Pinwheel Technologies (C3)
PDR: 4/1/08 Pinwheel Technologies (C3) Heather Blaha Matt Fuxa Joey King Michael McConnell Domenic Tassoni
2
Overview Vertical-Axis Wind Turbine Interchangeable Shaft
Savonius Turbine Interchangeable Shaft
3
Last Week’s Action Items
Define ‘Step Two’ Plan from Raw to Final Mechanical Components Finalize circuit logic Decide on intelligence Circuit Diagram
4
‘Step Two’ Step One was receiving parts
Step Three is displaying the final product Step Two is EVERTHING IN BETWEEN Fabrication Assembly
5
‘Step Two’ Shafts Base Turn to proper size
Install bearings, sprockets, shaft couplings Machine Flats and Keyways Align centers Base CNC base plates Mounting for bearings, generator, battery Seatings for vertical supports and diagonal straps
6
‘Step Two’ Turbine Hand Crank Machine barrel into blades
Mounting blades to the shaft Hand Crank Discuss with Welder Cut/Drill pieces to make his job easier
7
Circuit Design Circuit Block Diagram
Microcontroller input = current sensor Decided on ‘slow drain’ circuit Real circuitry is overly complicated for MEs Products already available
8
Circuit Design
9
This Week’s Action Items
Finish all machining Shafts – Matt, Joey, Michael Baseplate – Domenic, Heather Turbine – Heather, Matt, Domenic Hand Crank – Joey, Michael, (Paul)
10
This Week‘s Action Items
Final Documentation Rough Draft Plan who/how: Joey will take the lead on writing/organizing Meet/Discuss to divide up sections and assign work to ‘experts’ Outline as a group Combine individual efforts into one coherent report
11
Conclusion So close…yet so far away. Show Stopper: Rotating Parts!
Behind: Waiting for electronic components We can catch up!