STATUS of 6m ANTENNA RELOCATION Matt Fleming 8/24/04
2
Moving contract Original estimate (Nov 2002) –Heavy Transport $764K RFP revised, competitive bidding: –Heavy Transport $496 K –Sheedy Crane $336 K –Bigge Crane $330 K Contract issued to Bigge Crane (Jul 2004)
3
Move plan: 2 trucks/antenna
4
DISASSEMBLY Done for 5 antennas, 4 remain
5
PARTS READY FOR LOADING
6
STAFF ON THE JOB Al Masters (no longer available) Mark Masters Jim & Calvin LesDavid (gone) Not shown: Jim Wirth & Matt
7
LIFT & SUPPORT ITEMS Yoke bearing lifter Shown with spreader bar 2 required per antenna Pedestal support frame To be used while legs are removed 1 required for project Stays at Hat Creek Yoke & pedestal below
8
TASKS REMAINING Fabricate lift & support items ( Bigge, hopefully ) Meeting with Bigge Sept.1 ( to detail above ) Continue preparations & wrap of 4 more antennas. Modify AZ cable chain supports on all antennas if possible. Remove dishes on last 4 antennas Sept. 13,14,15 Final wrap and preparation of containers. Preparation of Cedar Flat unload area. Begin moving operation Sept. 27