Slide 1UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE UCSB 4-Hybrid Thermal Test System Status 13 October 2003 Sam Burke Lance Simms UCSB HEP Group
2
Slide 2UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE Status UCSB 4-Hybrid Thermal Test system is operational ARCS and ACDC software integrated so that test is a “one button” operation
3
Slide 3UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE Setup in UCSB Clean Room
4
Slide 4UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE UCSB Cold Box
5
Slide 5UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE Installing Hybrid/PA’s
6
Slide 6UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE Pulser: Functional Pulser had been triggering on noise. Needs to be synchronized with ARC Clock. à Twisted cable from ARC Controller card used à Eliminated noise in UCSB LVDS/CMOS Converter No LVDS signals from ARC Controller Card
7
Slide 7UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE LVDS Signal? ARC Boards with functioning External Bus à Ser 29 à Ser 31 ARC Boards with non-functioning External Bus à Ser 56 à Ser 57 à Ser 59 LVDS Signal Noise
8
Slide 8UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE ARC Controller Problem Bad Batch of ARC BOARDS: LVDS Driver and LVDS Receiver U32 and U33 were switched during board assembly. Problem was never discovered. External Buss connector and associated IC’s on lower left of photo. U32
9
Slide 9UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE With Pulser Operational… Opens detectable in “Scope Mode” Intentionally Plucked Bonds Show up in Pedestal Profile
10
Slide 10UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE With Pulser Operational…. Opens are also detectable in Pedestal & Noise Test Plucked Bonds
11
Slide 11UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE Grounding Issues Same Problem CERN was having…. Huge spikes in noise at APV edges
12
Slide 12UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE Using their same method… Ground lines connected to Support plate by silver strip Problem Solved: No more spikes
13
Slide 13UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE Thermal Cycle Test Test Time: ~42 min. Three Sets of Tests: Pedestal & Noise Pulser Short Detection
14
Slide 14UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE Automated Test Results Final Report After Thermal Cycle Test: Lists -Shorts -Opens -Noisy Channels
15
Slide 15UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE So Far At UCSB 6 Hybrids Bonded and Thermal Cycled 30216711300712 30216711600699 30216711500720 30216711500730 30216711500732 30216711500733 Serial # Shorts Opens Failure at -20 0 0 0 0 0 0 0 0 0 0 0 0 No
16
Slide 16UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE And Now… Building a new peltier plate in order to bring test time down Goal: Loading + Testing + Unloading in ~50 minutes Nevertheless, ready to thermal test on mass scale