3 Last Week  Assemble the vehicle body Complete  Redesign of Arm Mechanism Complete – No automatic extension Team HazardHawk 2008

4 Last Week Order Parts for Arm Complete All necessary parts ordered, scheduled for delivery on 3/26 - 3/27  Gather Electronic Components Complete: Components collected and circuit diagram developed Team HazardHawk 2008

5 Concept Status  Inventory List: all major components ordered Team HazardHawk 2008

6 Concept Status  Redesigned Arm Mechanism Simplifies design: eliminates automated extension Retains important design characteristics Material ○ PVC ○ Epoxy

7 Concept Status, arm

8 Concept Status  Electronics: Circuit Diagram Approved by Mr. Brownell

9 Action Items  Complete Mock-up of circuit assembly Assemble electronic components on tabletop  Install Bearing Mounts and Drive Shafts Positioning must be precise to reduce resistance to shaft rotation Team HazardHawk 2008