Pierrick Hanlet MICO June 6, 2011 MICE Operations Manager Report
2
2 June 6, 2011MOM Report Recent Happenings Substation work completed – all circuits ON Decay Solenoid cooldown started on Friday, June 3 Detectors: TOF0, TOF2, and KL installation done TOF1 reinstallation next week – Maurizio and Co. CKOV work & reinstallation starts ~June 17 EMR & group arrive June 13 New Rack installation complete – see Henry’s slides Water rerouting in Hall – John Govans Beam test scheduled for June 13 – 16:30 – 24:00 *** EMR data-taking in JULY User Run – Beam starts June 27 10 May – 9 June 2011: ISIS run 10 June – 12 June 2011: machine physics – pushed back to June 13/14 13 June – 26 June 2011: shutdown – starts now June 15 27 June – 3 July, 4 July: run up, machine physics, and permits 5 July – 4 August 2011: ISIS run 5 August – 7 August 2011: machine physics 8 August – 4 September 2011: shutdown? (subject to change)
3
3 June 6, 2011MOM Report Power Outage in MICE Hall - Finished POWER ON: Status: DAQ machines ON PPS rack OFF Target rack ON DS rack ON Magnet rack ON Network switches ON RAID machines ON ONREC01 & 02 ON OPIPC1, 2 & 3 ON MICESTORE ON Rack Room recovered power – testing remains to be done Power outage issue: Need to know (without doubt) where on distribution board each rack is powered Solution: RACK Power sources will be labeled by Daresbury electrical group POWER ON: MICE Control Room remains powered ON In Hall: Neutron Monitor – back to normal power DS Vacuum pump in DSA – still on extension cord SY527 HV crate – needs to be returned to normal power Some Online Computers remain ON for use by group – everything that was on wall power now back to normal IOCPC1 ON ONREC02 ON ECSERV2 ON IOCPC2 ON ECSERV ON CAGATEWAY ON
4
4 June 6, 2011MOM Report Substation in Hall Complete Power out as of Friday May 13 Finished on schedule – Friday May 27 A few circuits not finished/turned on by Tuesday when power-up started
5
5 June 6, 2011MOM Report Hall Hall supervision under Andy Nichols & Vishal Francis Andy and Vishal are now sending MOM weekly worksheets Water is now re-established Weekly work list to be posted on wall of MLCR Need better communication regarding DL work & contractor work Magnets to be tested after restoration of Hall water Need document to describe water flow management & control PPS will be tested before EMR Run Last hardware needs installation before this can happen New hard hats & hi-vis vests have been brought down to the Hall Are having MICE design painted on them to prevent walk-about
6
6 June 6, 2011MOM Report Other MOM Handover Victoria takes over tomorrow – June 7 Machine Physics Schedule Mtg with ISIS tomorrow morning – 10am EPICs control of Diffuser first pass working MICE server failure of hard disk today – micewww All access to redmine, config DB, Coverity & testing of code now down Software Group work majorly handicapped now Fortunately, micestore had been restored from power outage and a backup exists (still verifying this) Antony is working to recover
7
7 June 6, 2011MOM Report Needs Learn how to use cooling water system Mount the ISIS BLM display monitor in MLCR Water trays in DSA HV 527 system work continues today