GLAST LAT ProjectOnline Roadmap Progress Report – April 22, 2004 R. Claus1 Online Roadmap to the July 2004 Freeze Progress report for April 22, 2004 (to be compared against LAT-TD-03075) R. Claus
2
GLAST LAT ProjectOnline Roadmap Progress Report – April 22, 2004 R. Claus2 GASU support GASU shipped yesterday with corresponding LATTE release. –Completed: Trigger software interface ACD script migration EBF (now called LDF) package update –Significant schedule drift (~ 1 month) due to complexities of hardware and firmware debugging and thorough testing Required more than full time support from Jim –“New” jobs: Veto rate counters in two forms based on FSW –Multiplexed registers => command server work –Dedicated event data analysis => event server work
3
GLAST LAT ProjectOnline Roadmap Progress Report – April 22, 2004 R. Claus3 Hardware monitoring system Two new ELX hires working on the LAT Test Bed Power Management System –Includes monitoring which Online may be able to leverage off of Online is involved in its design and is providing support However, ELX requirements are different than Online’s Online requires Housekeeping server from FSW –Currently being worked on ELX monitoring package is modular, so HSKsvr is expected to drop right in –No dedicated work by Online on this problem so far
4
GLAST LAT ProjectOnline Roadmap Progress Report – April 22, 2004 R. Claus4 Power-up sequence Sequencing code to be provided by FSW and triggered by LATTE Two options: –ELX Power Management System –FSW supplied code First option is in progress No involvement by Online until interface is described
5
GLAST LAT ProjectOnline Roadmap Progress Report – April 22, 2004 R. Claus5 Electronic Logbook Stand-alone version is tantamount to complete –Have released the current version with LATTE 3 –New version needs testing and review –Alicia is currently studying for Quals, so ability to iterate on this is limited –Security on both stand-alone and web versions needs to be revisited
6
GLAST LAT ProjectOnline Roadmap Progress Report – April 22, 2004 R. Claus6 Release mechanism for subsystem test scripts Completed Included in LATTE 3 releases In use by CAL
7
GLAST LAT ProjectOnline Roadmap Progress Report – April 22, 2004 R. Claus7 Items not worked on (1) Event prescaling in Event Server –Small job Subsystem scripts –None received –Some ELX available for the picking but no time to pick –Ditto TKR –CAL says “soon” –ACD still has issues with ITAR but will share informally if pressed –I&T: No time to make progress LATTE security against unauthorized software changes –On hold LATTE security against operator complacency –On hold Test conductor training –On hold until LATTE completion
8
GLAST LAT ProjectOnline Roadmap Progress Report – April 22, 2004 R. Claus8 Items not worked on (2) Building 33 EGSE room 102 set-up –Agreed with Larry to have Brian H. carry the brunt of this OPUS and the paper trail –Need to follow up Validation and Verification –Due to start in May –We very likely won’t be ready to start
9
GLAST LAT ProjectOnline Roadmap Progress Report – April 22, 2004 R. Claus9 Additional requests to Online LDF compilation issues with GCC 3.2 –Done Method for tracking components by “serial number” –Provided method as part of the configuration files Probably others I can’t remember