TEAM MEMBERS: SKIP POND KENNETH SIMPSON
GAS ABSORPTION COLUMN TEAM MEMBERS: SKIP POND KENNETH SIMPSON
2
OUTLINE BACKGROUND OPERATION PRESSURE DROP FLOODING POINT DATA GRAPH
CONCLUSIONS QUESTIONS
3
BACKGROUND MEDIA --- 3/8” RASCHIG RINGS PACKED MEDIA HEIGHT = 5 FT.
INNER DIAMETER OF COLUMN= 3 IN. DENSITY OF H20 = .994g/cc TEMPERATURE OF AIR = 24.50C AIR ASSUMED TO BE DRY
4
BACKGROUND
5
BACKGROUND
6
BACKGROUND MEDIA --- 3/8” RASCHIG RINGS PACKED MEDIA HEIGHT = 5 FT.
INNER DIAMETER OF COLUMN= 3 IN. DENSITY OF H20 = .994g/cc TEMPERATURE OF AIR = 24.50C AIR ASSUMED TO BE DRY
7
OPERATION LIQUID DISTRIBUTION/FILM “RICH” ENTERING GAS MASS TRANSFER
COLLECTION OF LIQUID GAS OUTLET
8
OPERATION PROBLEMS FLOODING PRESSURE DROP CHANNELING
INADEQUATE LIQUID FILM COVER
9
PRESSURE DROP (P) FLUID FRICTION MEDIA TYPE AND SHAPE TOWER DIMESIONS
LIQUID/GAS FLOW RATES DENSITY & VISCOSITY OF LIQUID
10
FLOODING POINT GAS FLOW FORCED THROUGH LIQUID CORRELATION WITH P
PACKING FACTORS Pflood = .115Fp.7 PACKING FACTOR > 60 ASSUMED = Pflood = 2 IN. H20/FT.
11
GAS COLUMN DATA
12
CONCLUSIONS Pflood = 2 in. H20/ft. of packing P(geyser) = 26 in. H20
ENGR.435 COLUMN = 10 in. H20 P(geyser) = 26 in. H20 COLUMN BECOMES INOPERABLE OPTIMUM OPERATING POINT 1/2 GAS FLOW RATE OF FLOODING 1.5 LBS./MIN
13
QUESTIONS ???