack(C,D) On(A,B) On(C,D) Holding(B) Holding(C) Hand-empty

24 Modeling greedy approaches as value ordering strategies  Variation of [Kambhampati & Kedar,1993] greedy algorithm for temporal planning as value ordering:  Supporting variables: S p A = A’ such that:  et p A’ < st p A in the p.c plan P pc   B s.t.: et p A’ < et  p B < st p A   C s.t.: et p C < et p A’ and satisfy two above conditions  Ordering and interference variables:   p AB = if st  p B > st p A   r AA’ = if st r A > et r A’ in P pc ;  r AA’ =  other wise. Key insight: We can capture many of the greedy approaches as specific value ordering strategies on the CSOP encoding

25 CSOP Variables and values  Continuous variables:  Temporal: st A ; D(st A ) = {0, +  }, D(st init ) = {0}, D(st Goals ) = {Dl(G)}.  Resource level: V r A  Discrete variables:  Resource ordering:  r AA’ ; Dom(  r AA’ ) = { } or Dom(  r AA’ ) = {,  }  Causal effect: S p A ; Dom(S p A ) = {B 1, B 2,…B n }, p  E(B i )  Mutex:  p AA’ ; Dom(  p AA’ ) = { }; p  E(A),  p  E(A’) U P(A’) Q R R G Q RR {Q} {G} A1A1 A2A2 A3A3 Exp: Dom(S Q A2 ) = {A ibit, A 1 } Dom(S R A3 ) = {A 2 }, Dom(S G Ag ) = {A 3 }  R A1A2,  R A1A3

26 Constraints  Causal-link protection:  S p A = B   A’,  p  E(A’): (  p A’B = )  Ordering and temporal variables:  S p A = B  et p B < st p A   p A’B =  et  p A > st p A’   r AA’ =  st r A > et r A’  Optional temporal constraints:  Goal deadline: st Ag  t g ;  Time constraints on individual actions: L  st A  U  Resource precondition constraints:  For each precondition V r A  K,  = {>,<, , ,=} set up one constraint involving all  r AA’ such as:  Exp: Init r +  A’ K if  = >

27 Modeling Different Objective Functions  Temporal quality:  Minimum Makespan: Minimize Max A (st A + dur A )  Maximize summation of slacks: Maximize  (st g Ag - et g A ); S g Ag = A  Maximize average flexibility: Maximize Avg(Dom(st A ))  Fewest orderings:  Minimize #(st A < st A’ )

28 Empirical evaluation  Objective:  Demonstrate that metric temporal planner armed with our approach is able to produce plans that satisfy a variety of cost/makespan tradeoff.  Testing problems:  Randomly generated logistics problems from TP4 (Hasslum&Geffner) Load/unload(package,location): Cost = 1; Duration = 1; Drive-inter-city(location1,location2): Cost = 4.0; Duration = 12.0; Flight(airport1,airport2): Cost = 15.0; Duration = 3.0; Drive-intra-city(location1,location2,city): Cost = 2.0; Duration = 2.0;

29 LPG Discussion—Look at notes of Week 12 (as they are more uptodate)