Download presentation
Presentation is loading. Please wait.
1
Tracking Detectors Working Group MICE Collaboration Meeting March 30, 2004 A. Bross
2
Tracker Status Outstanding Issues from Abingdon u Light Yield u Trigger timing u Channel mapping u Dead Channels u Tracking efficiency u Point Set resolution These have now all been resolved
3
Tracking This event is now truly representative of a typical event
4
Light Yield – Tracking Efficiency pT + 3HF (2500 ppm) Corrected for gain variation MP yield = 10.5 - 11 pe u Agrees with extrapolation from D0 Efficiency expected due to Poisson: u 8 PE: 98.62 % u 9 PE: 99.38 % u 10 PE: 99.72 % Efficiency measured (0x350 data): u 5000 ppm 3HF: 98.09 ± 0.39 (stat.) (8.9 pe) u 3500 ppm 3HF: 99.29 ± 0.25 (stat.) (10.3 pe) u 2500 ppm 3HF: 99.73 ± 0.16 (stat.)
5
Point Resolution Subtracting extrapolation error from residual widths (RMS or sigma) gives point resolution (assuming all three X planes have the same resolution). Resolution = 442 ± 4 (stat) ± 27 (syst) m. Depending on definition of the width of one channel (clusters complicate the issue slightly), expected resolution is between 424 and 465 m. Resolution measured in tracker agrees with expectations.
6
Dead Channels For each channel, determine the rate of hits above 4 PE on that channel. Plot rate versus channel number and look for channels that are 0, or very low. No channels with exactly 0 hits, however 1 with a very low rate, and another that is a little lower than its neighbours. Worst case: 2 / 1008 = 0.2% G4MICE assumption is 0.25%
7
Prototype Test Summary The prototype fiber tracker is working well within expectations Light Yield agrees with what was expected from extrapolations from D0 data Dead channel fraction very low Light yield good Tracking efficiency very high and consistent with light yield
8
Progress on Mechanical Design
9
Cryogenics Current plan is to use develop a VLPC cryostat using cryo- cooler u Sumitomo 451D Each tracker would have two cryostats each holding two D0-type cassettes (2048 ch) This arrangement may allow for shorter waveguides – 3m max. u Current prototype – 4m u 13% increase in light yield
10
Integration Issues Specification of tracker mounting inside magnet still being developed Magnetic field monitoring: u Hall probes probably can be sited inside bore u Signal/low voltage cables can be routed through patch panel though their own bulkhead connector u BUT: can monitoring be accomplished using Hall probes outside solenoid bore … simpler and fewer interfaces Diffuser I: u Tilley: place it at ‘start’ of first correction coil u Requires ‘re-entrant’ exit window on upstream tracker Safety Issue was raised u Simultaneous failure of H containment and safety windows could allow tracker volume to fill with H s IMPACT? –Hall probes –Vacuum pump
11
Technical Reference Document All contributions to Saturday have been implemented Require to include missing sections and redraft … Another interation of the tracker section will happen Restart regular phone meetings after the collaboration meeting
12
Cost Capital costs of tracker and associated electronics as discussed in Osaka and FNAL JP staff costs not counted (additional JP contribution) US staff costs appear in ‘loaded’ capital costs UK staff costed separately as required in the UK for reporting
13
Cost Note on contingency: u Capital: s Includes contingency on US staff costs since US staff introduced by ‘loading’ capital cost u Staff: s Includes contingency on UK staff cost only since only UK staff costs explicitly ‘pulled out’ Note on cost saving option: u Construction of new VLPC cassettes ~$1M s Helpful to understand if loan of ‘spare’ D0 realistic s If tentative agreement (hedged with caveats) can be reached US contribution of $1M moves from capital to explicit contingency u Full Electronics costs $1.79M s Tracker costs: approximately $410k
14
Schedule: Note: tracker construction schedule could be advanced if required
15
MICE Stage 1.5 Beam test with Prototype Objective u More Statistics s calibration, efficiency, uniformity u High Rate u Momentum Analysis Target test at KEK Spring 2005
16
KEK π 2 Beam Line
17
Slow extracted u 2 sec Flat top u 10 mm R.M.S Yield of Pion10^5 u 10^5 @ 1 GeV/c u 10^3 @ 0.4 GeV/c BEAM Conditions
18
BESS/Super JACEE Magnet B=1T 1 week life Beam
19
What can we do with Magnet? Momentum Resolution Calibration scheme Tracking in realistic environment u high rate, noise u Also this test allows for test of new tracker station built to final specifications s Impose QC procedures – Not done for current prototype test
20
TPG R&D Hexaboards have been a problem u First – unusable u Second – better, but still problems u Third – expect delivery soon u In addition – external company (with CERN supervision) is making boards u Going to larger pads (and VIAs – the real problem) should improve quality drastically, lower cost since standard PCB process. Full optimization u Take diffusion into effect in order to optimize readout s Do not impose OverKill u Possible cost reductions s In construction s Length of chamber and thus length solenoid
21
TPG front view
22
What’s next for TPG Preamp gain curves Trying to set up a TPG reconstruction “workshop” in Trieste u Implement the combination of projections into space points. u Interface to G4MICE data format. Early June: one week test-beam. Mid July: one week test-beam.
23
Reducing the detector cost? Main components u Field-cage u GEMs and Hexaboard u Electronics u DAQ Is it possible to reduce their cost?
24
So can we save money somewhere else than in the TPG? Diffusion with He-based mixtures can spoil the resolution in the last part of the tracking volume First trials with track fitting show the algorithm can do perfectly well with much fewer points u Simulation and Test-beam can check this Shorter TPG shorter spectrometer magnet less money? What is the cost/m of the solenoid?
25
Tracker Working Group Summary Prototype tracker performance meets all specifications u As expected based on D0 data Mechanical design progressing well u Integration with Solenoid under development Cryo-coolers for VLPC system now baseline u Need “Proof-of-principle” design AS SOON AS POSSIBLE u Geometry allows for shorter WG (+10% increase in LY) Need to develop full QC procedures Planning/preparation for KEK beam test u Second station prototype u QA procedures, connectors etc. u Measurement of basic fibre properties TPG R&D Program continues u Test beam results soon Simulation and reconstruction. u Yagmur’s Talk
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.