Status at P2 C. Lippmann Jan. 22, 2007 TRD DCS workshop at PI, Heidelberg
2
2007 January 22ndC. Lippmann2 The TPC at P2
3
2007 January 22ndC. Lippmann3 Super Module In final position since december 2006.
4
2007 January 22ndC. Lippmann4 Cables (1) Status LV cables: On A side: Sectors 12-15 cabled on SM side On C side: First cables
5
2007 January 22ndC. Lippmann5 Cables (2) Baby space frame (A side): HV done. Ethernet Y cables done. There was the request that we verify these cables soon.
6
2007 January 22ndC. Lippmann6 LV Power Supplies (1) LV supplies for sector 8 (in racks O27, O28) and pretrigger C side (in racks O29, I29) installed. O27 O28
7
2007 January 22ndC. Lippmann7More Netgear Switches: Many installed HV distribution: No change since october. Needs safety revision.
8
2007 January 22ndC. Lippmann8Safety Procedure to enable and disenable powering of the electric racks in the ALICE areas was defined. To guarantee safety of the personnel. Important for our commissioning.
9
2007 January 22ndC. Lippmann9