Download presentation
Presentation is loading. Please wait.
1
ATA - 42 Antenna & Zone Cost Summary Matt Fleming 2008-03-14 Part B of a two part presentation Part A Antenna & Zone Design Summary Part B Antenna & Zone Cost Summary
2
2 Antenna Elements & 1 Zone Node House
3
Hat Creek Radio Observatory HCRO
4
Included in this discussion ANTENNA Pedestal Alidade & Azimuth Bearing Drives, Motors, Amps Pri Frame, Support Struts Pri & Sec Reflector Surfaces Sec support, Shroud, Radome Limits & Encoders Enclosures & Conduit Electrical & Comm in Antenna ZONE Foundation Zone Node All in Ground Services EXCLUDED Antenna Control Computer Feed & Receiver Signal Path Everything Else
6
More pros With the pedestal able to project into the area behind the reflector, the elevation and azimuth axis can be positioned very near the reflector surface. Each axis is close to the center of wind force and these reduced lever arms mean smaller drive loads and should help reduce costs. The elevation axis is close to the center of mass for the tilting assembly which should reduce the need for counterweight.
7
Cost Projection Based on 42 Antennas
8
Antenna Cost Estimated for 350 all tooling and engineering included
9
Antenna Cost Measured at 42 all engineering & tooling included
10
Engineering Cost per category at 42
11
Tooling Cost per Category at 42
12
Material & Labor Cost per Category at 42
13
Material & Labor Cost per Category for 350
14
Delivery of Primary Reflectors This is our most expensive item. This along with the secondary use about 2000 lbs of aluminum. Aluminum costs about 2.40 $ / lb so our actual material cost is $4,800. We are paying 17,000 for the Pri & Sec delivered with stiffeners ready for welding. These items offer the greatest opportunity to reduce labor costs or control profit.
15
The famous Primary Tool The primary and secondary tool shown here was priced as follows: $568,000 Primary tool $75,000 Secondary tool $68,000 Other table equipment $46,000 Tuning tool. The original price base on going full steam ahead into production was $8,300 for a primary and $571 for a secondary
16
Extra Costs Building this tool and moving it around in the plant required raising the roof and installing a heavy duty bridge crane. Basically we picked up the cost of a lot of this in our tool cost. The 47,000 lb primary mold tool is shown here After this work and a reduced quantity on the order the price for a complete set of reflectors moved from $8,871 to $17,400
17
Trenching Costs A lot of this through rock. Trench work Trenching22,400 Vault28,393 Materials12,758 Boxes13,089 Conduit24,280 Electrical Equipment19,772 Wires48,556 Comm3,913 Staff Labor 5p x 30 wks150,000 Total Cost for 42 ants323,162 meters2455 Complete trench $ / meter131.63
18
Zone node Cost Zone Node Design90,409 Zone nodes 5 ea143,227 Total233,636 Units5 Price ea with NRE46,727 Projected future cost27,742 Assy tent53,000 Assy fixtures12,000 Transport vehicle30,000 On Site Assembly Area
19
Foundation Costs Foundation Contractor175,519 Staff 3p x 4 wks12,000 total187,519 units42 Price each4,465
21
2 Foundation Types
22
Integration Fully integrated azimuth limit and e-stop board with relays and sensors
23
Lots of Sub Contractors managed by our staff
24
Hat Creek Staff
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.