1
Aloha Proof Module Design Cabled Observatory Mechanical Presentation School of Ocean and Earth Science and Technology February 2006
2
Aloha Phase 1 Mechanical Systems Main Assemblies: Float Package Proof Module Cable Termination Frame Bottom Line: -Mechanicals have gone smoothly -Manufacturing and testing complete -Final assembly remains -Quick tour or three main assemblies
3
Buoyancy Test Float allows for the retrieval of the proof module. Link between termination frame and proof module will be cut by ROV.
4
Seawater Return Hydrophone Proof Module Electronics Housing Assembly Status: -Manufacturing completed -Passed pressure testing -Partially assembled AT&T MUX Endcap (tube not shown) Strong-back UH Electronics Titanium Shackle
5
Proof Module Cable Termination Frame Status: -Manufacturing and tension testing complete -Waiting for Tyco/ODI cable harness for final assembly
6
Termination Frame Tension Test -Frame is inverted inside railway
7
20Kpounds-Passed