BUILDING STRONG ® USACE/FEMA 2011 Remedial Action Program Workshop December 6-9, 2011 Orlando, FL
2
BUILDING STRONG ® RFO & Contracting 2011 USACE/FEMA RAP Workshop
3
BUILDING STRONG ® 2011 USACE National Events Total personnel deployed to support CONUS response activities: 2143 Total FEMA mission assignments: 176 ($630 million) Total FCCE dollars: $180 million MR&T funds: $23.4 million
4
BUILDING STRONG ® Planning and Response Teams (PRT) DISASTER RESPONSE & RECOVERY Emergency Power Water & Ice Debris Temporary Housing / Critical Public Facilities Infrastructure Assessment Temporary Roofing LEGEND Team members: Are all volunteer All work for USACE Are trained Are capable of deploying within six hours notice How Do PRTs Work? USACE Districts are proponents for FEMA missions Teams rotate deployments DISASTER
5
BUILDING STRONG ® RFO & Contracting IssueRecommendationsStatus 1.Action #1: Develop National level training with current SMEs 2.Action #2: Better publicize location of ACI (ENGLink) and other IDIQ contracts (SWF web site) 3.Action # 3 Include regional IDIQ in National data base. Start Date: 9 Dec 2011 Est. Completion Date: 31 May 2012 Action Lead: NCO Ongoing Resolutions: Obstacles: PDT Members: HQS USACE PARC Rep NWD District CT PRT CS/Contr Issue Title: Reinvigorate National CT Cadre Problem Statement: Knowledge gap Key Discussion Points: Trained Members as SMEs on contracting aspects of emergency acquisition (Stafford Act focused) deploy to RFO (district or national cadre) reach back
6
BUILDING STRONG ® RFO & Contracting IssueRecommendationsStatus Best Practices CT chief at RFO come from supported district (situational dependent) Perform Risk Management of Contracting issues Issue Title : Reinvigorate National CT Cadre (Cont’d)
7
BUILDING STRONG ® RFO & Contracting IssueRecommendationsStatus 1.Action #1: Complete NWK Sharepoint Start Date: 9 Dec 2011 Est. Completion Date: 1 March 2012 Action Lead: NWK 2.Action#2: Vet with HQS & MSCs SAD RFO Training and NWK Sharepoint & revise Start Date: 15 March 2012 Est. Completion Date: 1 April 2012 Action Lead: SAD Ongoing Resolutions: Obstacles: PDT Members: SAD G-33 USACE RSC SAD HQS USACE SWK NWD SWD POD Issue Title: Doctrine Problem Statement: Requires enhancement Key Discussion Points: HQ USACE Overarching Guidance Structure: standardized scalable and flexible to meet common and catastrophic Template of information used by RFO leadership – mission predictions showing targets Lines of communication ICW internal & external partners
8
BUILDING STRONG ® RFO & Contracting IssueRecommendationsStatus 3.Action #3 Add RFO Information to HQS USACE All Hazards OPORD Start Date: 9 Dec 2011 Est. Completion Date: 12 January 2012 Action Lead: HQS USACE 4.Action # 4 Define best COA for interoperability: w/ENGLink/ FEMA Start Date: 9 Dec 2011 Est. Completion Date: 12 January 2012 Action Lead: RSC Issue Title: Doctrine (Cont’d)
9
BUILDING STRONG ® RFO & Contracting IssueRecommendationsStatus Best Practices: RFO leadership from supported district Senior Civilian needs Construction Project Planning and Execution experience Release of individual PRT approved by RFO Cdr Client Relationship Management (CRM) Request ACE-IT EERT Request ULA Support – scalable IR deploy to RFO (preferably from supported district) Work with HQ USACE RAO Mgr on Job Hazard Analysis & Physical requirements. Employ LGLs early Issue Title: Doctrine (Cont’d)
10
BUILDING STRONG ® RFO & Contracting IssueRecommendationsStatus 1.Action #1: MSCs designate individuals to complete RFO and sharepoint training Start Date: 1 May 2012 Est. Completion Date: 31 May 2012 Action Lead: DEMs Ongoing Resolutions: Obstacles: PDT Members: Division Emergency Managers Issue Title: Training Problem Statement: Requires enhancement Key Discussion Points: Other RFO staff training
11
BUILDING STRONG ® RFO & Contracting IssueRecommendationsStatus 2.Action #2: Add RFO Training to weekly Readiness Review “Bubble Chart.” Start Date: 1 May 2012 Est. Completion Date: continuing program Action Lead: UOC BEST PRACTICE: PRTs – AO & MM PgM, PM training under each PRT Ongoing Resolutions: Obstacles: PDT Members: Issue Title: Training (continued)
12
BUILDING STRONG ® RFO & Contracting IssueRecommendationsStatus Best Practices: PRB at RFO w/ FEMA and State – possibly city(ies) Data release protocols Collaborate w/FEMA Establish RFO email addresses Issue Title: Management Information / Knowledge Management