NGAO System Design Phase Management Report - Replan NGAO Meeting #6 Peter Wizinowich April 25, 2007.

Similar presentations


Presentation on theme: "NGAO System Design Phase Management Report - Replan NGAO Meeting #6 Peter Wizinowich April 25, 2007."— Presentation transcript:

1 NGAO System Design Phase Management Report - Replan NGAO Meeting #6 Peter Wizinowich April 25, 2007

2 2 Presentation Sequence Review of SEMP Status Review of Replan Budget Next Steps

3 3 SEMP Status

4 4 SEMP Tracking Tracked (Excel) version of the plan posted at http://www.oir.caltech.e du/twiki_oir/pub/Keck/ NGAO/SystemDesignP hasePlanning/NGAO_ SD_schedule_v20_trac ked_final.xls http://www.oir.caltech.e du/twiki_oir/pub/Keck/ NGAO/SystemDesignP hasePlanning/NGAO_ SD_schedule_v20_trac ked_final.xls Excel version highlights what’s complete, what’s late, what’s due within next month & status of work scope planning sheets.

5 5 SEMP Summary 1 WBS 1. SD Phase Management –On-schedule, except for replan (~ 1 month late) WBS 2.1. Science Requirements –1 work scope planning sheet approved. No others submitted. –All 13 science cases scheduled for completion by end of April. None completed. –Version 1 of Science Case Requirements complete. Version 2 due in Mar/07 WBS 2.2-2.3. System Requirements Document –1 planning sheet approved, 2 late. –Version 1 complete. Version 2 due in March. Need more feedback, especially on science operations requirements. –Version 1&2 of traceability matrix late.

6 6 SEMP Summary 2 WBS 3.1.1. Performance Budgets –8 planning sheets approved, 1 submitted, 5 late. –Model assumptions. 3 complete & 1 on schedule. –Model/tool validation. 3 complete & 2 late. –Performance budgets. 1 complete, 6 late (2 others due later). –Version 1 of summary late. WBS 3.1.2. Trade Studies (29 total) –12 planning sheets approved, 1 needs changes, 11 late. –9 complete, 1 cancelled & 15 late. WBS 3.1.3. System Architecture. –Version 1 should have started, but hasn’t. WBS 3.4. Science Operations –2 WBS elements should have been started pre-March, but haven’t & another 5 should have started in Mar. WBS 3.5 Science Instruments –Only Interferometer started. 4 others should have been started & 1 is late. WBS 4 SEMP –No significant work planned yet

7 7 SEMP Milestones Status MILESTONEDATEDESCRIPTION SD SEMP Approved 10/9/06 Approval of this plan by the Directors. Initial SEMP version released to Directors for comment on 9/12 & final version on 9/29/06. SD phase contracts in place 10/27/06 Contracts issued to Caltech & UCSC for the system design phase. Science Requirements Summary v1.0 Release 10/27/06 Initial Release of the Science Requirements as input to trade studies and performance budgeting System Requirements Document (SRD) v1.0 Release 12/8/06 Initial release of System Requirements with emphasis on the science requirements Performance Budgets Summary v1.0 Release 2/27/07 First round of all performance budgets complete & documented SRD v2.0 Release 3/22/07 Second release of System Requirements Doc Trade Studies Complete 5/25/07 All trade studies complete & documented (as a series of Keck Adaptive Optics Notes) SRD v3.0 Release 7/12/07 Third release of System Requirements System Design Manual (SDM) v1.0 Release 8/31/07 First release of System Design Manual Technical Risk Analysis v1.0 Release 11/13/07 First round of project risk analysis complete & documented Cost Review Complete 11/30/07 Project cost estimates complete, documented & internally reviewed SDM v2.0 Release 1/8/07 Second release of System Design Manual System Design Review Package Distributed 3/4/08 SDR documents sent to reviewers System Design Review 3/31/08 SDR meeting SDR Report & Project Planning Presentation at SSC meeting 4/14/08 Final SD phase report including results of SDR & project plans

8 8 Meeting Tracking The tracked version of the action items from each meeting are posted near the top of the meeting page –Meeting 2 http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Keck/NGAO/061114_CIT_NGAO_Meeting_2 http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Keck/NGAO/061114_CIT_NGAO_Meeting_2 –Meeting 3 http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Keck/NGAO/061213_Remote_NGAO_Meeting_3 http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Keck/NGAO/061213_Remote_NGAO_Meeting_3 –Meeting 4 http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Keck/NGAO/070122_NGAO_Meeting_4 http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Keck/NGAO/070122_NGAO_Meeting_4 –Meeting 5 http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Keck/NGAO/070307_Remote_NGAO_Meeting_5 http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Keck/NGAO/070307_Remote_NGAO_Meeting_5 –The bulk of the action items are incomplete –Remember to look at these action items for action items on your presentation (that should be incorporated in the final KAON). The minutes & action items from the EC meetings are posted at http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Keck/NGAO/SystemDesignPhasePlanning http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Keck/NGAO/SystemDesignPhasePlanning

9 9 Posted KAONs 415 TMT site monitoring data (restricted access) 416 Atmospheric sodium density from Keck LGS photometry 417 Sodium abundance data from MAUI Mesosphere 419 Simple models for the prediction of Na LGS brightness & comparison to measured returns from the Gemini & Keck lasers 420 Accessing the MK TMT seeing & weather data 427 Variable vs fixed LGS asterism 428 Implications & requirements for interferometry with NGAO 429 LGS asterism geometry & size 452 MOAO vs MCAO trade study report 455 Science Case Requirements Document v1.0 456 System Requirements Document v1.1 459 NGAO System Design Phase Report #1 461 Wavefront error budget predictions & measured performance for current & upgraded Keck AO 462 Keck AO upgrade trade study 463 Lessons learned on LGS operations: weather impact, efficiency & science ops model 465 NGAO LGS wavefront sensor: Type & number of subapertures trade study 466 Computer simulations of AO PSFs for NGAO 468 An algorithm for reconstruction of Keck Telescope segment figure errors 470 Keck NGAO sky coverage modeling 472 GLAO for non-NGAO Instruments 473 NGAO System Design Phase Report #2 474 AO Photometry for NGAO 475 Tomography codes comparison & validation for NGAO 476 Observing Models trade study

10 10 Reasons for Replan Significantly behind schedule Behind on earned value: 29% of labor & dollars spent, but plan only 24% complete Planned opportunity (scheduled in SEMP) to revisit plan approach, priorities, tasks, personnel, dictionary definitions, etc. We also need to improve how we are managing this project –Schedule and budget are tools in accomplishing the project

11 11 Replan http://www.oir.caltech.edu/twiki_oir/pub/Keck/NGAO/SystemDesignPhasePlanning/NGAO_SD_schedule_v24.mpp

12 12 System Requirements Replan

13 13 Changes made in Replan Excel summary of MS Project changes between versions 20 & 24 posted at http://www.oir.caltech.e du/twiki_oir/pub/Keck/ NGAO/SystemDesignP hasePlanning/NGAO_ SD_schedule_v24.xls http://www.oir.caltech.e du/twiki_oir/pub/Keck/ NGAO/SystemDesignP hasePlanning/NGAO_ SD_schedule_v24.xls Highlights what’s changed.

14 14 Replan Milestones (changes in bold) MILESTONEDATEDESCRIPTION SD SEMP Approved 10/9/06 Approval of this plan by the Directors. Initial SEMP version released to Directors for comment on 9/12 & final version on 9/29/06. SD phase contracts in place 10/27/06 Contracts issued to Caltech & UCSC for the system design phase. Science Requirements Summary v1.0 Release 10/27/06 Initial Release of the Science Requirements as input to trade studies and performance budgeting System Requirements Document (SRD) v1.0 Release 12/8/06 Initial release of System Requirements with emphasis on the science requirements Performance Budgets Summary v1.0 Release 6/15/07 First round of all performance budgets complete & documented SRD v2.0 Release 5/22/07 Second release of System Requirements Doc Trade Studies Complete 6/8/07 All trade studies complete & documented (as a series of Keck Adaptive Optics Notes) SRD v3.0 Release 8/6/07 Third release of System Requirements System Design Manual (SDM) v1.0 Release 9/6/07 First release of System Design Manual Technical Risk Analysis v1.0 Release 9/21/07 First round of project risk analysis complete & documented Cost Review Complete 11/30/07 Project cost estimates complete, documented & internally reviewed SDM v2.0 Release 2/21/08 Second release of System Design Manual System Design Review Package Distributed 3/4/08 SDR documents sent to reviewers System Design Review 3/31/08 SDR meeting SDR Report & Project Planning Presentation at SSC meeting 4/14/08 Final SD phase report including results of SDR & project plans

15 15 Replan

16 16 Budget Reduction in replan labor largely due to removing 1230h of students

17 17 Next Steps Complete Replan with Team’s input –Determine how to proceed with System Architecture –New & revised WBS dictionary definitions –Improved management strategies –More focused team –Redo team meeting goals Complete the following items in May: –SCRD & SRD v2 –FRD v0 & Science Instruments FRD v1 –Performance budgets summary –Trade Studies –Define Candidate Subsystems + Remember to do work scope planning sheets for new tasks