Report on E-165 Steve Schnetzer MCC Meeting June 28
2
Last 24 Hours Completed high intensity running Checked linearity of PMT’s PMT’s at low gain x 10 amp complete set of runs (0,2,4,6,8,10,12,14 r.l.) Started lateral shower profile measurement Diamond detectors Removed optical box 9 measurements in x 4(3) measurements in z 4 targets (2,6,10,14 r.l)
3
Diamond Shower Profile Plot agreement with Geant calculation distance from beam axis (cm)
4
Diamond Linearity good linearity 10 -7 C of charge deposited ! 1 A over 100 ns
5
Diamond Linearity 10 times more charge with 6 r.l. still good linearity charge density lower study density effect by taking data with different beam spot size
6
Next 24 Hours Continue lateral shower profile measurement Install and debug ionization chamber