© 2006 Atomic Ninja Designs Atomic Ninja Design Presents Advanced Air Vehicles Ted House Veng Lee Jamison Bloechl
2
© 2006 Atomic Ninja Designs Introduction Site Map Prototype Technology and Tools - Development - Deploying and Maintaining Phases
3
© 2006 Atomic Ninja Designs Site Map Link to Site MapSite Map or here http://www.ecst.csuchico.edu/~venglee/WebPageDesignFall06/SiteMap/technicialFlowChart.htm
4
© 2006 Atomic Ninja Designs Prototype Button link Button link
5
© 2006 Atomic Ninja Designs Technology and Tools Popular Browser - IE - Firefox - Avant - Mozilla Notepad Photoshop CS2 Mirage Digital Camera Microsoft Word and FrontPage
6
© 2006 Atomic Ninja Designs Phases Phase #1: October 27, 2006 Task: -Meet with Client to jump start the project. Meeting will be about what the client wants with an estimated quote. (all members will attend the meeting) -Work with Client on logo design Phase #2: October 27, 2006 to October 30, 2006 Completed: -Meeting and agreement with client finalized. Task: -Ted will do additional research on client for additional content. Jamison and Veng will audit the content researched. -Veng and Jamison will Photoshop/Mirage different layouts for potential website theme. -All members will gather ideas on possible navigation/maintenance
7
© 2006 Atomic Ninja Designs Phases cont… Phase #3: October 31, 2006 to November 3, 2006 Completed: -Content completed. -Picked possible layout of website Task: -Progress report 1 -Meet with Client/members to agree on the additional content (all members will attend the meeting). -All three will work on coding and layout of website. (all member will contribute idea) -Assign members task for the weekend: Coding (all members), contents (Ted) and graphics (Jamison and Veng). -Meet at the end of the phase to report progress of task
8
© 2006 Atomic Ninja Designs Phases cont… Phase #4: November 3, 2006 to November 10, 2006 Completed: -Early stage of website. Task: -Auditing on assigned tasks -Assign members task for next meeting. Coding(all members), contents(Ted) and graphics(Jamison and Veng). -meet at the end of the phase to report progress of task Phase #5: November 10, 2006 to November 17 Completed: -Near completed stage of Website Task: -Progress report 2 -Auditing on assigned tasks -Meet at the end of phase to finalize project
9
© 2006 Atomic Ninja Designs Phases cont… Phase #6: November 18, 2006 to Presentation to client/class Completed: -Final Website (not yet audit) Task: -Members will test out website with different browsers -Audit/recoding to finalize Website -Final Present to Client/class
10
© 2006 Atomic Ninja Designs Team Dynamics Team communication -E-mail -Cell phone -Meeting -Instant Messenger Division of team task - Refer to phases
11
© 2006 Atomic Ninja Designs Conclusion Site map (content) is not finalized and will be going through adjustment from research Further improve homepage/prototype design through maintenances Task and deadline is set and on schedule Thanks for your attendance