eRecruit Project Human Resource Unit Liaison Meeting June 19, 2009
2
Who is Involved? MAIS/ITCS – Judy Aldrich – Ann Tuttle – Chris Fillmore – Brian Miller – Radha Dhandapani – Pang Hang – Darryl Christensen UHR – Jane Miller – Katie McCollum – Michelle Kinker – Traci Buckner – Jeanne Christensen – Tammy Deane – Tim Wood UHSHR – Jan Mulcrone – Lynda Lauerman – Mindy Warden UNIT REPRESENTATIVES – Gwen Kearly, Nurse Recruitment – Pam Quinlivan, Internal Medicine, Medical School – Karen, Sloan, MAIS/ITCS – Patrick Smitowski, LS&A – Tina Truskowski, College of Engineering – Jodi Simpson, MAIS – Jennifer Knauf, SNRE – Stacy Johnson, Facilities and Operations – Beth Manning, Flint – Ginny Zarras, Dearborn
3
Project Team Feedback eRecruit Team EvaluationsScale of 0-5Total Points*% of whole Job Opening Comfort4.18181.00% Managing Applicant Comfort3.97777.00% Applicant Experience Comfort3.46868.00% Overall Comfort3.9879.579.50% *100 possible points
4
January Overview Session Feedback Number of Show Stoppers Jobs in eMploy per year NYY/NBlankTotal Total -Blanks 1 to 53113144935 5 to 10141092415 10 to 202415124230 I live there3222114736 10151046162116 Percentage of total (minus blanks)87.07%4.31%8.62%
5
January Fit-Gap, Appreciated Features Multiple hires on a single job opening Ability to list more than one job code on a single job opening (supports Underfill process) Corrections made in one place only Ability to save a draft job opening Preview capability of job opening posting Ability to email applicants from inside the product Location of resume Libraries containing standard language
6
Hottest Issues Mass dispositioning Mass print resumes Mass email resumes Restricted table fix RIF status fix Candidate Summary Form with pertinent information Cover letters Test score details Applicant experience
7
Frequently Mentioned Security of employee bids and what hiring managers can see Searching and finding jobs Resume wizard Look and feel
8
Design Philosophy Use familiar terms Populate fields from tables Hide unused fields Default standard values Reduce the number of clicks Consider business practices Secure data elements
9
Timeline Design, March 1 – May 29 Requirements documentation, May 1 – June 30 Development, June 1 – November 30 System Testing, December 1 – March 31 End to End Testing, March 1 – March 31 Communication and Performance Support (Unit Readiness), January 1 – August 31 Training, April 1 – August 31 Implementation, May 3 – June 7 Stabilization, June 7 – September 7
10
Questions?