Response of Steel MRF to Puente Hills simulated motions Anna Olsen Tom Heaton Dean John Hall Caltech Civil Engineering
2
Model: 20 story steel moment-frame building 20 story steel moment-frame building plus one basement. Designed according to the 1994 UBC Natural period is 3.5 sec H=77.88 m Frame ElevationFloor Plan
3
20-story SMRF
4
6-story SMRF (1.54 sec period)
5
Faults Modeled 1. Sierra Madre (7.0) 2. Santa Monica SW (6.3) 3. Hollywood (6.4) 4. Raymond (6.6) 5. Puente Hills I (6.8) 6. Puente Hills II (6.7) 7. Puente Hills (all) (7.1) 8. Compton (6.9) 9. Newport-Inglewood (6.9) 10. Whittier (6.7) Day and others, 2005
6
Coordination Scheme UCB - LLNL UCSBCMUURS (RG) URS (AP) S. MadreF,R,SC S. Mon.F,RC HollyWF,RC RaymF,RC P.Hills6.8F,RC P.Hills6.7F,RC P.Hills7.1F,R,R,SC CompF,R,SC N-I N.R,SFC Whit N.RFC F = 6 3D scenarios C = single cross-check R = 1D rock reference simulation S = 1D basin-profile simulation
7
Puente Hills M 7.1
8
Puente Hills M 7.1 (2sec. Bandpass)
9
Downtown LA site for M 7.1 Puente Hills DLA
10
Puente Hills (M7.1) LA downtown 6-story with perfect welds
11
Puente Hills (M7.1) LA downtown 6-story with brittle welds
12
Puente Hills (M7.1) LA downtown 20-story with perfect welds
13
Puente Hills (M7.1) LA downtown 20-story with brittle welds
14
Mid-city site for M 7.1 Puente Hills MC
15
Puente Hills (M7.1) mid-city 6-story with perfect welds
16
Puente Hills (M7.1) mid-city 6-story with brittle welds
17
Puente Hills (M7.1) mid-city 20-story with perfect welds
18
Puente Hills (M7.1) mid-city 20-story with brittle welds
19
West LA site for M 7.1 Puente Hills WLA
20
Puente Hills (M7.1) West LA 6-story with perfect welds
21
Puente Hills (M7.1) West LA 6-story with brittle welds
22
Puente Hills (M7.1) West LA 20-story with perfect welds
23
Puente Hills (M7.1) West LA 20-story with brittle welds
24
Puente Hills M 7.1 6-story with perfect welds
25
Puente Hills M 7.1 6-story with brittle welds
26
Puente Hills M 7.1 20-story with perfect welds
27
Puente Hills M 7.1 20-story with brittle welds
28
Graves
29
Comparison of Graves motions vs SCEC motions for downtown LA
30
Comparison of Graves motions vs SCEC motions for Whittier
31
Graves scenario and 6-story with perfect welds
32
Graves scenario and 6-story with brittle welds
33
Graves scenario and 20-story with perfect welds
34
Graves scenario and 20-story with brittle welds
35
Are We Addressing the Right Questions in Earthquake Engineering? Current methodology assumes 1) architecture and 2) seismic hazard. Simplified assumptions about nonlinear building response (ductility factors) are used to produce a design. “collapse mechanisms” are rarely defined. Earth scientists are almost never asked if it is possible that the site will experience motions that can trigger the collapse mechanisms. Choose designs that are least susceptible to poorly predicted ground motions. It’s really tough to predict fault slip and hence long- period ground motions.
37
Graves
39
Puente Hills (East segment, M 6.8,epi 2) SCEC/PEER
41
Puente Hills (East segment, M 6.8) SCEC/PEER slip models
42
Puente Hills (East segment, M 6.8) 6-story with brittle welds
44
Puente Hills (East segment, M 6.8) 6-story with perfect welds
46
Puente Hills (East segment, M 6.8) 20-story with brittle welds
48
Puente Hills (East segment, M 6.8) 20-story with perfect welds
50
Puente Hills LA Segment (M 6.7)
52
Puente Hills LA Segment (M 6.7) Slip
53
Puente Hills LA Segment (M 6.7) 6-story with brittle welds
55
Puente Hills LA Segment (M 6.7) 6-story with perfect welds
57
Puente Hills LA Segment (M 6.7) 20-story with brittle welds
59
Puente Hills LA Segment (M 6.7) 20-story with perfect welds
61
Puente Hills M 7.1
62
Puente Hills M 7.1 6-story with brittle welds
63
Puente Hills M 7.1 6-story with perfect welds
64
Puente Hills M 7.1 20-story with brittle welds
65
Puente Hills M 7.1 20-story with perfect welds
66
Graves downtown site 1 20-story with brittle welds
67
Graves downtown site 2 20-story with brittle welds
68
Graves downtown site 3 20-story with brittle welds
69
Graves downtown site 4 20-story with brittle welds
70
Graves downtown site 5 20-story with brittle welds
71
Graves downtown site 6 20-story with brittle welds
72
Graves downtown site 7 20-story with brittle welds
73
Graves downtown site 8 20-story with brittle welds
74
Graves downtown site 9 20-story with brittle welds