Presentation is loading. Please wait.

Presentation is loading. Please wait.

1 Virgo Commissioning progress and plans ILIAS, Jan 23 rd 2007 Matteo Barsuglia on behalf of the Commissioning Team.

Similar presentations


Presentation on theme: "1 Virgo Commissioning progress and plans ILIAS, Jan 23 rd 2007 Matteo Barsuglia on behalf of the Commissioning Team."— Presentation transcript:

1 1 Virgo Commissioning progress and plans ILIAS, Jan 23 rd 2007 Matteo Barsuglia on behalf of the Commissioning Team

2 2 Outline  Status at the last meeting, November 13 th  Commissioning progress during last 2 months  Future steps  Related talks:  Noise hunting issues in Virgo (Gabriele)  Use of a second modulation (Maddalena, Henrich)  Some considerations on Virgo design sensitivity (Matt)

3 3 Thermal lensing: power decrease needed Laser power reduction (25%) Stored power reduction ~ 10% wrs WSR-1 20 min 100 sec Matching activity: 10% power increase

4 4 WSR5 noise budget  Unknown noise in the 100 Hz region (suspect: diffused light)  Longitudinal control near the sensitivity – sometimes limiting

5 5 Sensitivity to weather conditions Red curve: 2.7 Mpc -(wind+sea) Red curve = 2.7 Mpc-(wind+sea)

6 6 Progress since last meeting  Calibration uncertainty fixed  Noise hunting  Diffused light investigations  Longitudinal control noise  Increase ITF robustness  Automatic alignment  Mirror suspension control  2 WSR’s performed  WSR-6 in December  WSR-7+ commissioning run in January

7 7 Calibration fixed – end of November  Discrepancy of 40% between calibrations with north-end and west-end  Conservative value taken so far  Problem discovered in a DAC of one of the end test masses  New value gives “improvement” in sensitivity  1.4 above 100 Hz  Present uncertainty ~ 10%

8 8 Diffused light investigations

9 9 Detection port  Dump spurious beam on vacuum (half of December)  Simplify optical scheme of the external bench (beginning of January)

10 10 B1b B5b Optics centering checks: - Realignment of M9 (on B1s) In vacuum beam dumps

11 11 In vacuum beam dumps/2 No significant results from the mitigations in and out vacuum

12 12 Big work on alignment  Increase the gain in the alignment filters, in order to:  Improve the quality of the data  Increase ITF robustness  deal with bad weather conditions  Gain increase already done, further increase planned  Re-design of the alignment control chain  Filters migration to the global control (not the DSP)  more flexible  Possibility to change between acquisition/detection filters  Possibility to inject noise on error points and measure open loop TF  Second modulation at 8 Hz, control the “common-end” mode

13 13 New alignment filters ty (yaw) tx (pitch)

14 14 Quality of the data: WSR5 vs WSR7 WSR5 (nov 10-13) WSR7 (Jan 12-15) Coalescing binaries analysis

15 15 WSR’s program  1 (Sept 8 th -11 th ) ~ 90% duty cycle  2 (Sept 22 nd -25 th ), ~ 65% due to infrastructure failure, >90% after  3 (Oct 6 th -9 th ) - cancelled  4 (Oct 13 th -16 th ) – cancelled  5 (Nov 10th-13th), ~ 65%  6 (Dec 1 st -4 th ), ~ 80%  7 (Jan 12 th -15 th ), ~ 76% + commissioning run 2.5 days  Tests (noise injections, change of some parameters,…) in stable and homogeneous conditions  8 (Feb 9 th -12 th ) planned

16 16 Earthquake during WSR7 From Hanford e-log

17 17 Noise budget – WSR7  Unknown noise in the 100 Hz region (suspect: diffused light)  Power recycling control near the sensitivity – sometimes limiting

18 18 Structures around 100 Hz

19 19 Longitudinal control noise  Switch to B2  “Beta” technique  Change completely control scheme

20 20 Locking scheme

21 21 Switch to B2  PR is currently controlled with B2_3f (third harmonics)  B2 (first harmonics) gives better SNR, about 1 order of mag  Transition B2_3f  B2 works  B2 contains an offset  Not understood  Manually compensated  ITF controlled with B2 works for hours but still not convincing (instabilities), more test are needed

22 22 Noise budget – B2

23 23 Beta technique MICH and PRCL corrections sent to the end mirrors to subtract the noise reintroduced by these loops to the dark fringe

24 24 Change the control strategy  beta technique is not sufficient to decrease enough the control noise  Fluctuations of the coupling  Second modulation (not resonant in the recycling cavity) already in preparation to control the angular common end mode  If transition to B2 does not work ina reliable way  Lock the SSFS with the second modulation  Move the power recycling control from B2_3f to B5 (pick-off)

25 25 Plans before next meeting  Noise hunting  Diffused light investigations  Control noise  SSFS new board  Continue work on alignment  Increase filter gain  Second modulation – common end  Continue work on mirror suspension control  WSR8 (mid February) + 1-2 WSR’s to be decided

26 26 Noise hunting: terminal benches  Diffused light mitigation end benches (next week)

27 27 Noise hunting: detection port  Further diffused light mitigation suspended injection bench (half February)  Further diffused light mitigation external injection bench (February)  Acoustic mitigation detection laboratory (end of March)  New (larger) Brewster (April?)

28 28


Download ppt "1 Virgo Commissioning progress and plans ILIAS, Jan 23 rd 2007 Matteo Barsuglia on behalf of the Commissioning Team."

Similar presentations


Ads by Google