Open Cruise Requirements status and planning LSWT#4, Venice 30/03-01/04-2009 LSWT#4
2
2 LSWT#4, Venice, 30/03-01/04-2009 SCrOP Annex_G - PC10 Active Payload Checkout PC10: Regular tests for active checkouts ESS RAM Patch Test for ESS events Finalize SW Upload for Lander Units, Part 2 of 2: SW Upload for SESAME SW Patch for ADS (tbc) + COSAC SW Upload + CIVA SW Upload + APXS parameter setting, re-run PC8 test All units SW shall be final after PC10. This does not apply for CDMS: SW8.0 upload PC12 Lander internal Interference Tests (Part 1) On-comet Preparation tests, Part 1 New requirements from PTOLEMY to finalize activities (substitute existing requirement) CONSERT tests on switch-ON accuracy
3
3 LSWT#4, Venice, 30/03-01/04-2009 SCrOP Annex_G - PC12 Active Payload Checkout PC12: CDMS SW Upload to V8.0 Battery charge to 100% prior DSH Regular tests for active checkouts Contingency activities, if needed S-D-L combined tests (mainly driven by Flywheel S-D-L operations) Lander Internal Interference Tests, Part 2 On-comet Preparation tests, Part 2 (MUPUS, CONSERT) ANCHOR, COSAC, PTOLEMY, CONSERT
4
4 LSWT#4, Venice, 30/03-01/04-2009 Cruise Phase Events 2009 Passive PC9 Jan 2009 PC9 execution-> Jan 2009 Rosetta Thermal Characterization Test execution -> Feb-2009 Active PC10 High level inputs to ESA -> Feb 2009 Start of GRM campaign-> May 2009 End of GRM campaign-> July 2009 LOR delivery-> Aug 2009 GO/NOGO-> 03-Sep-2009 PC10 execution-> 21-Sep to 02-Oct 2009 ESB3 (no Philae activities) High level inputs to ESA -> Feb 2009 ESB3 CA-> 13-Nov-2009
5
5 LSWT#4, Venice, 30/03-01/04-2009 Cruise Phase Events 2009/2010 In-flight Power System Test (PSS, MPPT, SBatt) High level inputs to RMOC-> Nov 2009 (tbc) End of GRM campaign-> Jan 2010 (tbc) LOR delivery-> Feb 2010 (tbc) PST execution-> February 2010 CDMS SW V8.0 verification Start-> September 2009 End -> Nov 2009 Active PC12 High level inputs to ESA-> Oct 2009 End of GRM campaign-> Feb 2010 LOR delivery-> Mar 2010 GO/NOGO-> Apr 2010 PC12 execution-> April/May 2010
6
6 LSWT#4, Venice, 30/03-01/04-2009 Cruise Phase Events 2009/2010 Lutetia High level inputs to ESA-> March 2009 End of GRM campaign-> Apr 2010 LOR delivery-> May 2010 GO/NOGO-> June 2010 LUT CA-> 10-July-2010 Passive PC13 => Last payload activity prior DSH!!! PC Change Req. to ESA-> Sep 2010 LOR delivery-> Oct 2010 GO/NOGO-> Nov 2010 PC13 execution-> Dec 2010
7
7 LSWT#4, Venice, 30/03-01/04-2009 Cruise - OPS Preparation Schedule 2009 PC10 EQM Test RMOC-> April 2009 PC10 Start of GRM campgn-> May 2009 PC10 End of GRM campgn-> July 2009 PC10 LOR delivery-> Aug 2009 PC10 GO/NOGO-> 03-Sep-2009 CDMS SW8.0 Test Start-> September 2009 PC10 execution-> 21-Sep to 02-Oct 2009 PC12 First Inputs to ESA-> Oct 2009 PST Inputs to RMOC-> Nov 2009 (tbc) PC12 SCrOP + timeline-> Nov 2009 (tbc) CDMS SW8.0 Test End -> Nov 2009
8
8 LSWT#4, Venice, 30/03-01/04-2009 Cruise - OPS Preparation Schedule 2010 PST GRM campgn-> Jan 2010 (tbc) PST LOR delivery-> Feb 2010 (tbc) PST execution-> February 2010 PC12 End of GRM campgn-> Feb 2010 PC12 LOR delivery-> Mar 2010 PC12 GO/NOGO-> Apr 2010 LUT End of GRM campgn-> Apr 2010 PC12 execution-> April/May 2010 LUT LOR delivery-> May 2010 LUT GO/NOGO-> June 2010 LUT CA-> 10-July-2010 PC13 Change Req. to ESA-> Sep 2010 PC13 LOR delivery-> Oct 2010 PC13 GO/NOGO-> Nov 2010 PC13 execution-> Dec 2010
9
9 LSWT#4, Venice, 30/03-01/04-2009 Longterm planning Deep Space Hibernation Phase (DSH) Start DSHJuly 2011 End DSHJanuary 2014 Payload Commissioning PeriodApril/May 2014 Limited Resources !!! (Power/Data) Comet Phase StartAugust 2014 Global Mapping 18-Aug to 21-Sep2014 Close Observation22-Sep to 19-Oct2014 Lander Delivery Period StartOctober 2014 Lander Delivery11-Nov-2014 Lander Baseline Mission12 to 16- Nov2014 Comet Escort Phase Start Escort Phase17-Nov-2014 Perihelion13-Aug-2015 End Escort Phase31-Dec-2015
10
10 LSWT#4, Venice, 30/03-01/04-2009 Open NCR Status Total of 28 open NCRs to units FM model: APXS (1)->PC10ADS (2) ->PC10 CIVA (3/1*)->PC10 Battery* (1) CONSERT (2) ->PC10 CDMS (10)->PC12 COSAC (1) ->PC10 ESS* (2) PTOLEMY (1) ->PC10 PSS* (3) ROMAP* (2) Last review based on dedicated emails and LOWG#12 presentations (*) further clarification required