1 Open Cruise Requirements status and planning LSWT#4, Venice 30/03-01/04-2009 LSWT#4

2 2 LSWT#4, Venice, 30/03-01/04-2009 SCrOP Annex_G - PC10  Active Payload Checkout PC10:  Regular tests for active checkouts  ESS RAM Patch Test for ESS events  Finalize SW Upload for Lander Units, Part 2 of 2:  SW Upload for SESAME  SW Patch for ADS (tbc)  + COSAC SW Upload  + CIVA SW Upload  + APXS parameter setting, re-run PC8 test All units SW shall be final after PC10. This does not apply for CDMS:  SW8.0 upload PC12  Lander internal Interference Tests (Part 1)  On-comet Preparation tests, Part 1  New requirements from  PTOLEMY to finalize activities (substitute existing requirement)  CONSERT tests on switch-ON accuracy

3 3 LSWT#4, Venice, 30/03-01/04-2009 SCrOP Annex_G - PC12  Active Payload Checkout PC12:  CDMS SW Upload to V8.0  Battery charge to 100% prior DSH  Regular tests for active checkouts  Contingency activities, if needed  S-D-L combined tests (mainly driven by Flywheel S-D-L operations)  Lander Internal Interference Tests, Part 2  On-comet Preparation tests, Part 2 (MUPUS, CONSERT) ANCHOR, COSAC, PTOLEMY, CONSERT

4 4 LSWT#4, Venice, 30/03-01/04-2009 Cruise Phase Events 2009  Passive PC9 Jan 2009   PC9 execution-> Jan 2009  Rosetta Thermal Characterization   Test execution -> Feb-2009  Active PC10  High level inputs to ESA  -> Feb 2009  Start of GRM campaign-> May 2009  End of GRM campaign-> July 2009  LOR delivery-> Aug 2009  GO/NOGO-> 03-Sep-2009  PC10 execution-> 21-Sep to 02-Oct 2009  ESB3 (no Philae activities)  High level inputs to ESA  -> Feb 2009  ESB3 CA-> 13-Nov-2009

5 5 LSWT#4, Venice, 30/03-01/04-2009 Cruise Phase Events 2009/2010  In-flight Power System Test (PSS, MPPT, SBatt)  High level inputs to RMOC-> Nov 2009 (tbc)  End of GRM campaign-> Jan 2010 (tbc)  LOR delivery-> Feb 2010 (tbc)  PST execution-> February 2010  CDMS SW V8.0 verification  Start-> September 2009  End -> Nov 2009  Active PC12  High level inputs to ESA-> Oct 2009  End of GRM campaign-> Feb 2010  LOR delivery-> Mar 2010  GO/NOGO-> Apr 2010  PC12 execution-> April/May 2010

6 6 LSWT#4, Venice, 30/03-01/04-2009 Cruise Phase Events 2009/2010  Lutetia  High level inputs to ESA-> March 2009  End of GRM campaign-> Apr 2010  LOR delivery-> May 2010  GO/NOGO-> June 2010  LUT CA-> 10-July-2010  Passive PC13 => Last payload activity prior DSH!!!  PC Change Req. to ESA-> Sep 2010  LOR delivery-> Oct 2010  GO/NOGO-> Nov 2010  PC13 execution-> Dec 2010

7 7 LSWT#4, Venice, 30/03-01/04-2009 Cruise - OPS Preparation Schedule 2009  PC10 EQM Test RMOC-> April 2009  PC10 Start of GRM campgn-> May 2009  PC10 End of GRM campgn-> July 2009  PC10 LOR delivery-> Aug 2009  PC10 GO/NOGO-> 03-Sep-2009  CDMS SW8.0 Test Start-> September 2009  PC10 execution-> 21-Sep to 02-Oct 2009  PC12 First Inputs to ESA-> Oct 2009  PST Inputs to RMOC-> Nov 2009 (tbc)  PC12 SCrOP + timeline-> Nov 2009 (tbc)  CDMS SW8.0 Test End -> Nov 2009

8 8 LSWT#4, Venice, 30/03-01/04-2009 Cruise - OPS Preparation Schedule 2010  PST GRM campgn-> Jan 2010 (tbc)  PST LOR delivery-> Feb 2010 (tbc)  PST execution-> February 2010  PC12 End of GRM campgn-> Feb 2010  PC12 LOR delivery-> Mar 2010  PC12 GO/NOGO-> Apr 2010  LUT End of GRM campgn-> Apr 2010  PC12 execution-> April/May 2010  LUT LOR delivery-> May 2010  LUT GO/NOGO-> June 2010  LUT CA-> 10-July-2010  PC13 Change Req. to ESA-> Sep 2010  PC13 LOR delivery-> Oct 2010  PC13 GO/NOGO-> Nov 2010  PC13 execution-> Dec 2010

9 9 LSWT#4, Venice, 30/03-01/04-2009 Longterm planning  Deep Space Hibernation Phase (DSH)  Start DSHJuly 2011  End DSHJanuary 2014  Payload Commissioning PeriodApril/May 2014 Limited Resources !!! (Power/Data)  Comet Phase StartAugust 2014  Global Mapping 18-Aug to 21-Sep2014  Close Observation22-Sep to 19-Oct2014  Lander Delivery Period StartOctober 2014  Lander Delivery11-Nov-2014  Lander Baseline Mission12 to 16- Nov2014  Comet Escort Phase  Start Escort Phase17-Nov-2014  Perihelion13-Aug-2015  End Escort Phase31-Dec-2015

10 10 LSWT#4, Venice, 30/03-01/04-2009 Open NCR Status  Total of 28 open NCRs to units FM model:  APXS (1)->PC10ADS (2) ->PC10  CIVA (3/1*)->PC10 Battery* (1)  CONSERT (2) ->PC10 CDMS (10)->PC12  COSAC (1) ->PC10 ESS* (2)  PTOLEMY (1) ->PC10 PSS* (3)  ROMAP* (2) Last review based on dedicated emails and LOWG#12 presentations (*) further clarification required