1 Materials Requirements Planning

2 Collins Industries Largest manufacturer of ambulances in the world
International competitor 12 major ambulance designs 18,000 different inventory items 6,000 manufactured parts 12,000 purchased parts MRP seems to be a good way to manage inventories: IBM’s MAPICS system is used

3 Independent and Dependent Demand
Independent Demand A B(4) C(2) D(2) E(1) D(3) F(2) Dependent Demand Independent demand is uncertain. Dependent demand is certain.

4 Dependent Demand Dependent demand: Demand for items that are subassemblies or component parts to be used in production of finished goods. Once the independent demand is known, the dependent demand can be determined.

5 Demand Characteristics
Week 400 – 300 – 200 – 100 – No. of tables Continuous demand M T W Th F M T W Th F Discrete demand Independent demand 100 tables Dependent demand 100 x 1 = 100 tabletops 100 x 4 = 400 table legs

6 Dependent vs Independent Demand
Time Demand Stable demand “Lumpy” demand Amount on hand Safety stock

7 Material Requirements Planning Defined
Materials requirements planning (MRP) is a computerized inventory planning and control system for determining when (no earlier and no later) and how many of each of the parts, components, and materials should be ordered or produced. It translates master schedule requirements fr end items into time-phased requirements for subassemblies, components and raw materials. Dependent demand drives MRP MRP is a software system

8 When to Use MRP Dependent and discrete items Complex products
Job shop production Assemble-to-order environments

9 Material Requirements Planning System
Based on a master production schedule, a material requirements planning system: Creates schedules identifying the specific parts and materials required to produce end items Determines exact unit numbers needed Determines the dates when orders for those materials should be released, based on lead times

10 Secondary reports Primary reports Exception reports Planning reports
10 Firm orders from known customers Forecasts of demand from random Aggregate production plan Bill of material file Engineering design changes Inventory record file transactions Master production Schedule (MPS) Material planning (MRP computer program) Primary reports Secondary reports Planned order schedule for inventory and production control (work orders, purchase orders), rescheduling notices Exception reports Planning reports Reports for performance control The McGraw-Hill Companies, Inc., 2004

11 MRP System MRP Inputs MRP Processing MRP Outputs Master schedule
Bill of materials Inventory records MRP computer programs Changes Order releases Planned-order schedules Exception reports Planning reports Performance- control reports transaction Primary Secondary

12 MRP Inputs 1: Master Production Schedule
Drives MRP process with a schedule of finished products; states which end items are to be produced, when these are needed, and in what quantities Quantities may consist of a combination of customer orders & demand forecasts Quantities represent what needs to be produced, not what can be produced

13 Master Production Schedule (MPS)
Time-phased plan specifying how many and when the firm plans to build each end item Aggregate Plan (Product Groups) MPS (Specific End Items)

14 Master Production Schedule
Shows items to be produced Derived from aggregate plan Example: Item / Week Oct 3 Oct. 10 Oct. 17 Oct.24 Oct. 31 Clipboard Lapdesk Lapboard Pencil Case

15 MRP Inputs 2: Bill-of-Materials
Bill of materials (BOM): One of the three primary inputs of MRP; a listing of all of the raw materials, parts, subassemblies, and assemblies needed to produce one unit of a product. Product structure tree: Visual depiction of the requirements in a bill of materials, where all components are listed by levels.

16 Product Structure Tree: Example 1
Chair Seat Legs (2) Cross bar Side Rails (2) Back Supports (3) Leg Assembly Level 1 2 3

17 Product Structure Tree: Example 2
Bicycle(1) P/N 1000 Handle Bars (1) P/N 1001 Frame Assembly (1) P/N 1002 Wheels (2) P/N 1003 Frame (1) P/N 1004

18 Product Drawing: Example 3
Top clip (1) Bottom clip (1) Pivot (1) Spring (1) Rivets (2) Finished clipboard Pressboard (1) Clipboard

19 Product Structure Tree ( Example 3)
Clipboard Level 0 Level 1 Level 2 Spring (1) Bottom Clip (1) Top Clip (1) Pivot (1) Rivets (2) Clip Ass’y (1) Pressboard (1)

20 MRP Inputs 3: Inventory Records File
One of the three primary inputs of MRP Includes information on the inventory status of each item by time period Gross requirements Scheduled receipts Amount on hand Lead times Lot sizes And more....

21 MRP Terminology (1 of 3) Gross requirements Scheduled receipts
Projected on hand Net requirements Planned-order receipts Planned-order releases

22 MPR Terminology (2 of 3) Gross requirements Total expected demand
Scheduled receipts Open orders scheduled to arrive Projected on hand Expected inventory on hand at the beginning of each time period

23 MRP Processing Terminology (3 of 3)
Net requirements Actual amount needed in each time period Gross requirements – available inventory Planned-order receipts Quantity expected to be received at the beginning of the period Offset by lead time Planned-order releases Planned amount to be ordered in each time period

24 MRP Processing Logic: Assembly Time Chart
1 2 3 4 5 6 7 8 9 10 11 Procurement of raw material D raw material F part C part H raw material I Fabrication of part G of part E Subassembly A Subassembly B Final assembly and inspection Weeks

25 Calculation of Gross Requirements
40 50 15 A C B 5 6 7 8 9 10 11 Lead time = 4 for A Master schedule for A 40 20 30 S B C 8 9 10 12 11 13 Lead time = 6 for S Master schedule for S 10 1 2 3 Master schedule for S sold directly Periods 10 40+10 = 50 40 50 20 15+30 = 45 Periods Gross requirements: B Therefore, these are the gross requirements for B

26 Basic MRP Processes Exploding the bill of material
Netting out inventory Lot sizing Time-phasing requirements

27 The MRP Matrix Gross Requirements
ITEM NAME OR NO. LLC - LOW LEVEL CODE PERIOD LOT SIZE QTY MADE IN LY - LEAD TIME Gross Requirements Derived from MPS or planned order releases of the parent Scheduled Receipts On order and scheduled to be received Projected on Hand Beg Inv Anticipated quantity on hand at the end of the period Net Requirements Gross requirements net of inventory and scheduled receipts Planned Order Receipts When orders need to be received Planned Order Releases When orders need to be placed to be received on time

28 MRP Processing: Example 1-School Mate Products
Master Production Schedule Clipboard Lapdesk Item Master File (ınventory record file CLIPBOARD LAPDESK PRESSBOARD On hand On order 175 (Period 1) 0 0 (sch receipt) LLC 0 0 1 Lot size L4L Mult 50 Min 100 Lead time 1 1 1

29 School Mate Products Product Structure Record Clipboard Lapdesk
Pressboard (2) Trim (3’) Beanbag (1) Glue (4 oz) Level 0 Clip Ass’y Rivets Level 1

30 School Mate Products ITEM: CLIPBOARD LLC: 0 PERIOD
LOT SIZE: L4L LT: Gross Requirements Scheduled Receipts 175 Projected on Hand 25 Net Requirements Planned Order Receipts Planned Order Releases

31 School Mate Products (25 + 175) = 200 units available
ITEM: CLIPBOARD LLC: 0 PERIOD LOT SIZE: L4L LT: Gross Requirements Scheduled Receipts 175 Projected on Hand Net Requirements 0 Planned Order Receipts Planned Order Releases ( ) = 200 units available ( ) = 115 on hand at the end of Period 1

32 School Mate Products 115 units available
ITEM: CLIPBOARD LLC: 0 PERIOD LOT SIZE: L4L LT: Gross Requirements Scheduled Receipts 175 Projected on Hand Net Requirements 0 0 Planned Order Receipts Planned Order Releases 115 units available ( ) = 20 on hand at the end of Period 2

33 School Mate Products 20 units available
ITEM: CLIPBOARD LLC: 0 PERIOD LOT SIZE: L4L LT: Gross Requirements Scheduled Receipts 175 Projected on Hand Net Requirements Planned Order Receipts Planned Order Releases 100 20 units available ( ) = -100 — 100 additional Clipboards are required Order must be placed in Period 2 to be received in Period 3

34 School Mate Products ITEM: CLIPBOARD LLC: 0 PERIOD LOT SIZE: L4L LT: Gross Requirements Scheduled Receipts 175 Projected on Hand Net Requirements Planned Order Receipts Planned Order Releases Following the same logic Gross Requirements in Periods 4 and 5 develop Net Requirements, Planned Order Receipts, and Planned Order Releases

35 School Mate Products ITEM: LAPDESK LLC: 0 PERIOD
LOT SIZE: MULT 50 LT: Gross Requirements Scheduled Receipts Projected on Hand 20 Net Requirements Planned Order Receipts Planned Order Releases

36 School Mate Products ITEM: LAPDESK LLC: 0 PERIOD LOT SIZE: MULT 50 LT: Gross Requirements Scheduled Receipts Projected on Hand Net Requirements Planned Order Receipts Planned Order Releases Following the same logic, the Lapdesk MRP matrix is completed as shown

37 School Mate Products ITEM: CLIPBOARD LLC: 0 PERIOD
LOT SIZE: L4L LT: Planned Order Releases ITEM: LAPDESK LLC: 0 PERIOD LOT SIZE: MULT 50 LT: Planned Order Releases ITEM: PRESSBOARD LLC: 0 PERIOD LOT SIZE: MIN 100 LT: Gross Requirements Scheduled Receipts Projected on Hand 150 Net Requirements Planned Order Receipts Planned Order Releases

38 School Mate Products x1 x2 ITEM: CLIPBOARD LLC: 0 PERIOD
LOT SIZE: L4L LT: Planned Order Releases x2 x1 ITEM: LAPDESK LLC: 0 PERIOD LOT SIZE: MULT 50 LT: Planned Order Releases ITEM: PRESSBOARD LLC: 0 PERIOD LOT SIZE: MIN 100 LT: Gross Requirements Scheduled Receipts Projected on Hand 150 Net Requirements Planned Order Receipts Planned Order Releases

39 School Mate Products ITEM: CLIPBOARD LLC: 0 PERIOD
LOT SIZE: L4L LT: Planned Order Releases ITEM: LAPDESK LLC: 0 PERIOD LOT SIZE: MULT 50 LT: Planned Order Releases ITEM: PRESSBOARD LLC: 0 PERIOD LOT SIZE: MIN 100 LT: Gross Requirements Scheduled Receipts Projected on Hand Net Requirements Planned Order Receipts Planned Order Releases

40 School Mate Products Planned Order Report PERIOD ITEM 1 2 3 4 5
Clipboard Lapdesk Pressboard

41 MRP Processing: Example 2
B(1) D(5) C(2) X C(3) Requirements include 95 units (80 firm orders and 15 forecast) of X in week 10

42 X A(2) It takes 2 A’s for each X

43 X A(2) B(1) It takes 1 B for each X

44 X A(2) B(1) C(3) It takes 3 C’s for each A

45 X A(2) B(1) C(3) C(2) It takes 2 C’s for each B

46 X A(2) B(1) C(3) C(2) D(5) It takes 5 D’s for each B

47 MRP Outputs Planned orders (schedule indicating the amount and timing of orders) Work orders Purchase orders Order releases (authorization for the execution of planned orders) Changes to previous plans or existing schedules (revision of due dates or order quantities, or cancellations of orders) Action notices Rescheduling notices

48 Updating the MRP System
Regenerative system Updates MRP records periodically Net-change system Updates MPR records continuously

49 MRP Secondary Reports Performance-control reports Planning reports
Exception reports

50 MRP Dynamics Supports “replanning”
“Time fence” - allows a segment of the master schedule to be designated as “not to be rescheduled” “Pegging” - tracing upward in the bill-of-materials from the component to the parent item That a manager can react to changes, doesn’t mean he/ he should

51 Other Considerations Safety Stock Lot sizing
Lot-for-lot ordering (L4L) Economic order quantity Part Period Balancing Wagner-Whitin algorithm & others Which one to use? The one that is least costly!

52 MRP in Services Can be used when demand for service or service items is directly related to or derived from demand for other services Food catering service End item => catered food Dependent demand => ingredients for each recipe, i.e. bill of materials Hotel renovation Activities and materials “exploded” into component parts for cost estimation and scheduling

53 Benefits of MRP Reduced inventories without reduced customer service
Ability to track material requirements Ability to evaluate capacity requirements Means of allocating production time Increased customer satisfaction due to meeting delivery schedules Faster response to market changes Improved labor and equipment utilization. Better inventory planning and scheduling

54 Requirements of MRP Computer system and necessary software
Mainly discrete products Stable lead times Accurate and up-to-date Master schedules Bills of materials Inventory status records Integrity of data

55 Extensions of MRP

56 Extensions of MRP Closed loop MRP Capacity planning - load reports
MRP II - Manufacturing Resources Planning Enterprise Resources Planning

57 MRP and The Production Planning Process
Forecast & Firm Orders Material Requirements Planning Aggregate Production Resource Availability Master Scheduling Shop Floor Schedules Capacity Realistic? No, modify MPS Yes

58 Closed Loop MRP

59 Capacity Planning Capacity requirements planning: The process of determining short-range capacity requirements. Load reports: Department or work center reports that compare known and expected future capacity requirements with projected capacity availability. Time fences: Series of time intervals during which order changes are allowed or restricted.

60 Capacity Requirements Planning (CRP)
Computerized system that projects load from material plan Creates load profile Identifies underloads and overloads

61 Usually expressed as standard machine hours or labor hours
Capacity Usually expressed as standard machine hours or labor hours Capacity = (no. machines or workers) x (no. shifts) x (utilization) x (efficiency)

62 Capacity Terms Load reports
Department or work center reports that compare known and expected future capacity requirements with projected capacity availability. Load profile Compares released and planned orders with work center capacity Capacity Productive capability; includes utilization and efficiency Utilization % of available working time spent working

63 More Capacity Terms Efficiency
Refers to how well a machine or worker porforms compared to a standard output level Load The standard hours of work assigned to a facility Load percent The ratio of load to capacity Load % = (load/capacity)x100%

64 Capacity Requirements Planning
MRP planned order releases Routing file Capacity requirements planning Open orders Load profile for each machine center

65 resource requirements
Capacity Planning Develop a tentative master production schedule Use MRP to simulate material requirements Convert material requirements to resource requirements Firm up a portion of the MPS Is shop capacity adequate? Can capacity be changed to meet Revise tentative Change Yes No

66 Determining Loads and Capacities
2 copiers, 2 operators 5 days/wk, 8 hr/day 1/2 hr meals, 1/2 hr maintenance per day The machines are new, so efficiency is estimated at 100% Utilization = 7/8 = 87.5% Daily capacity = 2 machines x 2 shifts x 8 hours/shift x 100% efficiency x 87.5% utilization = 28 hours or 1,680 minutes

67 Determining Loads and Capacities
JOB NO. OF SETUP RUN TIME NO. COPIES TIME (MIN) (MIN/UNIT) TOTAL TIME (500 x 0.08) = 45.2 20 1, (1,000 x 0.10) = 110.6 30 5, (5,000 x 0.12) = 603.4 40 10, (10,000 x 0.14) = 1,411.2 50 2, (2,000 x 0.10) = 215.3 min Load percent = 2,385.7 / 1,680 = 1.42 x 100% = 142% Add another shift: Daily capacity = 2 machines x 3 shifts x 8 hours/shift x 100% efficiency x 87.5% utilization = 42 hours or 2,520 minutes Revised load percent = 2,385.7 / 2,520 = x 100% = 94.67%

68 Initial Load Profile Hours of capacity Normal capacity Time (weeks)
Time (weeks) Normal capacity 120 – 110 – 100 – 90 – 80 – 70 – 60 – 50 – 40 – 30 – 20 – 10 – 0 –

69 Remedies for Underloads
Acquire more work Pull work ahead that is scheduled for later time periods Reduce normal capacity

70 Remedies for Overloads
Eliminate unnecessary requirements Reroute jobs to alternative machines or work centers Change lot-sizing or safety stock requirements Split lots between two or more machines Send pieces to the second operation before the entire lot has completed the first operation Increase normal capacity Subcontract Increase the efficiency of the operation Push work back to later time periods Revise master schedule

71 Adjusted Load Profile Hours of capacity Normal capacity Time (weeks)
Time (weeks) Normal capacity 120 – 110 – 100 – 90 – 80 – 70 – 60 – 50 – 40 – 30 – 20 – 10 – 0 – Pull ahead Push back Overtime Work an extra shift

72 Relaxing MRP Assumptions
Material is not always the constraining resource Lead times can vary Not every transaction needs to be recorded JIT can be used with MRP The shop floor may require a more sophisticated scheduling system

73 Manufacturing Resources Planning- MRP II
Expanded MRP with emphasis placed on integration of: Financial planning Marketing Engineering Purchasing Manufacturing Human resources

74 Manufacturing Resources Planning (MRP II)
Goal: Plan and monitor all resources of a manufacturing firm (closed loop): manufacturing marketing finance engineering Simulate the manufacturing system

75 MRP II Market Demand Production plan Problems? Yes No Finance
Rough-cut capacity planning Yes No Finance Marketing Manufacturing Adjust production plan Master production schedule MRP Capacity req. planning Requirements schedules Adjust master schedule

76 MRP II

77 Manufacturing Resource Planning (MRP II)
Forecast Aggregate production plan Customer orders Feasible? Master production schedule Material requirements planning Capacity requirements planning Purchase orders Work orders Inventory Shop floor control Manufacture No Yes Feedback

78 Manufacturing Resource Planning (MRP II)
Forecast Aggregate production plan Customer orders Feasible? Master production schedule Material requirements planning Capacity requirements planning Purchase orders Work orders Inventory Shop floor control Manufacture No Yes Feedback Forecast Aggregate production plan Customer orders Feasible? Master production schedule No Yes

79 Manufacturing Resource Planning (MRP II)
Forecast Aggregate production plan Customer orders Feasible? Master production schedule Material requirements planning Capacity requirements planning Purchase orders Work orders Inventory Shop floor control Manufacture No Yes Feedback Master production schedule Material requirements planning Capacity requirements planning Feasible? Yes No

80 Manufacturing Resource Planning (MRP II)
Forecast Aggregate production plan Customer orders Feasible? Master production schedule Material requirements planning Capacity requirements planning Purchase orders Work orders Inventory Shop floor control Manufacture No Yes Feedback Inventory Shop floor control Manufacture Purchase orders Work orders

81 Manufacturing Resource Planning (MRP II)
Forecast Aggregate production plan Customer orders Feasible? Master production schedule Material requirements planning Capacity requirements planning Purchase orders Work orders Inventory Shop floor control Manufacture No Yes Feedback

82 Enterprise Resource Planning (ERP)
The next step in the evolution that began with MRP and evolved into MRP II ERP system is a computer system that integrates application programs in accounting, sales, manufacturing, human resources and other functions in the firm. ERP provides a system to capture and make data available in real time do decision makers and other users in the organization

83 ERP MRP II with ties to customers and suppliers (connects with supply-chain and customer management applications) Integrates financial, manufacturing and human resources on a single computer system. Provides tools for planning and monitoring various business processes

84 Enterprise Resource Planning (ERP)
Attempts to integrate all departments and functions across a company onto a single computer system that can serve all those different departments’ particular needs Organizes and manages a company’s business processes by sharing information across functional areas Standardized record-keeping permit information sharing and communication throughout the organization

85 Enterprise Resource Planning - ERP
Such an integration is accomplished through a database shared by all the application programs

86 ERP ERP allows companies to:
Automate and integrate many of their business processes Share a common database and business practices throughout the enterprise Produce information in real time ERP systems also include: Supply Chain Management software and Customer Relationship Management software

87 ERP Modules

88 ERP’s Central Database
Finance & Accounting Sales & Marketing Human Resources Production & Materials Management ERP Data Repository

89 ERP Strategy Considerations
High initial cost High cost to maintain Future upgrades Training


Download ppt "Materials Requirements Planning"