1 8.7.04TRD Status meeting HdClemens Adler TRD ROC Status

2 8.7.04TRD Status meeting HdClemens Adler Production Status L1C1 Material arrived last week Glued 3 L1C1 Frames last week 1 L1C0 Frame finished Started wiring this week (Meteor switched off for last 8 cm) Try to keep up production rate of 2 Chambers per week (probably not sustainable, due to holidays)

3 8.7.04TRD Status meeting HdClemens Adler Production Problems „Warping of Padplane panel assembly disapears when supported on all sides Wire tension measuring machine (prototype): –Very sensitve. –Position accuracy not to spec. – has problems finding all wires Holger: most problems will be soved with the“ real“ machines.

4 8.7.04TRD Status meeting HdClemens Adler Chamber Status Finished: 3 x L1C0 (1 glued, 2 taped waiting to be tested) 3 x L2C0 (3 taped) 2 x L1C1 (mid next week)

5 8.7.04TRD Status meeting HdClemens Adler Dead Pads David measured connection of cables on one glued panel: –2 Channels were not connected Need to measure all panels? (very time consuming)

6 8.7.04TRD Status meeting HdClemens Adler Material Status: L-Profiles L1C1 in Production Next: L2C1,L3C1 Quality is very good now after some opimization. Rate: ~4/week (average)

7 8.7.04TRD Status meeting HdClemens Adler Material Status: Front Profiles L4 in Production Production rate: ~9/week

8 8.7.04TRD Status meeting HdClemens Adler Material Status: Padplanes L2C0: broken traces are repaired by Optiprint Arrived: L1C1, L5C1, L5C0, (L6C0) At CERN: L3C0, L4C0 Next: L2C1 Missing: L3C1, L4C1 Optiprint has to reorder base FR4 -> only 0.38 mm thickness available (instead of 0.36).

9 8.7.04TRD Status meeting HdClemens Adler Material Status: Fischer Panels Production will be finished in KW30. Missing: L2C1, L3C1.

10 8.7.04TRD Status meeting HdClemens Adler Chamber type distribution Original plan (15.4.04): -Bukarest: L1C1, L2C1 -GSI:L3C1, L5C1 -Hd:L4C1, L6C1 (skipped-> L1C1) New proposal: -Hd: L1C1, ??? (L6C1,L0C1,++) - GSI: L5C1, L4C1 (last Padplane type) - BukarestL2C1, L3C1 - Dubna:LxC0

11 8.7.04TRD Status meeting HdClemens Adler HD Test Room Gas lines are in place, first leak rate measurements (but Oxygen sensor problem). Currently: bad CO2 X-Ray tube waiting for appoval by Gewerbeaufsichts- amt. X-Y-test stand is ready.