PDR: 4/10/08 Pinwheel Technologies (C3) Heather Blaha Matt Fuxa Joey King Michael McConnell Domenic Tassoni
2
Overview Vertical-Axis Wind Turbine Vertical-Axis Wind Turbine Savonius Savonius Turbine Interchangeable Shaft Interchangeable Shaft
3
Last Week’s Action Items Finish all machining Final Documentation
4
Machining Summary Made up lost ground. Base plates machined out of HDPE. Shaft-Hub connection. Flats and keyways on shafts. Aluminum Struts. Hand crank.
5
Documentation Summary Divide Focus and Conquer Domenic: CAD. Heather: Bill of Materials, project nugget. Mike and Matt: Executive Review and User Interface. Joey: Link to web and organization. Unite to edit and organize documentation. Integrated into the website.website.
6
Action Items Full Assembly of the Turbine Systematically assemble subsystems. Unite into entire turbine. Integrate circuit.
7
Action Items Cont. Develop a Prototype Display Presentation. Decide what points are to be focused on. Determine who will say what. Possible real time assembly. Outline as a group.
8
Concerns and Showstoppers Last week: Rotating Parts Resolved machined with advice from Leon. Sealed bearings Wear-in period. Run in drill press. Time is short! Expect complications. Solve them immediate as they arise.
9
Beyond the Last PDR Testing will crucial in the days that follow the turbine assembly. Small adjustments to the prototype may be made. A more accurate understanding of the concept will be achieved.
10
Conclusion Home Stretch Assembly First Presentation Second Testing Finally On Schedule Stay that way!
11
Thank You!