Download presentation
Presentation is loading. Please wait.
1
AN INTRODUCTION TO MICROPILES CIVL 141 Spring 2011
2
A Local Situation:
3
A Shallow Footing Definition: D f /B < 2
4
Capacity of Spread Foundations (cohesionless soils)
5
THIS ONLY CONSIDERS THE SHEAR STRENGTH OF THE SOIL; WHAT ABOUT SETTLEMENTS?
6
Settlement-Based Capacity Use a bearing pressure that results in meeting some allowable settlement. – Less than 1 inch of total settlement; or – Less than ½ inch of differential settlement.
7
Settlement-Based Capacity Use a bearing pressure that results in meeting some allowable settlement. – Less than 1 inch of total settlement; or – Less than ½ inch of differential settlement. FOR COHESIONLESS SOILS (SANDS), THIS CRITERIA GENERALLY CONTROLS. THE LOST CAPACITY FROM SHEAR STRENGTH CAN BE SIGNIFICANT.
8
FOR MANY PROJECTS, THERE IS MOTIVATION TO INCREASE THE BEARING LOAD WITHOUT ADDITIONAL SETTLEMENTS OR SIMPLY REDUCE THE EXPECTED SETTLEMENTS ALTOGETHER.
9
HOWEVER, A CHALLENGE EXISTS TO DO SO WHILE MAINTAINING CONSTRUCTION BUDGETS
10
Lower the Bearing Pressure
11
Lower Bearing Pressures Do Not Always Provide Less Settlement q allow = 2,000 psf
12
Lower Bearing Pressures Do Not Always Provide Less Settlement q allow = 4,000 psf
13
More-Often, This is the Observed Design Situation
14
Currently Available Alternatives For Reducing Settlement Densify Bearing Soils – Over-Excavate and Recompact – Rapid Impact Compaction Deep Foundations (drilled shafts or piles) Intermediate Solutions – Rammed Aggregate Piers – Helical Piers – Micropiles
15
Over-Ex and Recompact
18
Micropiles
19
Micropiles are high capacity, small diameter (typically 5" to 12") drilled and grouted in- place piles designed with steel reinforcement to primarily resist structural loading.
20
Micropiles Micropiles are high capacity, small diameter (typically 5" to 12") drilled and grouted in- place piles designed with steel reinforcement to primarily resist structural loading. Micropiles do not necessarily use hollow-core bars but this is what I will present today.
21
Micropile Types
22
Hollow-Core Bar (F y = 75 ksi)
23
Pressure-Grouted Micropiles This discussion will be limited to hollow-core, pressure-grouted micropiles because they can be readily adapted to shallow foundations. Too, flow of grout is ensured over the complete length of the micropile.
24
Structural Limitations Ref: FHWA Manual, Section 5 (Through full-scale tests, elastic buckling does not appear to be a design concern and is not considered by FHWA. (note: IBC uses 0.33 and 0.40 instead of 0.40 and 0.47, respectively) Compression:
25
Structural Limitations Ref: FHWA Manual, Section 5 (note: IBC uses 0.6 instead of 0.55) Tension:
26
Geotechnical Limitations
27
Capacity of a Micropile
28
grout-soil can be 3 to 10 kips per square foot, found from a test; F typically taken as 2.5; bit diameter is conservative; and L = bond length of micropile.
29
Capacity of a Micropile q tip ; taken as 32 ksf (Reese et al. 1976) F typically taken as 3; R f = 0.6B
30
Example q tip = 32 ksf for medium dense sands; Bit diameter = 0.5 feet; L = 10 feet F is 3 for end bearing and 2.5 for side friction; and R f = 0.6(0.5 feet); grout-soil = 7 ksf
31
Example P ult = 51 kips
32
Estimating grout-soil
34
Structural Limitations During Testing
35
Grout-Soil Shear Strength from a Vertical Tension Test 10-ft long bonded zone
36
Grout-Soil Shear Strength from a Vertical Tension Test
37
Word of Caution (or a Strong Reason to Use Hollow-Core Bars)
40
Example situation
41
Assumes no support from soil
42
Example situation Shear in concrete – acceptable?
43
Example situation Negative moment
44
Connection to Spread Footing South Mountain Community College, Phoenix, AZ Double-reinforced footing (grade beam)
45
Connection to Spread Footing
46
Proof loading is typically completed on about 5% of the production micropiles. Loading is completed to 167% of the Design Test Load. Creep test may or may not be completed. Proof Loading
47
Mt. Lemmon Highway Milepost 9.8 Tucson, Arizona Dec. 2009
48
Proof Loading Mt. Lemmon Highway Milepost 9.8 Tucson, Arizona Dec. 2009
49
Proof Loading Mt. Lemmon Highway Milepost 9.8 Tucson, Arizona Dec. 2009
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.