© British Telecommunications plc 2001 Dynamic Scheduling in Mobile Workforce Management Ralf Keuthen PLANET Information Day, Ulm, 2003
2
© British Telecommunications plc 2001 Contents Automated Mobile Workforce Management The Workforce Scheduling Problem TASKFORCE System Overview Issues Current/Future Work
3
© British Telecommunications plc 2001 Mobile Workforce Management a.p.solve -- A Short History è Involved in mobile workforce management since 1987. è Produced two major Work Management Systems which have evolved into the TASKFORCE products we currently market. è a.p.solve (100+ employees) was spun out via the British Telecom’s Brightstar business incubator initiative in April 2003. è a.p.solve’s planning and scheduling products primarily support the management of mobile workers via Personal Digital Assistants and mobile telephony.
4
© British Telecommunications plc 2001 Scope Large telecommunication, cable, utility and fix & repair companies typically maintain a fieldforce of 100s - 10,000s of technicians The fieldforce supplies provision of service, repair and maintenance tasks on a daily basis (between 1000s - 100,000s of tasks/day) Customers è Residential, Business (provision, repair) è Company itself (maintenance, repair)
5
© British Telecommunications plc 2001 Example: Mobile Workforce at British Telecom BT Customer Access: a.p.solve’s TASKFORCE products currently schedule BT’s workforce of Service Technicians. ~25,000 field technicians ~150,000 tasks every day across the United Kingdom. A high quality service at low operational cost needs to be delivered.
6
© British Telecommunications plc 2001 Work Management Organisation Domains: Geographical partition of the work area into autonomous domains Domains controlled by automated work management system Supervised by a human controller
7
© British Telecommunications plc 2001 Organisation: How it works Call Centre Network Service TASKFORCE Handheld terminal Laptop Mobile Customer Service Work allocation and visualisation Dispatch work to technicians
8
© British Telecommunications plc 2001 Organisation: How it works Customer Service: è take customer calls è arrange appointments TASKFORCE: è provide customer service with a selection of appointment slots è Allocate work to technicians è dispatch work to technicians Technicians è receive work details è travel to and carry out work è report back when work is finished
9
© British Telecommunications plc 2001 Workforce Management: From a Scheduling Point of View
10
© British Telecommunications plc 2001 Scheduling Model Resources: è Technicians è Vehicles and other equipment Activities: è provision, repair and maintenance work Constraints: è time windows, access restrictions è precedence constraints è co-op, assists, etc.
11
© British Telecommunications plc 2001 Main Objectives Right man - right time - right place - right costs Maximise productivity è number of tasks scheduled è most efficient resource for each task Ensure a high quality of service è compliance with agreed appointments & due dates è work importance - Minimise costs è travel times è waiting/idle times è overtime
12
© British Telecommunications plc 2001 Other Objectives Workforce satisfaction è task preferences è preferred working areas Business rules è every technician gets a job è avoid the splitting of tasks over breaks (if possible) Avoid disturbances è robust schedules è flexible schedule Some of these contradict one another
13
© British Telecommunications plc 2001 Issues Dynamics/Uncertainties/Complexities of problem Scale The need for a totally automated, online, system.
14
© British Telecommunications plc 2001 Dynamics Tasks The company and its customers can è request è cancel è amend tasks (at all time!!) Resources Availability subject to last minute changes è personal absence, sick leave, etc è changes to task completion times è vehicle breakdown
15
© British Telecommunications plc 2001 Uncertainties Duration of tasks Uncertain due to è exact scale of work often unknown before a technician arrives on site è varying technician skill levels Travel times Uncertain due to è weather è traffic conditions Business objectives Resource manager can change business objectives
16
© British Telecommunications plc 2001 Complexities Complex mixture of tasks: è different execution target times (appointment/commitments) è different task priorities: low - high priority tasks è Wide range in the duration of tasks: 8 mins - several days Inter task dependencies can be complex è coops, assists tasks è pre-installation tasks è stock point visits, etc Site access restrictions è security access è business opening times è road closure, etc
17
© British Telecommunications plc 2001 Complexities Geographical complexities è diverse (London vs East Wales, etc) è Preferred working areas Skills è heterogeneous workforce è diverse skill set Work type and work skill imbalances è some geographical areas can be under resourced è certain skills can be under resourced Business Rules
18
© British Telecommunications plc 2001 Scale Scale of individual problems domain dependent Technicians: è 10s to 100s of technicians Tasks: è 100s to 1000s of tasks Scheduler needs to cope efficiently with all domains
19
© British Telecommunications plc 2001 Issues No realistic forecasting possible! Assumed ‘static’ environment? è Optimised schedules quickly become sub optimal or even infeasible è What is optimality in an dynamic environment? First thing in the morning everything changes !! (sick leave, new tasks, etc) Building robust/flexible schedules? è Limited applicability è Radical changes to the current schedule may be desired
20
© British Telecommunications plc 2001 Scheduling Opportunities: Impact of Personal Digital Assistants on Scheduling Practice: Mobile phones, laptops, handheld terminals, the Internet, etc è allows to dispatch tasks to mobile workers in real time è tasks are (usually) dispatched one by one Scheduling impact: è allows to adjust the schedule to the changed environment è allows to correct (some) scheduling decisions made earlier However, the time available to react to changes is very limited
21
© British Telecommunications plc 2001 Available Tools: Identify processing bottlenecks Exploit scheduling opportunities Maintain schedule stability and existing process plans. Refine solutions. Repair constraint violations. Summarise solution states for human controllers and software agents. Dispatch scheduling tasks to field technicians with respect to current schedule state and customer demand.
22
© British Telecommunications plc 2001 TASKFORCE System Overview
23
© British Telecommunications plc 2001 Needed Automation Automated data flow from order source systems to job dispatch. Schedule revision must be automatic and robust. On line Dispatcher must be able to cope with corrupted schedules. The real-line monitoring of the location of mobile technicians and their expected completion times is important.
24
© British Telecommunications plc 2001 TASKFORCE Developed by BT and employed since 1997. TASKFORCE supports: Resource Management Operations Management Schedule/Jeopardy Management Progress Management Scheduling & Dispatching
25
© British Telecommunications plc 2001 System Overview
26
© British Telecommunications plc 2001 Schedule Manager Planer that transforms customer orders (service requests) into scheduling variables with their associated constraints Identifies tasks in jeopardy of becoming tardy Pre-processes tasks & resource information according to business rules Calls scheduling tools to create/maintain executable schedule
27
© British Telecommunications plc 2001 Scheduling Needs Batch Scheduling Schedule revision Appointment booking support Interrupt Scheduling Route Optimisation Schedule Dispatcher What-If Scheduling Schedule Visualisation & Manual scheduling support
28
© British Telecommunications plc 2001 Architecture Overview Visualiser DS Pre-scheduler Optimiser Interrupt Scheduler Dispatcher Intelligent Appointer Schedule Manager
29
© British Telecommunications plc 2001 Batch Scheduler Runs overnight to construct high quality schedule for the following day è Build provisional start-of-day schedule è Schedule construction & route optimisation Techniques: è Chronological backtracking based Constructive Algorithm assign important and hard to schedule tasks è Local Search based optimisation supported by a constraint net to ensure feasibility Stochastic Local Search: Simulated Annealing
30
© British Telecommunications plc 2001 Dynamic Scheduler Run while schedule is being executed to maintain a high quality schedule Responsibilities: è Absorb schedule changes and most up to date information è Rebuild, repair, update & re-optimise provisional schedule How it works: è Perform frequent short batch runs to rebuild a feasible schedule è Pass provisional schedule to Schedule Manager
31
© British Telecommunications plc 2001 Dynamic Scheduler Pre-scheduling: è Reload and try to rebuild old schedule Tree Search assigning remaining important and hard to schedule tasks Optimisation: è Low Temperature Simulated Annealing. Currently looking into more focused techniques such as exploring large neighbourhoods based on an ejection chain model, Guided Local Search, etc
32
© British Telecommunications plc 2001 Intelligent Appointer Controller/call centre support tool Heuristic based è find a set of feasible appointment slots based on the current schedule è suggest feasible appointment slots to human controller è controller books appointment slot and associates time windows with the new task è task is sent to schedule manager
33
© British Telecommunications plc 2001 Interrupt Scheduler Automatic Schedule Revision: Reallocation algorithm to support situations where important work would otherwise fail. è The system can’t find an available resource for high priority work at specified times è Interrupt scheduler identifies a sequence of reallocations to free a technician to perform the work
34
© British Telecommunications plc 2001 Automatic Dispatcher Online and event triggered System Responds to requests for work from field force in real-time, making alterations to the planned tour as required. Supports the management of uncertainties & last second changes to the schedule associated with: è travel time & task duration è arrival of new high priority work and cancellation of already scheduled work
35
© British Telecommunications plc 2001 Dispatching Algorithms Rule based system. è If Field Technician request work then the Dispatcher identifies a task for the technician to service. Rule Examples: è Find work on site for technicians rather than travel to new locations è Give preference to tasks getting close to their deadlines è Keep technicians from travelling outside their preferred working area è etc, etc This may result in the need to repair a damaged schedule
36
© British Telecommunications plc 2001 What-if and Manual Scheduling Are off-line schedulers that support work controllers by providing the visual and analysis tools to try out different scheduling parameters and allocations to discover improvement opportunities without risk. Changes to scheduling parameters can be applied to current or archived data and the resulting schedule can be examined in an off- line environment. Changes can then be applied to live sites.
37
© British Telecommunications plc 2001 Schedule Visualisation Tools Compress schedule information and represent it in a way that can easily be captured by the user Provides the human controller with: è statistics è tour task tables è Gantt chart è map tour representation
38
© British Telecommunications plc 2001 Schedule Visualisation: Gantt Chart
39
© British Telecommunications plc 2001 Schedule Visualisation: Map
40
© British Telecommunications plc 2001 Current/Future Work
41
© British Telecommunications plc 2001 Dynamic Work Crew Scheduling Field force activities can often not be carried out by a single person but need multi-skilled crews è safety reasons (gas, electric, etc.) è activity reasons (heavy equipment, etc.) è specific equipment (elevator unit, crane, etc) Examples: Expansion/repair of the telephone network Electricity/gas/water supply to new build homes etc.
42
© British Telecommunications plc 2001 Dynamic Work Crew Scheduling Workpackages instead of single tasks Complex workpackages è long tasks (2h to a few weeks) è many inter task dependencies è different configurations possible Skill matching è is a crew skill the sum of its crew member skills? Task duration è If 2 people need 1 hour do 4 people need only 1/2 hour? How and when to build, amend or break crews in a dynamic environment?
43
Intelligent End-to-End Fieldforce Automation www.apsolve.com