Uli Schäfer 1 JEM1: Status and plans JEM1.1 Status Plans
2
Uli Schäfer 2 Largely identical to JEM 1.0 Additional daughter module: Control Module (CM) CAN VME control Fan-out of configuration lines JEM1.1
3
Uli Schäfer 3 JEM status 4 JEM 1.0 main boards available 3 are fully working, 1 has short on TTCdec module connector 1 JEM 1.1 main board available, so far ok. All populated with input modules 5 new G-link modules available Assembled by Bruno So far 3 working 0-version of control module No CAN No VME CPLD Sum processor configuring from flash (ACE, working now!), all others via VME JEM1s working (standard tests) Firmware (sum, input) stable - new readout format successfully tested
4
Uli Schäfer 4 JEM1 status : tests JEM tests done in Mainz, at RAL and CERN test beam Up to 4 JEMs in a 9U crate allowing for FIO tests either direction, along with VMM, TCM, CMM (and CPMs!) External data sources for LVDS : 1 DSS 16-channel (MZ) Several DSS (RAL) LSM (RAL) PPr (RAL, CERN - 4 channels) External data sinks for Merger signals : 2 CMMs (RAL) Readout path: Complete ROS (RAL, CERN) G-link tester with f/w pattern comparison (MZ)
5
Uli Schäfer 5 JEM1.0 status : tests System tests at RAL: (from June 2004) DSS JEM crate CMM system CMM ROD ROS ROD ROS Comparing readout data against simulation. Data taken up to 5 slices of JEM DAQ data. Trigger rate up to 60kHz, 4*10 6 events analysed, no errors observed on JEM readout. Interface tests: LVDS inputs, merger outputs, FIO, readout links BER measured, no errors in 10 13 (CMM,FIO), 10 14 (ROD), 10 15 bits (LVDS)
6
Uli Schäfer 6 FIO tests : delay scan All data latched into jet processor on a common clock edge Sweep TTCrx delay setting, 104ps steps Measure data errors on each channel : 10 bits, 5 signal lines Single channel 8ns error free All channels 6.5ns error free All interfaces ok, timing ok, latency within budget (<9.5 ticks) But: noise observed on FIO lines…
7
Uli Schäfer 7 JEM1 noise problem FIOs using 1.5V DCI/60Ω signalling. CMOS thresholds 35%/65% Noise observed close to thresholds (full activity) Screen shot typical, not worst case: All signal lines active -- 1 input proc. -- every other off
8
Uli Schäfer 8 JEM1 problems Difficult to distinguish cross talk ground bounce FPGA pins / vias, daughter module GND connection Check on merger lines: 2.5V signals Noise 1.25 V pp
9
Uli Schäfer 9 JEM1 noise Current assumption: Noise might have several contributions but dominated by crosstalk: buses are typically 30cm long, 130µ tracks, 290µ pitch 160µ gap No effort available for simulation Build test board with widely spaced 60Ω tracks (.46 mm)
10
Uli Schäfer 10 Various track densities Varied GND return quality (GND shields) No results yet Cross-talk tester
11
Uli Schäfer 11 JEM1.2 Design JEM1.2 with wide spacing (~.5mm?) Need more routing space, signal layers,… Significant amount of design work
12
Uli Schäfer 12 JEM1.2 Signal layers: 2 microstrip 2 striplines 1 dual-stripline Micro-vias Blind vias.4mm Buried vias Total: 2.2mm Components on bottom!
13
Uli Schäfer 13 Plans Continue cross-talk tests Layout JEM with widened data buses Further design work required JTAG test adapters Input modules (add voltage/temperature sensor) Control module (add CAN / VME / configuration circuitry) Readout tests (9U RODs) Further tests with stress patterns required on all interfaces, particularly on FIOs Tests at elevated temperature ? Further LVDS tests required (LSM, PPR) PRR in August ? Production time ~8 weeks Need test rig in MZ (or HD?) LSM / GIO / CMM ? / ??? !!!! Lead time for FPGAs !!!!