1 Project Overview E911 Provisioning System Royal Flush Software
Kevin Francis, Jason Plaisted, Jessica St. Croix, Mike O’Connor, Derrick Hudson

2 Project Goals Provide E911 provisioning software for Paetec Communications Replace existing E911 software, fixing several known problems Update system to current technologies to improve maintainability

3 Description Rewrite PaeTec’s existing E911 provisioning software using J2EE, JSP, and Enterprise Java Bean technology Fix existing problems in, and make improvements to, the current database model Rewrite C++ code in Java for generating flat files for ILEC’s

4 Technology Technology being used Resin Enterprise Application Server
Specified by PaeTec J2EE More extensible and flexible than C++ Enterprise Java Beans Increases scalability of system Java Server Pages Replaces no-longer-supported Oracle Web Design

5 Architecture Overview
Verizon E911 Flat File E911 UI (JSP Pages) Verizon data record Ameritech E911 Flat File E911 Batch Data Extract (Java) Ameritech data record E911 Processing & Data Modeling (EJB based) PacBell data record PacBell E911 Flat File Other ILEC data record PaeTec E911 Local Database Other ILEC E911 Flat File

6 Color Denotes Deliverables
Schedule Date Action / Deliverables Weeks 1-3 Examine existing system and documentation Week 3 Create Project Plan Weeks 4-5 Gather Requirements / Software Requirements Document Week 6 Revised Data Model Week 7 Architecture Document Week 9 Design Document Week 10 Begin Implementation Week 12 Begin Testing Week 18 Beta Software Complete Week 19 Conclude Testing Week 20 Presentation & Post Mortem, Deliver Final Product Color Denotes Deliverables

7 Risks E911 Related Software Resin Enterprise Application Server Time
Leaves little-to-no room for error Resin Enterprise Application Server New tool to all members of the development team Time Extremely strict deadline

8 Team Jon Templin Kevin Francis Jason Plaisted Michael O’Connor
PaeTec Contact, Customer Kevin Francis Development Team Leader Jason Plaisted Planning Leader Michael O’Connor Configuration Manager Jessica St. Croix Development Leader Derrick Hudson Testing Leader

9 Current Status High-level Overview of Progress
Project Plan created and is being maintained Requirements Gathering is commencing and on-track Prototype for the user interface is under development Revised data model is almost ready

10 Questions