Presentation is loading. Please wait.

Presentation is loading. Please wait.

Planning “Science Operations” tasks for the PD phase NGAO PD Phase D. Le Mignant W. M. Keck Observatory 08/19/2008.

Similar presentations


Presentation on theme: "Planning “Science Operations” tasks for the PD phase NGAO PD Phase D. Le Mignant W. M. Keck Observatory 08/19/2008."— Presentation transcript:

1 Planning “Science Operations” tasks for the PD phase NGAO PD Phase D. Le Mignant W. M. Keck Observatory 08/19/2008

2 2 Outline 1.“Science Operations” during PD phase 1.Narrative 2. Schematic 3.Work in progress 2.Proposed Priorities 1.High 2.Low 3.Discussion / comments

3 3 Science Operations during the PD phase Narrative WBS 3.2 Requirements –WBS 3.2.1: Observing Operations Concept Document (OOCD) “Example observations”, including simulations of quantitative science output from NGAO + science instrument Uses cases, leading to operations sequences and science tools WBS 3.4 System architecture –WBS 3.4.4: NGAO Sequences Definitions Document (SDD) WBS 3.6 Science Ops Tools Design –WBS 3.6.1 Multi-system Command Sequencer (MCS) –WBS 3.6.2 User Interfaces –WBS 3.6.3 Pre and post-observing science support tools –WBS 3.6.4 Data server WBS 3.9 Operations Transitions –WBS 3.9.1 Ops Plans –WBS 3.9.2 Ops Handover

4 4 NGAO sequences definitions document OOCD document: Keck standard Example observations Planning User System Observing User System Post-observing Uses cases Use case 1 User System Use case 2 User System WBS 3.2 WBS 3.4.4: Science observing planning, simulation and execution User Interfaces design WBS 6.2.2 WBS 6.2.3 WBS 6.2.4 Science requirements WBS 3.1 Re-planning (phased) approach? (New) performance budgets WBS 3.1.3 -- 3.1.6 users inputs documentactivityWBS name WBS 3.1.2 SDM (KAON 511)

5 5 OOCD document: Keck standard Example observations Planning User System Observing User System Post-observing Uses cases Use case 1 User System Use case 2 User System NGAO sequences definitions document WBS 3.2 WBS 3.4.4: MCS sequences WBS 6.1.2 WBS 6.1.3 WBS 6.1.4 User Interfaces WBS 6.2.2 WBS 6.2.3 WBS 6.2.4 documentactivityWBS name The detailed sequences will be documented In the NGAO SDD. The context will be provided in the OOCD

6 6 NGAO sequences definitions document WBS 3.4.4: MCS sequences WBS 6.1.2 WBS 6.1.3 WBS 6.1.4 User Interfaces WBS 6.2.2 WBS 6.2.3 WBS 6.2.4 NGAO software architecture document WBS 3.4.3 External ICD WBS 3.5 Internal ICD WBS 3.6 Coordination with general software effort!! OOCD document: Keck standard Example observations Planning User System Observing User System Post-observing Uses cases Use case 1 User System Use case 2 User System WBS 3.2 documentactivityWBS name

7 7 NGAO sequences definitions document WBS 3.4.4: MCS sequences WBS 6.1.2 WBS 6.1.3 WBS 6.1.4 User Interfaces WBS 6.2.2 WBS 6.2.3 WBS 6.2.4 NGAO software architecture document WBS 3.4.3 External ICD WBS 3.5 Internal ICD WBS 3.6 documentactivityWBS name MCS infrastructure document WBS 6.1.1: UI infrastructure document WBS 6.2.1: Data server infrastructure WBS 6.4.1: WSPS/outline for the deliverables - Operations concept? - Software Interface?

8 8 Science Operations during the PD phase Work in progress… Plan the deliverables: Outline/standard for the document Plan for release(s) and content update Lead person per document / section How to include (realistic) science instruments for quantitative estimates for the example observations Phase the effort (under the assumption there will be a learning curve on the science instruments)…

9 9 Priorities HIGH… OOCD Outline for release 1: Get buy-in and include suggestions / comments How do we include a case for the wide fov science? (assumptions, assumptions…) Sequences Definitions Document Outline and start of release 1 [Not a perfect flow-down..] Sci ops architecture Release 1 for system infrastructure (MCS)

10 10 Priorities low… Science operations support tools Release 1 in support of working on observing scenarios (i.e., narrow-field science:OSIRIS, VIS/NIR-IMGR) Keep it descriptive for d-IFS for instance?? User Interface (release 1 - tbd) Observing sequences control Science observing sequences Awaiting progress on science instrument [e.g., fine centering with coronagraph] Troubleshooting & alarm handling? Operations Transitions (100h for DLM) Outline for document (~ 20h or less)

11 11 Comments and discussion Questions about priorities? High and low “Build to cost paradigm”, can be seen as: Opportunity to deliver an integrated science machine Driven by the science instruments requirements:  Review science case to cost-benefit  Include design/build of science instruments  Focus on science instruments rather than details on science operations and observing sequences, e.g, who cares about 5% observing efficiency when you don’t know whether there will be 0, 3 or 6 d-IFS Outstanding science instruments are key to AO success!


Download ppt "Planning “Science Operations” tasks for the PD phase NGAO PD Phase D. Le Mignant W. M. Keck Observatory 08/19/2008."

Similar presentations


Ads by Google