Download presentation
1
Project Management Cost Control
2
Outline Introduction Understanding Control The Operating Cycle
Cost Account Codes Budgets The Earned Value Measurement System( EVMS) Variance and Earned Value
3
Outline The Cost Baseline Justifying the Costs
The Cost Overrun Dilemma Recording Material Costs Using Earned Value Measurement The Material Accounting Criterion Material Variances : Price and Usage Summary Variances
4
Outline Status Reporting Cost Control Problems
5
Introduction Do project managers control costs, monitor costs or both?
Cost control is not only “monitoring” costs and recording data, but also analyzing the data in order to take corrective action before it is too late.
6
Cost Management Cost estimating Cost accounting Project cash flow
Company cash flow Direct labor costing Overhead rate costing Others, such as incentives, penalties, and profit-sharing
7
Cost And Control System
PLANNING WORK AUTHORIZATION AND RELEASE DATA COLLECTION AND REPORTING COST ACCOUNTING CUSTOMER AND MANAGEMENT REPORTING PHASE I PHASE II PHASE III PHASE IV PHASE V PLANNING OPERATING CYCLE CYCLE
8
Cost Control Requirements
Measure resources consumed Measure status and accomplishments Compare measurements to projections and standards Provide the basis for diagnosis and re-planning
9
Cost Control Activities
Contract receipt (if applicable) Work authorization for project planning Work breakdown structure Subdivided work description Schedules Planning charts Budgets
10
Cost Control Requirements
Thorough planning of the work to be performed to complete the project Good estimating of time, labor, and costs Clear communication of the scope of required tasks A disciplined budget and authorizations of expenditures Timely accounting of physical progress and cost expenditures Periodic re-estimation of time and cost to complete remaining work
11
Cost Control Requirements (Continued)
Frequent, periodic comparison of actual progress and expenditures to schedules and budgets, both at the time of comparison and at project completion
12
Purposes of Cost Control (1/2)
Verification The objectives have been successfully translated into performance standards The performance standards are, in fact, a reliable representation of program activities and events Meaningful budgets have been established such that actual versus planned comparison can be made
13
Purposes of Cost Control (2/2)
Decision making via three reports The project plan, schedule, and budget prepared during the planning phase A detailed comparison between resources expended to date and those predetermined. A projection of resources to be expended through program completion
14
When to Implement a Cost Management System
Possible cost reductions Cost of change PROJECT COSTS PROJECT LIFE CYCLE PHASES CONCLUSION A cost management system should be implemented right at the beginning of the life cycle of the project.
15
Ability to Influence Cost
16
Cost Account Intersection
17
Cost Account Code Breakdown
18
Work Authorization Form
WBS: Work order no: D1385 Date of original release: Feb 97 Date of revision: March 97 Revision number: C Cost Work Work Centers Hours Cost Starts Ends Description - Test Material R Aug Sept - Processing R7500 - Final inspection R3500 - Packaging R 750 - Delivery R 350 Project office authorization signature:________________
19
Planning and Budgeting
WBS Element Work Package Work packages M G R Org WP______ORG_______ Description of task_____ ____________________ Sched: Start____Stop__ Budget:______________ Org Org
20
CACN No. _____________ Revision to Cost Account No
CACN No. _____________ Revision to Cost Account No. ____________ Date ___________ DESCRIPTION OF CHANGE: ____________________________________________________________________________________ REASON FOR CHANGE: __________________________________________________________________________________ Requested Budget Authorized Budget Labor Hours _________________ _________________ Period of performance Materials _________________ _________________ From _____________ ODCS _________________ _________________ To _____________ BUDGET SOURCE: Funded Contract Change Management Reserve Undistributed Budget Other _________________ INITIATED BY: ____________________________ APPROVALS: Program Mgr. ________ Prog. Control ________ COST ACCOUNT CHANGE NOTICE (CACN)
21
Sources Of Additional Funding
Funded contract change Management reserve Undistributed budget Other (e.g. profits)
22
Cost data collation and reporting flow chart
Actuals Monthly Total Program Effort BCWP Labor Weekly Labor Reports ACWP Computer MCCS Comparison reports To All Execs Inventory Accounts BCWS Variance Report ACWP: Actual Cost for Work Performed BCWP: Budgeted Cost for Work Performed BCWS: Budgeted Cost for Work Scheduled MCCS: Management Cost and Control System
23
Cost Data Labor Material Other direct charges Overhead
24
Weekly Labor Report Example
25
Types of Budgets Distributed budget Management budget
Undistributed budget Contract changes
26
Variance Analyses
27
Variances The cost variance compares deviations only from the budget and does not provide a measure of comparison between work scheduled and work accomplished. The scheduling variance provides a comparison between planned and actual performance but does not include costs.
28
Variables for Variance Analysis
Budgeted Cost for Worked Scheduled (BCWS) is the budgeted amount of cost for word scheduled to be accomplished plus the amount of level of effort or apportioned effort scheduled to be accomplished in a given time period. Budgeted Cost for Work Performed (BCWP) is the budgeted amount of cost for completed word, plus budgeted for level of effort or apportioned effort activity completed within a given time period. this is sometimes referred to as an “earned value.”
29
Variables for Variance Analysis
Actual Cost for Work Performed (ACWP) is the amount reported as actually expended in completing the work accomplished within a given time period. Cost Variance = BCWP – ACWP Schedule/Performance Variance = BCWP - BCWS
30
Measurements Measurable efforts: discrete increments of work with a definable schedule for accomplishment, whose completion produces tangible results. Level of effort: work that does not lend itself to subdivision into discrete scheduled increments of work, such as project support and project control.
31
Cost Variance Calculation
CV = BCWP - ACWP A Negative Variance Indicates A Cost Overrun
32
Schedule Variance Calculation
SV = BCWP - BCWS A Negative Variance Indicates A Behind Schedule Condition
33
Variance Percents SV SCHEDULE VARIANCE % = X 100 (SVP) BCWS
COST VARIANCE % = (CVP) X 100 BCWS CV X 100 BCWP
34
Permitted Variances May be Dependent on Such Factors as :
Life cycle phase Length of life cycle phase Length of project Type estimate Accuracy of estimate
35
Variance Control for Example Program
36
Project Variance Analysis
VARIANCE UPPER BOUNDARY PROJECTED COST $ ACTUAL COST VARIANCE VARIANCE LOWER BOUNDARY R&D QUALIFICATION DEVELOPMENT PHASE I PHASE II PHASE III TIME
37
Performance Index BCWP Cost Performance Index = (CPI) ACWP
Schedule Performance Index = (SPI) ACWP BCWP BCWS
38
Performance Index Example
39
Management Reserve Defined as the difference between the contracted cost for projected performance to date and the budgeted cost. It is to cover the unforseen events within a defined project scope, but is used for unlikely major events.
40
Management Reserve CONTRACTED COST MANAGEMENT ACTUAL COST RESERVE $
RELEASED BUDGET TIME
41
Integrated Cost/schedule System
42
Information Requirements
Budgeted cost for work scheduled (BCWS) Budgeted cost for work performed (BCWP) Actual cost for work performed (ACWP) Estimated cost at completion Budgeted cost at completion Cost and schedule variances/explanations Traceability
43
Variance Analysis Questions
What is the problem causing the variance? What is the impact on time, cost, and performance? What is the impact on other efforts, if any? What corrective action is planned or under way? What are the expected results of the corrective action?
44
Variance Reporting Variance reporting is accomplished at each reporting interval. However, the variance threshold reports are exception reports and occur only when the variances exceed the upper and lower boundaries of the project variances envelope.
45
Reporting Intervals Depends on the type of organization and characteristics of the projects. Project-driven organization - weekly. Non-project-driven organization - monthly
46
Cost Account Variance Analysis Report
Cost account no/cam Reporting level WBS/Description As of Cost performance data Variance At completion BCWS BCWP ACWP SCHED COST Budget EAC Var. Month to date ($) Contract to date ($k) Problem cause and impact Corrective action (including expected recovery date) Cost account Date Cost center Date WBS element Date Date Mgr Mgr Mgr.
47
The 50/50 Rule Half of the budget for each element is recorded at the time that the work is scheduled to begin and the other half at the time the work is scheduled to be completed. For a project with a large number of elements the amount of distortion from such a procedure is minimal.
48
Analysis Budgeted cost for work Scheduled (BCWS) Performed (BCWP) 8
Cost account budget = 100 (thousands) 8 14 12 10 Work packages 12 8 BCWS = 38 BCWP = 49 SCHED. VARIANCE = +11 12 10 8 50-50 rule used for work in process J F M A M J J A S O N D
49
Using The 50-50 Rule 4,000 TIME LINE 10,000 LEGEND 12,000 COMPLETED
NOT COMPLETED 6,000 BCWS = 34,000 BCWP = 33,000 6,000 BAC = 52,000 10,000 TIME
50
Earned Value Status Reporting
TIME LINE BCWS SV ACWP CV CUMMULATIVE COST, $ BCWP TIME
51
Progress Reporting 1. Where are we today (time and cost)?
Progress reporting needs to answer four fundamental questions: 1. Where are we today (time and cost)? 2. Where will we end up (time and cost)? 3. What are the present and future risks? 4. Are there any special problems that need to be addressed and what can management do to help?
52
Estimate At Completion (EAC)
ACWP EAC = X Budget at completion BCWP (BAC) The estimate at completion is the best estimate of the total cost at the completion of the project. The EAC is a periodic evaluation of the status of the project - usually on a monthly basis or until a significant change has been identified.
53
Monthly Project Report
1. VARIANCE ANALYSIS (Cost in Thousands) June 1997 Budgeted Budgeted Cost Milestone Cost Work Work Actual Variance, % Subtask Status Scheduled Performed Cost Schedule Cost Completed Completed Completed Not Started Completed Not started Started Not started Total
54
2. ESTIMATE AT COMPLETION (EAC)
EAC = (360/340) X 579,000 = $613,059 Overrun = 613, ,000 = $34,059 3. COST SUMMARY Costs are running approximately 5.9% over budget due to higher salaried labor. 4. SCHEDULE SUMMARY The 24.4% behind schedule condition is due to subtasks 4 and 6 which have not yet begun due to lack of raw materials and the 50/50 method for booking costs. Overtime will get us back on schedule but at an additional cost of 2.5% of direct labor costs.
55
5. MILESTONE REPORT Milestone/ Scheduled Projected Actual Subtask Completion Completion Completion /1/ /1/97 /1/ /1/97 /1/ /23/97 /1/ /1/97 /1/ /1/97 /1/ /1/97 /1/ /1/97 /1/ /1/97
56
Current Potential Corrective
6. ACTIVITY REPORT Current Potential Corrective Problem Impact Action (a) Lack of raw Cost overruns and Overtime is scheduled. materials behind schedule We will try to use lower condition salaried staff. Raw materials are expected to be on dock next week. (b)Customer un May need add Customer will provide happy with test itional planning us with revised results statement of work on /15/97.
57
Status Reporting Status Reporting Is More Than Just A Computer Printout Intranet Status Reporting Reporting Favorable Status Reporting Unfavorable Status
58
Data Accumulation Budget Organization WBS BCWS BCWP ACWP SCHED VAR
COST VAR ACWP
59
Cost Problems Poor estimating techniques and/or standards, resulting in unrealistic budgets Out-of-sequence starting and completion of activities and events Inadequate work breakdown structure No management policy on reporting and control practices Poor work definition at the lower levels of the organization
60
Cost Problems (Continued)
Management reducing budgets or bids to be competitive or to eliminate “fat” Inadequate formal planning that results in unnoticed, or often uncontrolled, increases in scope of effort Poor comparison of actual and planned costs Comparison of actual and planned costs at the wrong level of management Unforeseen technical problems
61
Cost Problems (Continued)
Schedule delays that require overtime or idle time costing Material escalation factors that are unrealistic
62
Cost Control and Report Flow
63
Graphical Status Reporting
64
Program Interrelationships(1/7)
Program Manager Functional Manager Relationship Makes or approves all decisions that affect the contractually committed target time, cost, and performance requirements or objectives of the program Assembles and furnished the information needed to assist the program manager in making decisions. Submits to the program manager all proposed changes that affect program cost, schedule targets and technical requirements and objectives through the program team member Management controls, contract administration, budgeting, estimating, and financial controls are a functional specialty. The program manager utilizes the services of the specialist organizations. The specialists retain their own channels to the general manager but must keep the program manager informed through the program team member.
65
Program Interrelationships(2/7)
Program Manager Functional Manager Relationship Approves all engineering change control decisions that affect the contractually committed target time, cost, and performance requirements or objectives of the program. Establishes program budgets in conjunction with the cognizant program team members; monitors and negotiates changes. Implements engineering change decisions by the program manager. Advises him of any resulting programming impasses and negotiates adjustments through the program team member. In all matters pertaining to budget and cost control, the program manager utilizes the services of the program team member repressenting the cognizant financial control organization.
66
Program Interrelationships(3/7)
Program Manager Functional Manager Relationship Authorizes release of the budget and work authorization for the performance of approved work, and negotiates any intradirectorate reallocation above section level with the affected functional organizations through the program team members. Within the allocated budget, provides manpower skills, facilities, and other resources pertaining to his functional specialty to the degree and level necessary to meet program schedule, cost, and technical performance requirements of the contract.
67
Program Interrelationships(4/7)
Program Manager Functional Manager Relationship Requests the assignment of program team members to the program, and approves the release of the team member from the program. Coordinates with the program manager on the selection and assignment of a program team member to the program or release of the program team member from the program. Program manager does not fire functional personal. Program team members should not br removed from the program without the concurrence of the program manager.
68
Program Interrelationships(5/7)
Program Manager Functional Manager Relationship Establishes report requirements and controls necessary for evaluation of phases of program performance consistent with effective policies and procedures. Works in concert with other functional organizations to ensure that he and they are proceeding satisfactorily in the completion of mutually interdependent program tasks and events. Insofar as possible, program controls must be satisfied from existing data and controls as defined by division policies and procedures.
69
Program Interrelationships(6/7)
Program Manager Functional Manager Relationship Measures and evaluates performance of tasks against the established plan. Identifies current and potential program. Decides upon and authorizes corrective action. Follows up all activities of his organization to ensure satisfactory performance to program requirements. Detects actual or potential problems. Takes timely corrective action in his organization, and when such problems involve interface with other functional organization, notifies them and coordinates the initiation of mutually satisfactory remedial action. Keeps the program manager advised (through the program team member) of conditions affecting the program, existing, or expected problems solved, and corrective action required or performed. The program manager directs or redirects activities of functional organizations only through the cognizant program team member. Functional managers are responsible for the performance of their organizations. Functional managers do not implement decisions involving increased total program costs, changes in schedule, or changes in technical performance without prior approval of the program team members and the program manager.
70
Program Interrelationships(7/7)
Program Manager Functional Manager Relationship Apprises the program team members and/or functional organizations of program changes affecting their function. Assures the establishment, coordination, and execution of support program to the extent required or pemitted by the contract. This includes such programs as value engineering, data management, and configuration management.
71
Problem Areas in Cost Control
Organization: - Inadequate Work Breakdown Structure - Poor work definition at working levels - Lack of formal system procedures Planning and budgeting: - Inadequate forward planning - Over-allocation of budget - Poor integration of budget, schedule, work authorization
72
Problem Areas in Cost Control
Accounting: - Inability to account for cost of material on applied basis Analysis: - Determination of status not based on work package completion - Comparison of actual vs. planned costs at improper level Revisions: - Failure to maintain valid measurement baseline
73
Cost Problems Per Phase
Proposal Phase Failure to understand customer requirements Unrealistic appraisal of in-house capabilities Underestimating time requirements
74
Cost Problems Per Phase
Planning phase Omissions Inaccuracy of the work breakdown structure Misinterpretation of information Use of wrong estimating techniques Failure to identify and concentrate on major cost elements Failure to assess and provide for risks
75
Cost Problems Per Phase
Negotiation phase Forcing a speedy compromise Procurement ceiling costs Negotiation team that must “win this one”
76
Cost Problems Per Phase
Contractual phase Contractual discrepancies SOW different from RFP requirements Proposal team different from project team
77
Cost Problems Per Phase
Design phase Accepting customer requests without management approval Problems in customer communications channels and data items Problems in design review meetings
78
Cost Problems Per Phase
Production phase Excessive material costs Specifications that are not acceptable Manufacturing and engineering disagreement
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.